Data Center Record.
Census GEOID: 26125 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 1 primary and local source

● Running Announced October 27, 2026 · 2 Buildings · ManagedWay

ManagedWay and 123NET Southfield Data Center (SFJ2 / DC2)

Street address 24275 Northwestern Highway, Southfield, MI 48075, Oakland County verified address Exact, at the address [1] managedway.com

Overview, regulatory gates and specifications

ManagedWay and 123NET operate the SFJ2, DC2, and DC3 commercial colocation campus at 24275 and 24245 Northwestern Highway in Southfield, Oakland County, Michigan. [1] Filings on the record specify disclosed capacity of 8 MW (the developer's figure), 2 planned or operational buildings. [1] Verified facility status from Michigan EGLE permits, MPSC dockets, township planning records, or operator campus specifications. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Not yet on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [1]
8 MW
the developer's figure

Equivalent to ~6,640 U.S. homes (U.S. EIA 830 homes/MW baseline) · 0.4% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
2 buildings
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 24275 Northwestern Highway, Southfield, MI 48075.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
8 MW developer figure Equivalent to the continuous electricity demand of about 6,640 average U.S. homes based on U.S. Energy Information Administration residential consumption data. Less than 0.1 percent (0.078 percent) of New York City's summer peak demand in 2024.
[1] managedway.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
2 buildings operator page
[1] managedway.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2018 (8 years)
Who leads it
ManagedWay as stated by the source
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. ManagedWay and 123NET Southfield Data Center (SFJ2 / DC2), capacity: 8 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 8 ÷ 10,245 = 0.00078 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: ManagedWay · Parent: 123NET
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for ManagedWay and 123NET Southfield Data Center (SFJ2 / DC2).

Field / Parameter Permitted / Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 8 MW 8 MW the developer's figure [1] managedway.com
Site Footprint (Acres)
Data Hall Buildings 2 buildings 2 operator page [1] managedway.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Oakland County and Southfield about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Wixom restrictive Wixom has imposed a moratorium and adopted new zoning rules cbsnews.com (opens in a new tab)
Wixom restrictive Wixom in Oakland County has been sued by developers claiming the moratorium is unlawful michiganindependent.com (opens in a new tab)
Wixom restrictive Wixom implemented a 180 day data center moratorium michiganadvance.com (opens in a new tab)
August 12, 2026 Wixom, MI Wixom City Council moves to regulate data centers with new ordinance Wixom City Council 3 clips

WXYZ TV Detroit | Channel 7 report on Wixom City Council and community proceedings in Wixom, MI: Wixom City Council moves to regulate data centers with new ordinance (August 12, 2026).

  1. WXYZ TV Detroit | Channel 7 Broadcast Report Broadcast Report transcribed from local broadcast report
    "Changing the city's zoning ordinance to specifically regulate data centers. Now, this is a story we've been covering for months. What you're seeing here is aerial video of where the data center would go right along. I-96 in Wixom now the city of breaks and has been developing data center regulation since late 2025 and even adopted a temporary moratorium on city leaders. Study the issue last night council began reviewing proposed changes that would"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "Alicia. Yeah. This data dana center debate took over city council meeting yesterday and it was under the category unfinished business. And I think that's how a lot of that only with some city leaders, but also residents are feeling when it comes to this debate. Now, there is one month left on the six month moratorium when it comes to data center development. And as the clock ticks city council is now released from the time that this rules surrounding data"
  3. WXYZ TV Detroit | Channel 7 Broadcast Report Broadcast Report transcribed from local broadcast report
    "Where can they be located? What qualifies as a data center and what will the city's rules be like with noise coming from cooling systems and even fuel storage. With some industrial one, which is partner with sans one is looking to build a 55 acre 3 building complex currently tree covered area off of Wixom road near pontiac trail. Many people at the meeting, please with city leaders having some guidelines. All of this puts me at ease"
July 14, 2026 Wixom, MI Wixom residents to weigh in on data center ordinance as city council meets Wixom City Council 3 clips

WXYZ TV Detroit | Channel 7 report on Wixom City Council and community proceedings in Wixom, MI: Wixom residents to weigh in on data center ordinance as city council meets (July 14, 2026).

  1. WXYZ TV Detroit | Channel 7 Broadcast Report Broadcast Report transcribed from local broadcast report
    "concerns. Township officials are considering a 12 year tax break for Oracle and Open AI. Well, now in the next hour, the Wixom City Council will consider a proposed data center on Wixom Road near Pontiac Trail, but this would require the council to waive their moratorium on data centers. 7 News Detroit reporter Whitney Bernie is in Wixom, where she found a lot of data center apprehension from the"
  2. WXYZ TV Detroit | Channel 7 Broadcast Report Broadcast Report transcribed from local broadcast report
    "It's a waste of money. It's a waste of water. It's a waste of resources. There are a lot of opinions. I'm worried about the electricity. I'm worried about the low numbers of employees that work at these places. I'm concerned that they're asking for tax breaks already. Absolutely not. Those guys can pay for their own stuff. Take it out there where, you know, where there's space. Arizona, New Mexico, California."
  3. Resident public comment Resident Public Comment transcribed from local broadcast report
    "worked to draft an ordinance specifically regulating data centers. As the countdown ticks down for that 6 month moratorium to expire, City Council is set to hear what could be included in that legislation at their meeting Tuesday. So, people will have the opportunity at this meeting to make that public comment and give feedback to council about what they think about the ordinance amendment or about what they think ought to be done. City Manager Steve Brown says the council will also consider lifting the"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on October 27, 2026 (the day the page was read; it gives no date of its own)

    Verified facility status from Michigan EGLE permits, MPSC dockets, township planning records, or operator campus specifications.

    [1] managedway.com

Nearest data centers in Michigan

Verified data center records in Michigan within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
123NET Southfield Data Center Campus (DC1) Southfield, Oakland County Less than 1 mi Running 123NET 10 MW
365 Data Centers Detroit (DT1) Southfield, Oakland County 1 mi Running 365 Data Centers 4 MW
EdgeConneX Detroit Data Center (DET01) Southfield, Oakland County 2 mi Running EdgeConneX 8 MW
Liberty Center One Royal Oak Data Center Royal Oak, Oakland County 5 mi Running Liberty Center One 4 MW
ManagedWay Troy Data Center (TYM1) Troy, Oakland County 8 mi Running ManagedWay 5 MW
Otava Metro Detroit Data Center (Westland) Westland, Wayne County 13 mi Running Otava 6 MW

Blank cell: not disclosed by any source on file.

Common questions about ManagedWay and 123NET Southfield Data Center (SFJ2 / DC2)

Answered directly from the verified filings and local actions on this page.

Who is building ManagedWay and 123NET Southfield Data Center (SFJ2 / DC2)?

ManagedWay is the developer. No construction contractor is named on the record yet.

How much power and water does ManagedWay and 123NET Southfield Data Center (SFJ2 / DC2) say it needs?

Power: 8 MW (the developer's figure, managedway.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does ManagedWay and 123NET Southfield Data Center (SFJ2 / DC2) stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

What has Southfield or Oakland County decided about it?

Wixom (rated restrictive): Wixom has imposed a moratorium and adopted new zoning rules (reported October 7, 2026, cbsnews.com (opens in a new tab)); and Wixom: Wixom in Oakland County has been sued by developers claiming the moratorium is unlawful (reported October 1, 2026, michiganindependent.com (opens in a new tab)). 3 events are on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. ManagedWay and 123NET Southfield Data Center (SFJ2 / DC2) Official Disclosure (opens in a new tab), ManagedWay / 123NET, news outlet

1 source on file.

Regional grid context

This site is in the RFC Michigan (RFCM) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "ManagedWay and 123NET Southfield Data Center (SFJ2 / DC2)", https://datacenterrecord.org/projects/managedway-sfj2-southfield-mi, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "ManagedWay and 123NET Southfield Data Center (SFJ2 / DC2)", https://datacenterrecord.org/projects/managedway-sfj2-southfield-mi. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
42.467029, -83.234962
How the location is known
Location from the site's street address.
Location source
https://www.managedway.com/data-centers/
Coordinate source
ManagedWay SFJ2 and 123NET DC2/DC3 specification
How capacity was disclosed
the developer's figure
Capacity, if disclosed
8 MW, the developer's figure
Rating of the county's rows
Restrictive
Published
October 21, 2026
Last verified
October 27, 2026
Not disclosed
Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection

Researcher view · ManagedWay and 123NET Southfield Data Center (SFJ2 / DC2) · 1 source, 1 entry, 3 decisions nearby · basis and source tier on every row · verified October 27, 2026

Download CSV JSON