Census GEOID: 39089 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 2 primary sources

● Running First recorded September 14, 2026 · 1 Building

Microsoft Heath datacenter

Street address 1600 Dorsey Mill Rd, Heath, OH 43056, Licking County verified address Exact, at the address Microsoft Ohio Datacenter Community hub for Heath (Dorsey Mill Rd), Licking County, Ohio. (opens in a new tab)

Overview, regulatory gates and specifications

Microsoft lists a data center at Heath, Ohio among the sites it operates. [1] Filings on the record specify 1 planned or operational building. [1] Microsoft lists Microsoft Heath datacenter at Heath, Ohio on its own page of data center locations, read September 14, 2026. [2]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Not yet on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
1 building
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 1600 Dorsey Mill Rd, Heath, OH 43056.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
1 building operator page
local.microsoft.com (opens in a new tab)
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2025 (1 year)
Who leads it
Microsoft as stated by the source
Official project website
local.microsoft.com (opens in a new tab) verified October 28, 2026
local.microsoft.com (opens in a new tab)
Archived promotional websites
local.microsoft.com (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Microsoft
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Microsoft Heath datacenter.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings 1 building 1 operator page
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

September 9, 2026 Johnstown, OH Licking County communities push for special elections on data centers Licking County Board of Commissioners 3 clips

NBC4 Columbus report on Licking County Board of Commissioners and community proceedings in Johnstown, OH: Licking County communities push for special elections on data centers (September 9, 2026).

  1. NBC4 Columbus Broadcast Report Broadcast Report transcribed from local broadcast report
    "residents and Johnstown City officials missed last Friday's deadline to get questions on November ballots. Nbc 4 s Gracie Collins covers data centers for us and tells us what's next in Licking County. Residents here in Johnstown and he had the goal getting a data center ban on November ballots. And even though that's not happening. They're not giving up on citizens having a say and we were pushing for an opportunity"
  2. NBC4 Columbus Broadcast Report Broadcast Report transcribed from local broadcast report
    "Charters. Which could lead to banning data centers using over. 25 megawatts of power to huge tax on our infrastructure. Specifically electricity, water. You know, the management of our roads. But Heath in Johnstown, that effort did not make it in time to get on ballots. The Heath law director tells me residents submitted 2 petitions neither having enough signatures."
  3. NBC4 Columbus Broadcast Report Broadcast Report transcribed from local broadcast report
    "enough signatures. But Mayor Tiffany Hollis says council wasn't given enough time to certify the petition. Receiving it 2 days before the deadline, City Council wasn't able to do what they needed to do in 48 hours. So this special election is a byproduct of their inaction. Resident Brenda Charles says she hopes a special election results in more transparency and information about the rapid"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Microsoft lists Microsoft Heath datacenter at Heath, Ohio on its own page of data center locations, read September 14, 2026.

    [2] local.microsoft.com

Nearest data centers in Ohio

Verified data center records in Ohio within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Microsoft Hebron datacenter Hebron, Licking County 4 mi Running Microsoft 1 building
Meta New Albany Data Center New Albany, Franklin County 17 mi Running Meta 5 buildings
Google New Albany data center New Albany, Franklin County 17 mi Running Google 3 buildings
Microsoft New Albany datacenter New Albany, Franklin County 18 mi Running Microsoft 1 building
Vantage New Albany New Albany, Franklin County 18 mi Running Vantage Data Centers 2 buildings
STACK NAL01 New Albany, Franklin County 18 mi Running STACK Infrastructure 2 buildings

Blank cell: not disclosed by any source on file.

Common questions about Microsoft Heath datacenter

Answered directly from the verified filings and local actions on this page.

Who is building Microsoft Heath datacenter?

Microsoft is the developer. No construction contractor is named on the record yet.

How much power and water does Microsoft Heath datacenter say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Microsoft Heath datacenter stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Microsoft: Microsoft datacenter communities (opens in a new tab), Microsoft, September 14, 2026
  2. Microsoft: Microsoft Heath datacenter (opens in a new tab), Microsoft, September 14, 2026

2 sources on file.

Regional grid context

This site is in the RFC West (RFCW) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Microsoft Heath datacenter", https://datacenterrecord.org/projects/microsoft-heath-datacenter-oh, last verified October 25, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Microsoft Heath datacenter", https://datacenterrecord.org/projects/microsoft-heath-datacenter-oh. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
reviewed in depth
Tags
Reviewed in depth
Coordinates
40.0085, -82.432
How the location is known
Location from the site's street address.
Location source
Microsoft Ohio Datacenter Community hub for Heath (Dorsey Mill Rd), Licking County, Ohio.
Coordinate source
operator address point
Location last verified
September 14, 2026
Published
September 14, 2026
Last verified
October 25, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Microsoft Heath datacenter · 2 sources, 1 entry · basis and source tier on every row · verified October 25, 2026