Google Prince William County data center

Street address 13001 Rollins Ford Road, Bristow, VA 20136, Prince William County verified address Exact, at the address [1] County seat (Manassas), Wikidata, placed at county level

Overview, regulatory gates and specifications

Google lists a data center at Prince William County, Virginia among the sites it operates. [1] Filings on the record specify 2 planned or operational buildings. [1] Google lists Google Prince William County data center at Prince William County, Virginia on its own page of data center locations, read September 14, 2026. [2]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
6 generators permitted
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water [3]
129,315 gal/day
measured

Equivalent to ~431 U.S. households (U.S. EPA 300 gal/day household baseline).

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
2 buildings
Disclosed building count

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 13001 Rollins Ford Road, Bristow, VA 20136.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
47,200,000 gallons a year (withdrawal) permitted Equivalent to the annual water use of about 431 average U.S. households based on the U.S. Environmental Protection Agency baseline of 109,500 gallons per year per home, or about 72 Olympic size swimming pools of 660,000 gallons each. What at most 431 American families use at home, at the EPA's more than 300 gallons a family a day (the EPA gives no year for it).
[3] sustainability.google
Land area
Not disclosed
Buildings
2 buildings permitted
[1] deq.virginia.gov
Backup generators
6 generators (9.88 MW) permitted
[1] deq.virginia.gov
Capital investment
Not disclosed
Commissioned
Operational since 2020 (6 years)
Who leads it
Google attributed via corporate HQ or property filing
[2] datacenters.google
Permitted legal entity
Nova Mango Farms LLC what a permit allows
[1] deq.virginia.gov [1] deq.virginia.gov
State air permit registration
74216 state air permit register
[1] deq.virginia.gov
Official project website
datacenters.google (opens in a new tab) verified October 28, 2026
datacenters.google (opens in a new tab)
Archived promotional websites
datacenters.google (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Google Prince William County data center, water: 47,200,000 gallons a year.
  2. 47,200,000 gallons a year ÷ 365 = 129,315 gallons a day.
  3. Water used at home each day by the average American family, more than: 300 gallons a day.
  4. 129,315.07 ÷ 300 = 431.05 (gallons a day over gallons a day).

Sources:

The two count different water: the data center figure is water withdrawn from its source, and the EPA's is water used at home, which the EPA does not split into water consumed and water returned.

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Google · Parent: Alphabet · Applicant / Shell LLC: Nova Mango Farms LLC
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Google Prince William County data center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings 2 buildings 2 Site filing [1] deq.virginia.gov
Cooling & Water System 47,200,000 gal/yr measured [3] sustainability.google
Backup Diesel / Gas Generators 6 units (9.88 MW) what a permit allows [1] deq.virginia.gov
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

2025 to 2026 hearings
September 22, 2026 Prince William County, VA Prince William Board of County Supervisors Data Center Overlay Vote Prince William Board of County Supervisors 3 clips

The Prince William Board of County Supervisors voted unanimously to repeal automatic by right data center zoning approvals inside the Data Center Opportunity Overlay District, requiring a Special Use Permit and public hearing for every future project.

  1. NBC4 Washington Broadcast Report Broadcast Report transcribed from local broadcast report
    "when the county was eager to expand its data center footprint, a previous Board of supervisors created what it called a data center opportunity overlay, which is a long, fancy name that basically says, here's an area of the county that we think data centers should go. And as long as these data center developers meet a certain set of criteria, they can just go ahead and build there. They don't need special approval from the Board"
  2. Deshundra Jefferson, Chair, Prince William Board of County Supervisors Elected Official transcribed from local broadcast report
    "local government stuff. That basically means data centers are still allowed to develop in Prince William County, but they can't just build in that area anymore without being scrutinized at the county level. Now, every new data center in Prince William County will have to come before the Board of Supervisors, which the board chair thinks is a much more transparent approach to addressing this type of development. These data center developers will need a special use permit if they want to"
  3. NBC4 Washington Broadcast Report Broadcast Report transcribed from local broadcast report
    "done extensive reporting on data centers. He explains what this means for any new development in the county. The change in Prince William County is significant, and it really reflects a massive shift in the county's posture and how it's going to address data center development. And it feels pretty reflective of the public sentiment on data centers and how that's been changing over the last decade. To explain what changed in Prince William"
2019 to 2024 hearings
December 13, 2023 Woodbridge, VA Prince William County Board greenlights controversial data center project Prince William Board of County Supervisors 3 clips

Prince William Board of County Supervisors marathon 27 hour public hearing and vote approving the 2,100 acre Prince William Digital Gateway rezoning (December 13, 2023).

  1. Woodbridge Economic Development and Applicant Presentation Developer Representative transcribed from local broadcast report
    "feet of data centers now at its core this has turned into a bait about preserving Green Space versus development while some say this complex could provide crucial tax dollars others share their concerns about environmental concerns and are asking for more research on how this could impact water quality for hundreds of thousands of families opponents also worry about its location near the Manassas Civil War battlefield I don't know where to begin"
  2. WUSA9 Broadcast Report Broadcast Report transcribed from local broadcast report
    "together blah blah blah blah you saw that even the board members aren't even talking to each other they weren't even Consulting each other and you saw that display up there they're doing a disservice to all of us I have no confidence at all how many of you are willing to give up your phones and computers and cars to keep buildings from being built on Pageland these days giving up a phone is like giving a limb too many"
  3. Resident public comment Resident Public Comment transcribed from local broadcast report
    "water quality but those who are affected next to us now the County Board of Supervisors voted five to two to move forward with this plan as for what happens next Larry we know the rezoning applications are now in the planning process at that point it will then move to the board of County Supervisors for a final vote again this is a topic that has a lot of people talking all night long Larry all"
December 22, 2021 Woodbridge, VA Land Use Chapter Update of Prince William County’s Comprehensive Plan Prince William Board of County Supervisors 3 clips

Prince William Board of County Supervisors November 2022 public hearing approving the Comprehensive Plan amendment for the Pageland Lane data center corridor (December 22, 2021).

  1. Woodbridge Economic Development and Applicant Presentation Developer Representative transcribed from the official recording
    "and innovation while providing equal access to a variety of jobs that pay living wages and career training opportunities for advancement inclusive community embracing the vibrant cultural and ethnically diverse population that makes our community distinct while creating conditions through an equity lens that allow all participants to reach their full potential"
  2. Prince William Board of County Supervisors Member Elected Official transcribed from the official recording
    "the washington metropolitan council of governments has identified several key regional activity centers that serve as urban centers transit hubs and regional employment centers we have broken the county down into three different distinct groups the first is regional activity center which will accommodate most of our future growth as we move forward on our pathway to 2040."
  3. Resident public comment Resident Public Comment transcribed from the official recording
    "centers or proposed data centers within the activity center some of the key policies for the southerly road corridor include encouraging the redevelopment of the older strip commercial uses with compact mixed use that integrates new housing options and neighborhoods serving commercial uses prioritizing the redevelopment of the nasa small site as a catalyst for"
Said and filed

Said and filed

Statements and filings, side by side

Column A · Dated Statement
Deshundra Jefferson & Prince William Board of County Supervisors Chair, Prince William Board of County Supervisors
Venue: Prince William County Data Center Opportunity Overlay Policy Record
"Established the 2016 Data Center Opportunity Overlay District allowing data center campuses inside designated overlay zones to be approved by right through administrative site plan review without individual Special Use Permit hearings."
Prince William County Broadcast Record
Column B · Subsequent Recorded Position
Prince William Board of County Supervisors Unanimous 8 to 0 Vote Stripping By Right Approvals in Data Center Overlay District
Prince William County Zoning Text Amendment · September 22, 2026 (Unanimous 8 to 0 Vote)
Agency or Venue: Prince William Board of County Supervisors
"In a unanimous 8 to 0 vote on September 22, 2026, Chair Deshundra Jefferson and the Prince William Board of County Supervisors repealed automatic by right approvals in the Data Center Opportunity Overlay District, shrinking the overlay from 9,698 acres to 3,641 acres and requiring a Special Use Permit and public hearing for every future data center."
Prince William County Broadcast Record
Column A · Dated Statement
Ann Wheeler Chair at Large, Prince William Board of County Supervisors
Venue: Prince William Board of County Supervisors 27 Hour Public Hearing
"Approving the 2,100 acre Prince William Digital Gateway rezoning along Pageland Lane will secure $400 million in annual commercial tax revenue to fund county schools and reduce the residential real estate tax burden while maintaining strict environmental buffers."
Column B · Primary Government Record
Prince William Circuit Court Void Ab Initio Ruling and September 2026 Board Repeal of By Right Data Center Overlay
Prince William Circuit Court Void Ab Initio Order · BOCS Sept 2026 5 to 3 Repeal Vote
Agency or Venue: Prince William County Circuit Court and Board of County Supervisors
"A Prince William County Circuit Court judge voided the December 2023 Digital Gateway rezoning ab initio for unlawful public notice; QTS withdrew its appeal in July 2026, and in September 2026 the newly elected Board of County Supervisors voted 5 to 3 to strip by right data center approvals from the Data Center Opportunity Zone Overlay."

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. · Status: running (content date)

    Virginia DEQ issued a minor New Source Review air permit (Article 6, 9VAC5-80) to Nova Mango Farms LLC, registration 74216 (permit action 74216-4), Prince William County, on February 27, 2024. The permit action supersedes the earlier permit action dated April 11, 2023. The permit document authorizes 6 emergency backup generators totaling 9.88 MW of permitted backup generator rating at 13001 Rollins Ford Road, Bristow, VA 20136.

    [1] deq.virginia.gov

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Google lists Google Prince William County data center at Prince William County, Virginia on its own page of data center locations, read September 14, 2026.

    [2] datacenters.google

Nearest data centers in Virginia

Verified data center records in Virginia within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Digital Third Second Manassas, LLC & Digital Carver Brickyard, LLC Manassas, Prince William County Less than 1 mi Proposed Digital Realty
CloudHQ - Cashvad Ventures LLC Manassas, Manassas City Less than 1 mi Proposed CloudHQ
Amazon Data Services (IAD-130, IAD-131, IAD-313 and DCA-072) Manassas, Prince William County Less than 1 mi Proposed Amazon Web Services
Amazon Data Services Inc IAD-45 Manassas, Prince William County Less than 1 mi Proposed Amazon Web Services
Amazon Data Services, Inc. IAD-7 IAD-11 IAD-24 Manassas, Prince William County Less than 1 mi Proposed Amazon Web Services
Amazon Data Services Inc IAD-205/307/317/612/612x Manassas, Manassas City Less than 1 mi Proposed Amazon Web Services

Blank cell: not disclosed by any source on file.

Common questions about Google Prince William County data center

Answered directly from the verified filings and local actions on this page.

Who is building Google Prince William County data center?

Google is the developer, datacenters.google (opens in a new tab). No construction contractor is named on the record yet.

How much power and water does Google Prince William County data center say it needs?

Power: not disclosed by any source on file. Water: 47,200,000 gallons a year (withdrawal) (measured, sustainability.google (opens in a new tab)).

Where does Google Prince William County data center stand today?

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Virginia DEQ Air Permit 74216-4: Nova Mango Farms LLC (Nova Mango Farms LLC) (opens in a new tab), Virginia Department of Environmental Quality, February 27, 2024
  2. Google: Data center locations (opens in a new tab), Google, September 14, 2026
  3. Google 2026 Environmental Report (Page 97: Water use by data center location, Prince William County, VA) (opens in a new tab), Google

3 sources on file.

Regional grid context

This site is in the SERC Virginia and Carolina North (SRVC-N) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Google Prince William County data center", https://datacenterrecord.org/projects/google-prince-william-county-data-center-va, last verified November 6, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Google Prince William County data center", https://datacenterrecord.org/projects/google-prince-william-county-data-center-va. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
reviewed in depth
Tags
Reviewed in depth
Coordinates
38.75142, -77.4764
How the location is known
Location from the site's street address.
Location source
County seat (Manassas), Wikidata, placed at county level
Coordinate source
wikidata county seat
Location last verified
September 16, 2026
How water was disclosed
measured
Published
September 14, 2026
Last verified
November 6, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Google Prince William County data center · 3 sources, 2 entries · basis and source tier on every row · verified November 6, 2026