● Proposed Campus Announced June 24, 2026 · Digital Realty

Digital Third Second Manassas, LLC & Digital Carver Brickyard, LLC

Street address 9905 Godwin Drive and 10050 and 10051 Brickyard Way, Manassas, Virginia 20110, Prince William County city centroid Town level, the center of the city [1] deq.virginia.gov

Overview, regulatory gates and specifications

Virginia DEQ issued a minor New Source Review air permit (Article 6, 9VAC5-80) to Digital Third Second Manassas, LLC and Digital First Manassas, LLC, registration 74262 (permit action 74262-4), Prince William County, on June 24, 2026. The permit action supersedes the earlier permit action dated September 20, 2024. The permit document authorizes 266 emergency backup generators totaling 789.25 MW of permitted backup generator rating at 9905 Godwin Drive and 10050 and 10051 Brickyard Way, Manassas, Virginia 20110. [1]

Verified Site & Permit Summary
Verified address
9905 Godwin Drive and 10050 and 10051 Brickyard Way, Manassas, Virginia 20110, Prince William County city centroid
Operator / developer
Digital Realty
Permit / registry ID
undefined: undefined [1]

How much power it needs, how much water it would use and who would use it have not been disclosed.

What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
Not disclosed
Backup generators
266 generators (789.25 MW) permitted
[1] deq.virginia.gov
Capital investment
Not disclosed
Who leads it
Digital Realty attributed via corporate HQ or property filing
[2] digitalrealty.com
Permitted legal entity
Digital Third Second Manassas, LLC and Digital First Manassas, LLC what a permit allows
[1] deq.virginia.gov [1] deq.virginia.gov
State air permit registration
74262 state air permit register
[1] deq.virginia.gov
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Digital Realty · Applicant / Shell LLC: Digital Third Second Manassas, LLC and Digital First Manassas, LLC
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Digital Third Second Manassas, LLC & Digital Carver Brickyard, LLC.

Field / Parameter Permitted / Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings
Cooling & Water System
Backup Diesel / Gas Generators 266 units (789.25 MW) what a permit allows [1] deq.virginia.gov
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Prince William County and Manassas about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Prince William County restrictive Prince William County Board of Supervisors approved changes ending by right data center development and shrinking Data Center Opportunity Zone Overlay District from 9,698 acres to 3,641 acres commercialobserver.com (opens in a new tab)
Prince William County restrictive Supervisors approved 90 day transition period for properties within overlay, rejecting motion to eliminate grace period entirely. patch.com (opens in a new tab)
Prince William County restrictive Prince William County Board of Supervisors voted unanimously to reduce Data Center Opportunity Zone Overlay District from 9,700 acres to 3,650 acres, eliminating by right development outside the overlay and requiring special use permits. patch.com (opens in a new tab)
Prince William County restrictive Property owners have 90 days to file certain data center related applications to remain in the reduced district virginiabusiness.com (opens in a new tab)
Prince William County restrictive Data Center Opportunity Zone Overlay District expected to shrink from about 9,700 acres to roughly 3,641 acres virginiabusiness.com (opens in a new tab)
Prince William County restrictive Prince William County Board of Supervisors voted unanimously to eliminate automatic approvals and data center opportunity overlay district, requiring special use permits and public hearings for all future data center projects nbcwashington.com (opens in a new tab)
20 earlier decisions on the county's rows
DateWhoDecisionSource
Prince William County restrictive Planning Commission set to consider 120 day grace period and 500 foot setback buffer proposal, with November public hearing targeted wtop.com (opens in a new tab)
Prince William County restrictive Future data center projects will require special use permit instead of by right development wtop.com (opens in a new tab)
Prince William County restrictive Amendment established 90 day grace period for data centers with approved site plans or already built or under construction wtop.com (opens in a new tab)
Prince William County restrictive Prince William Board of County Supervisors voted 8 to 0 to approve zoning text amendment ending by right data center development countywide wtop.com (opens in a new tab)
Prince William County restrictive The Planning Commission is aiming for a November 2026 public hearing on setback proposal, with a board hearing targeted for January 2027 rappnews.com (opens in a new tab)
Prince William County restrictive The amendment includes a 90 day grace period for qualifying projects already built or being built in the county, as well as those already with a site plan that has passed the quality control threshold rappnews.com (opens in a new tab)
Prince William County restrictive The overlay district allows data centers to be built by right within its parameters; the countywide amendment will drastically shrink the size and scope of the overlay from its originally adopted form which dates back over a decade to May 2016 rappnews.com (opens in a new tab)
Prince William County restrictive Planning commission recommended a 120 day grace period for developers; supervisors were also considering eliminating the grace period entirely. patch.com (opens in a new tab)
Prince William County restrictive Prince William County Board of Supervisors is expected to vote on zoning changes to restrict by right data center development, shrinking the Data Center Opportunity Zone Overlay District. patch.com (opens in a new tab)
Prince William County restrictive Prince William County Board of Supervisors voted unanimously Tuesday to shrink the Data Center Opportunity Zone Overlay District virginiabusiness.com (opens in a new tab)
Prince William County restrictive Prince William Board of County Supervisors voted 8 to 0 on September 22, 2026 to end by right data center development countywide, requiring special use permits for future projects rappnews.com (opens in a new tab)
Prince William County restrictive Several high profile projects in Prince William County were recently halted due to sustained community opposition ground.news (opens in a new tab)
Prince William County restrictive Prince William County will vote to repeal zoning rules for one area of the county where data centers can be built without approval nbcwashington.com (opens in a new tab)
Prince William County restrictive Supervisors voted 8 to 0 to reject a comprehensive plan amendment for Dulles South Innovation Center, a proposed campus covering about 1,940 acres with 43 million square feet of data center space theminermag.com (opens in a new tab)
Prince William County restrictive A circuit judge invalidated rezonings for Prince William Digital Gateway in August 2025 and an appeals court upheld the result in March 2026 theminermag.com (opens in a new tab)
Prince William County restrictive Planning Commission recommended a 500 foot separation from existing homes and schools for projects qualifying through the transition provision theminermag.com (opens in a new tab)
Prince William County restrictive Planning Commission recommended extending the eligibility window from 90 to 120 days after adoption on September 9 theminermag.com (opens in a new tab)
Prince William County restrictive Prince William County supervisors scheduled for September 22 to consider restrictions that would subject more data center projects to individual review theminermag.com (opens in a new tab)
Prince William County restrictive Prince William dissolved the resident Data Center Ordinance Advisory Group and adopted a different measurement approach with advisory standards virginiamercury.com (opens in a new tab)
Prince William County restrictive Prince William County's Data Center Ordinance Advisory Group raised noise standards by 6 decibels over consultant recommendations virginiamercury.com (opens in a new tab)

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. · Status: permitting (content date)

    Virginia DEQ issued a minor New Source Review air permit (Article 6, 9VAC5-80) to Digital Third Second Manassas, LLC and Digital First Manassas, LLC, registration 74262 (permit action 74262-4), Prince William County, on June 24, 2026. The permit action supersedes the earlier permit action dated September 20, 2024. The permit document authorizes 266 emergency backup generators totaling 789.25 MW of permitted backup generator rating at 9905 Godwin Drive and 10050 and 10051 Brickyard Way, Manassas, Virginia 20110.

    [1] deq.virginia.gov

Every event in order

Nearest data centers in Virginia

Verified data center records in Virginia within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
CloudHQ - Cashvad Ventures LLC Manassas, Manassas City Less than 1 mi Proposed CloudHQ
Amazon Data Services (IAD-130, IAD-131, IAD-313 and DCA-072) Manassas, Prince William County Less than 1 mi Proposed Amazon Web Services
Amazon Data Services Inc IAD-45 Manassas, Prince William County Less than 1 mi Proposed Amazon Web Services
Amazon Data Services, Inc. IAD-7 IAD-11 IAD-24 Manassas, Prince William County Less than 1 mi Proposed Amazon Web Services
Amazon Data Services Inc IAD-205/307/317/612/612x Manassas, Manassas City Less than 1 mi Proposed Amazon Web Services
Amazon Data Services, Inc. IAD-75 IAD-85 IAD-95 IAD-96 Manassas, Prince William County Less than 1 mi Proposed Amazon Web Services

Blank cell: not disclosed by any source on file.

Common questions about Digital Third Second Manassas, LLC & Digital Carver Brickyard, LLC

Answered directly from the verified filings and local actions on this page.

Who is building Digital Third Second Manassas, LLC & Digital Carver Brickyard, LLC?

Digital Realty is the developer, digitalrealty.com (opens in a new tab). No construction contractor is named on the record yet.

How much power and water does Digital Third Second Manassas, LLC & Digital Carver Brickyard, LLC say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Digital Third Second Manassas, LLC & Digital Carver Brickyard, LLC stand today?
What has Manassas or Prince William County decided about it?

Prince William County (rated restrictive): Prince William County Board of Supervisors approved changes ending by right data center development and shrinking Data Center Opportunity Zone Overlay District from 9,698 acres to 3,641 acres (reported September 23, 2026, commercialobserver.com (opens in a new tab)); and Prince William County: Supervisors approved 90 day transition period for properties within overlay, rejecting motion to eliminate grace period entirely (reported September 23, 2026, patch.com (opens in a new tab)). 26 events are on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Primary documents

  1. Virginia DEQ Air Permit 74262-4: Digital Third Second Manassas, LLC & Digital Carver Brickyard, LLC (Digital Third Second Manassas, LLC and Digital First Manassas, LLC) (opens in a new tab), Virginia Department of Environmental Quality, June 24, 2026

Reporting

  1. Digital Realty corporate address and property attribution for Digital Third Second Manassas, LLC and Digital First Manassas, LLC (opens in a new tab), Digital Realty, June 24, 2026, news outlet

2 sources on file.

Regional grid context

This site is in the SERC Virginia and Carolina North (SRVC-N) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Digital Third Second Manassas, LLC & Digital Carver Brickyard, LLC", https://datacenterrecord.org/projects/digital-third-second-manassas-and-digital-first-prince-william-74262-va, last verified June 24, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Digital Third Second Manassas, LLC & Digital Carver Brickyard, LLC", https://datacenterrecord.org/projects/digital-third-second-manassas-and-digital-first-prince-william-74262-va. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
built from one source
Tags
Built from one source
Coordinates
38.7509, -77.4753
How the location is known
Location is the city center; exact site not disclosed.
Location source
https://www.deq.virginia.gov/home/showpublisheddocument/37093/639185072674230000
Coordinate source
city centroid
Location last verified
October 26, 2026
Rating of the county's rows
Restrictive
Published
November 1, 2026
Last verified
June 24, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed

Researcher view · Digital Third Second Manassas, LLC & Digital Carver Brickyard, LLC · 2 sources, 1 entry, 26 decisions nearby · basis and source tier on every row · verified June 24, 2026

Download CSV JSON