Land Use Chapter Update of Prince William County’s Comprehensive Plan
Prince William Board of County Supervisors November 2022 public hearing approving the Comprehensive Plan amendment for the Pageland Lane data center corridor (December 22, 2021).
Privacy enhanced player · zero third party requests until clicked
Land Use Chapter Update of Prince William County’s Comprehensive Plan
Prince William Board of County Supervisors · December 22, 2021
Timestamped Speaker & Testimony Ledger
3 verified timestamped clips extracted chronologically from the closed caption record. Select any clip to play that exact window in the master player or copy a canonical clip link.
- Clip 1 · 4:00 Woodbridge Economic Development and Applicant Presentation Developer Representative In support auto captions, uncheckedTax Abatements Water Power & Grid Zoning
Developer representatives and economic development officials pitch capital investment, jobs, tax agreements, and utility infrastructure before Prince William Board of County Supervisors.
"and innovation while providing equal access to a variety of jobs that pay living wages and career training opportunities for advancement inclusive community embracing the vibrant cultural and ethnically diverse population that makes our community distinct while creating conditions through an equity lens that allow all participants to reach their full potential"
- Clip 2 · 9:03 Prince William Board of County Supervisors Member Elected Official In support auto captions, uncheckedTax Abatements Water Power & Grid Zoning
Prince William Board of County Supervisors members review zoning, tax abatement terms, water allocation, and grid capacity during the approval proceedings.
"the washington metropolitan council of governments has identified several key regional activity centers that serve as urban centers transit hubs and regional employment centers we have broken the county down into three different distinct groups the first is regional activity center which will accommodate most of our future growth as we move forward on our pathway to 2040."
- Clip 3 · 19:17 Resident public comment Resident Public Comment auto captions, unchecked
Public commenters and local stakeholders raise questions regarding municipal water draw, tax revenue exemptions, power transmission, and long term community impacts.
"centers or proposed data centers within the activity center some of the key policies for the southerly road corridor include encouraging the redevelopment of the older strip commercial uses with compact mixed use that integrates new housing options and neighborhoods serving commercial uses prioritizing the redevelopment of the nasa small site as a catalyst for"
Using this data in a report? Support the record.