Data Center Record.
Census GEOID: 13077 Location Precision: assessor parcel Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 2 primary and local sources

● Proposed Campus Announced April 28, 2026 · 10 Buildings · Bridgeport Revised Development Applicant

Bridgeport Technology Park Data Center Campus (Coweta County, DRI #4727)

Street address 0 Bridgeport Pkwy, Newnan, Coweta County, GA 30265 assessor parcel Exact, on the parcel [2] apps.dca.ga.gov

Overview, regulatory gates and specifications

Georgia DCA DRI #4727 (Bridgeport Revised) was filed on April 28, 2026 for an 8,250,000 square foot data center campus requesting up to 1,500 MW along Bridgeport Parkway in Coweta County. [1] Filings on the record specify 10 planned or operational buildings. [1] On the regulatory record, state permit status is Georgia DCA DRI #4727 regional review filing. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
In local review
3. Tax & EDA Deal
$30,000,000/yr stated
4. Utility Grid Queue
1.5 GW disclosed
5. Air & Water Permits
Georgia DCA DRI #4727 region
What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.
Electricity Demand [1]
1.5 GW
the developer's figure

Equivalent to ~1,245,000 U.S. homes (U.S. EIA 830 homes/MW baseline) · 72% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water [1]
500,000 gal/day
the developer's figure

Equivalent to ~1,667 U.S. households (U.S. EPA 300 gal/day household baseline).

Stated annual local tax revenue: $30,000,000.

Site & Buildings [2]
10 buildings
Georgia DCA DRI Initial Form

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 0 Bridgeport Pkwy, Newnan, Coweta County, GA 30265.

Taxes & Permanent Jobs [1]
$30,000,000/yr
the developer's figure

200 permanent on site jobs disclosed.

Stated annual local tax revenue: $30,000,000.

Key specifications on the record

Power capacity
1.5 GW developer figure Equivalent to the continuous electricity demand of about 1,245,000 average U.S. homes based on U.S. Energy Information Administration residential consumption data, or about 0.7 times the 2,080 MW generating capacity of Hoover Dam. About 0.15 times New York City's summer peak demand in 2024.
apps.dca.ga.gov (opens in a new tab)
Water usage
500,000 gallons a day (withdrawal) developer figure Equivalent to the daily water use of about 1,670 average U.S. households based on the U.S. Environmental Protection Agency baseline of 300 gallons per day per home. What at most 1,667 American families use at home, at the EPA's more than 300 gallons a family a day (the EPA gives no year for it).
apps.dca.ga.gov (opens in a new tab)
Land area
Not disclosed
Buildings
10 buildings permitted
[2] apps.dca.ga.gov
Backup generators
Not disclosed
Capital investment
Not disclosed
Who leads it
Bridgeport Revised Development Applicant as stated by the source
[1] apps.dca.ga.gov
Jobs once it runs
200 the developer's figure
Tax each year
$30,000,000 the developer's figure
Permitted legal entity
Bridgeport Revised Development Applicant the developer's figure
[2] apps.dca.ga.gov
State air permit registration
Georgia DCA DRI #4727 state air permit register
State permit status
Georgia DCA DRI #4727 regional review filing the state's permit register, as of April 28, 2026, last verified November 11, 2026
[1] apps.dca.ga.gov
Not disclosed
Who would use it
The math behind the comparison
  1. Bridgeport Technology Park Data Center Campus (Coweta County, DRI #4727), capacity: 1,500 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 1,500 ÷ 10,245 = 0.15 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

  1. Bridgeport Technology Park Data Center Campus (Coweta County, DRI #4727), water: 500,000 gallons a day.
  2. Water used at home each day by the average American family, more than: 300 gallons a day.
  3. 500,000 ÷ 300 = 1,666.67 (gallons a day over gallons a day).

Sources:

The two count different water: the data center figure is water withdrawn from its source, and the EPA's is water used at home, which the EPA does not split into water consumed and water returned.

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Bridgeport Revised Development Applicant
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Bridgeport Technology Park Data Center Campus (Coweta County, DRI #4727).

Field / Parameter Permitted / Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 1.5 GW the developer's figure
Site Footprint (Acres)
Data Hall Buildings 10 buildings Georgia DCA DRI Initial Form [2] apps.dca.ga.gov
Cooling & Water System 500,000 gal/day the developer's figure
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue $30,000,000/yr the developer's figure

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Who would use it A lease announcement or a tenant named in a filing.

What was decided

Acts of Coweta County and the cities in it about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Coweta County case by case Before a packed chamber on December 16, 2025, the Coweta County Board of Commissioners voted 4 to 1, with Commissioner Bill McKenzie dissenting, to adopt a county data center ordinance setting noise, water, land buffer, and building design rules. coweta.ga.us (opens in a new tab)
December 16, 2025 Newnan, GA Coweta County Board of Commissioners Data Center Ordinance Vote Coweta County Board of Commissioners 3 clips

Before a packed chamber on December 16, 2025, the Coweta County Board of Commissioners voted 4 to 1, with Commissioner Bill McKenzie dissenting, to adopt a county data center ordinance setting noise, water, land buffer, and building design rules.

  1. WSB TV Broadcast Report Broadcast Report transcribed from local broadcast report
    "We have done that a chairman chairman. Sounds of disappointment came from the crowd before Kawita County commissioners voted to approve a data center ordinance. All in favor say I. I. Commissioner Bill McKenzie was the only one to vote against the ordinance. It puts guidelines in place on data center noise, land, and water usage as well as building design. I think the ordinances are more than"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "enough to protect their health, water, electricity, and property values. They're arrogant and they don't listen to the people. Commissioners started designing a data center ordinance when a California based tech company submitted an application to build a campus near Wagers Mill Road. Skin Edge represents the property owner. The taxes that can be brought in from a data center project are huge. Neighbors pointed out this land is a conservation zone."
  3. WSB TV Broadcast Report Broadcast Report transcribed from local broadcast report
    "Commissioners paused any construction until they agreed on an ordinance that established guidelines. And each draft was open to public comment. You do not serve the developers. You serve us. Data centers and AI are the next wave. A tsunami we cannot stop. Seven months later, the final draft passed, but the division remains. This is one of the best deals that come to Kawira. It come once in a great while."

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. · Status: permitting (content date)

    Georgia DCA DRI #4727 (Bridgeport Revised) was filed on April 28, 2026 for an 8,250,000 square foot data center campus requesting up to 1,500 MW along Bridgeport Parkway in Coweta County.

    [1] apps.dca.ga.gov

Every event in order

Nearest data centers in Georgia

Verified data center records in Georgia within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Central Coweta Industrial Phase II Data Center Campus (DRI #4374) Coweta County 8 mi Proposed Central Coweta Industrial, LLC 8 buildings
T5 Data Centers Atlanta IV Campus (Coweta County, DRI #4079) Coweta County 14 mi Proposed T5 Data Centers 7 buildings
Project Peach Data Center Campus (Coweta County, DRI #4301) Coweta County 14 mi Proposed North Coweta Investors, LLC 320 acres
Microsoft Palmetto Data Center (CCO06) Palmetto, Fulton County 17 mi Running Microsoft 2 buildings
QTS Atlanta Metro Fayetteville (ATL2) Fayetteville, Fayette County 17 mi Running QTS Data Centers 16 buildings
QTS Fayetteville ATL2 East Campus (DRI #4603) Fayetteville, Fayette County 18 mi Proposed QTS Data Centers 4 buildings

Blank cell: not disclosed by any source on file.

Common questions about Bridgeport Technology Park Data Center Campus (Coweta County, DRI #4727)

Answered directly from the verified filings and local actions on this page.

Who is building Bridgeport Technology Park Data Center Campus (Coweta County, DRI #4727)?

Bridgeport Revised Development Applicant is the developer, apps.dca.ga.gov (opens in a new tab). No construction contractor is named on the record yet.

How much power and water does Bridgeport Technology Park Data Center Campus (Coweta County, DRI #4727) say it needs?
Where does Bridgeport Technology Park Data Center Campus (Coweta County, DRI #4727) stand today?
What has Coweta County decided about it?

Coweta County (rated case by case): Before a packed chamber on December 16, 2025, the Coweta County Board of Commissioners voted 4 to 1, with Commissioner Bill McKenzie dissenting, to adopt a county data center ordinance setting noise, water, land buffer, and building design rules, coweta.ga.us (opens in a new tab). 1 event is on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Primary documents

  1. Georgia DCA DRI #4727 Application Summary (Bridgeport Technology Park Data Center Campus (Coweta County, DRI #4727)) (opens in a new tab), Georgia Department of Community Affairs, April 28, 2026
  2. Georgia DCA DRI #4727 Initial Form (Bridgeport Technology Park Data Center Campus (Coweta County, DRI #4727)) (opens in a new tab), Georgia Department of Community Affairs, April 28, 2026

2 sources on file.

Regional grid context

This site is in the SERC South (SRSO) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Bridgeport Technology Park Data Center Campus (Coweta County, DRI #4727)", https://datacenterrecord.org/projects/georgia-dri-4727-bridgeport-ga, last verified April 28, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Bridgeport Technology Park Data Center Campus (Coweta County, DRI #4727)", https://datacenterrecord.org/projects/georgia-dri-4727-bridgeport-ga. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
built from one source
Tags
Built from one source
Coordinates
33.318054, -84.779471
How the location is known
Location from the county parcel record.
Location source
https://apps.dca.ga.gov/DRI/InitialForm.aspx?driid=4727
Coordinate source
https://apps.dca.ga.gov/DRI/InitialForm.aspx?driid=4727
Location last verified
November 11, 2026
How capacity was disclosed
the developer's figure
How water was disclosed
the developer's figure
Capacity, if disclosed
1.5 GW, the developer's figure
Rating of the county's rows
Case by case
Published
October 21, 2026
Last verified
April 28, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How acreage was disclosed, Interconnection

Researcher view · Bridgeport Technology Park Data Center Campus (Coweta County, DRI #4727) · 2 sources, 1 entry, 1 decision nearby · basis and source tier on every row · verified April 28, 2026