Central Coweta Industrial, LLC filed Georgia DCA DRI #4374 on January 15, 2025 for an 8 building, 2,388,800 square foot data center campus with three planned substations in unincorporated Coweta County. [1] On the regulatory record, state permit status is Georgia DCA DRI #4374 regional review filing. [1]
U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.
Utility interconnection queue filings monitored.
Equivalent to ~93 U.S. households (U.S. EPA 300 gal/day household baseline).
Stated annual local tax revenue: $40,000,000.
Assessor parcel acreage and building square footage are added when municipal or county filings are published.
Location: Parcels 0965142001 and 0965115001, Newnan, Coweta County, GA.
Permanent operational headcount not yet disclosed on the record.
Stated annual local tax revenue: $40,000,000.
Sources:
The two count different water: the data center figure is water withdrawn from its source, and the EPA's is water used at home, which the EPA does not split into water consumed and water returned.
A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).
Connected government officials, corporate entities, utilities and local rules on the public record.
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Central Coweta Industrial Phase II Data Center Campus (DRI #4374).
| Field / Parameter | Permitted / Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | |||
| Site Footprint (Acres) | |||
| Data Hall Buildings | 8 buildings | Georgia DCA DRI Initial Form [2] apps.dca.ga.gov | |
| Cooling & Water System | 28,000 gal/day | the developer's figure | |
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue | $40,000,000/yr | the developer's figure |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Acts of Coweta County and the cities in it about data centers, on the record with their source. A rule about the area is not a decision about this record.
| Date | Who | Decision | Source |
|---|---|---|---|
| Coweta County | Before a packed chamber on December 16, 2025, the Coweta County Board of Commissioners voted 4 to 1, with Commissioner Bill McKenzie dissenting, to adopt a county data center ordinance setting noise, water, land buffer, and building design rules. | coweta.ga.us (opens in a new tab) |
Before a packed chamber on December 16, 2025, the Coweta County Board of Commissioners voted 4 to 1, with Commissioner Bill McKenzie dissenting, to adopt a county data center ordinance setting noise, water, land buffer, and building design rules.
"We have done that a chairman chairman. Sounds of disappointment came from the crowd before Kawita County commissioners voted to approve a data center ordinance. All in favor say I. I. Commissioner Bill McKenzie was the only one to vote against the ordinance. It puts guidelines in place on data center noise, land, and water usage as well as building design. I think the ordinances are more than"
"enough to protect their health, water, electricity, and property values. They're arrogant and they don't listen to the people. Commissioners started designing a data center ordinance when a California based tech company submitted an application to build a campus near Wagers Mill Road. Skin Edge represents the property owner. The taxes that can be brought in from a data center project are huge. Neighbors pointed out this land is a conservation zone."
"Commissioners paused any construction until they agreed on an ordinance that established guidelines. And each draft was open to public comment. You do not serve the developers. You serve us. Data centers and AI are the next wave. A tsunami we cannot stop. Seven months later, the final draft passed, but the division remains. This is one of the best deals that come to Kawira. It come once in a great while."
Using this data in a report? Support the record.
Chronological regulatory, corporate and permitting events on the record, newest first.
· Status: permitting (content date)
Central Coweta Industrial, LLC filed Georgia DCA DRI #4374 on January 15, 2025 for an 8 building, 2,388,800 square foot data center campus with three planned substations in unincorporated Coweta County.
Verified data center records in Georgia within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| T5 Data Centers Atlanta IV Campus (Coweta County, DRI #4079) Coweta County | 6 mi | Proposed | T5 Data Centers | 7 buildings |
| Project Peach Data Center Campus (Coweta County, DRI #4301) Coweta County | 6 mi | Proposed | North Coweta Investors, LLC | 320 acres |
| Bridgeport Technology Park Data Center Campus (Coweta County, DRI #4727) Coweta County | 8 mi | Proposed | Bridgeport Revised Development Applicant | 1.5 GW |
| Microsoft Palmetto Data Center (CCO06) Palmetto, Fulton County | 9 mi | Running | Microsoft | 2 buildings |
| Fairburn Technology Center (DRI #4213) Fairburn, Fulton County | 11 mi | Proposed | Bohannon Road Venture, LLC | 59.6 acres |
| T5 Data Centers Fairburn Campus Fairburn, Fulton County | 12 mi | Proposed | T5 Data Centers | 2 buildings |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
Central Coweta Industrial, LLC is the developer, apps.dca.ga.gov (opens in a new tab). No construction contractor is named on the record yet.
Power: not disclosed by any source on file. Water: 28,000 gallons a day (withdrawal) (the developer's figure, apps.dca.ga.gov (opens in a new tab)).
Coweta County (rated case by case): Before a packed chamber on December 16, 2025, the Coweta County Board of Commissioners voted 4 to 1, with Commissioner Bill McKenzie dissenting, to adopt a county data center ordinance setting noise, water, land buffer, and building design rules, coweta.ga.us (opens in a new tab). 1 event is on the county's rows; a rule about the area is not a decision about this record.
2 sources on file.
This site is in the SERC South (SRSO) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Central Coweta Industrial Phase II Data Center Campus (DRI #4374). Last verified January 15, 2025. https://datacenterrecord.org/projects/georgia-dri-4374-central-coweta-industrial-phase-ii-ga. Accessed November 17, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page. Report a correction · Send a tip about Central Coweta Industrial Phase II Data Center Campus (DRI #4374)
Data Center Record, "Central Coweta Industrial Phase II Data Center Campus (DRI #4374)", https://datacenterrecord.org/projects/georgia-dri-4374-central-coweta-industrial-phase-ii-ga. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.