Data Center Record.
AZ Mesa City Council May 4, 2022

Meta expands to the city of Mesa

Mesa City Council approval record for Elliott Road Technology Corridor hyperscale data center development and municipal desert water allocations (May 4, 2022).

Jurisdiction Mesa, AZ
Governing Body Mesa City Council
Meeting Date May 4, 2022
Extracted Clips 3 clips · 2 opposed · 1 supporting
Archived meeting broadcast · ABC15 Arizona Ready at Clip 1 (0:15 to 0:42) · Mesa Economic Development and Applicant Presentation
Open source video on YouTube ↗ (opens in a new tab)

Privacy enhanced player · zero third party requests until clicked

Meta expands to the city of Mesa

Mesa City Council · May 4, 2022

Timestamped Speaker & Testimony Ledger

3 verified timestamped clips extracted chronologically from the closed caption record. Select any clip to play that exact window in the master player or copy a canonical clip link.

  1. Clip 1 · 0:15 Mesa Economic Development and Applicant Presentation Developer Representative In support transcribed from the official recording
    Tax Abatements Water Power & Grid Zoning

    Developer representatives and economic development officials pitch capital investment, jobs, tax agreements, and utility infrastructure before Mesa City Council.

    "the company will try to cut down on water use with the addition of three new buildings the metadata facility in mesa will be massive 2.5 square feet but for what they do for facebook and instagram users the space is needed our data center and our teams here are going to make sure that their information is safely stored and that they have access to everything from old cat videos to their"

    YouTube at 0:15 ↗ (opens in a new tab)
  2. Clip 2 · 0:43 Mesa City Council Member Elected Official In support transcribed from the official recording
    Tax Abatements Water Power & Grid Zoning

    Mesa City Council members review zoning, tax abatement terms, water allocation, and grid capacity during the approval proceedings.

    "something has to keep the servers cool and for the most part that's water but metta says they want to use as little as possible 60 percent less than normal in fact offset by wind and the fact that the facility will be 100 percent solar what's fortunate about our site here in mesa is we're able to use fresh air from outside to cool our servers for more than half the year for the water they do use meta partnering with srp and the gila river indian"

    YouTube at 0:43 ↗ (opens in a new tab)
  3. Clip 3 · 1:15 Resident public comment Resident Public Comment transcribed from the official recording

    Public commenters and local stakeholders raise questions regarding municipal water draw, tax revenue exemptions, power transmission, and long term community impacts.

    "has already been planned and prepared for meadow recycles the water they use and also gives it back through their salt river program restoring 200 million gallons a year to the colorado river basin the ratio in fact more water for the river systems in arizona than it uses at the data center and with expansion comes jobs the project employing 2 000 skilled trade workers and 200 operational jobs once"

    YouTube at 1:15 ↗ (opens in a new tab)

Using this data in a report? Support the record.

Said and filed

Said and filed

Statements and filings, side by side

Column A · Dated Statement
Mesa Economic Development Officials and Hyperscale Applicants City Officials and Meta and Google Development Representatives
Venue: Mesa City Council Elliott Road Technology Corridor Expansion Approval
"Hyperscale data center expansions along the Elliott Road Technology Corridor incorporate water conservation designs and restorative water replenishment projects that protect East Valley desert water supplies."
Column B · Primary Government Record
City of Mesa Development Agreements (up to 1.25M to 4M Gallons/Day) and 2025 to 2026 East Valley Zoning Restrictions
Mesa City Council Development Agreements (Google Red Hawk and Meta) · 2025 Zoning Code Amendments
Agency or Venue: Mesa City Council and Arizona Department of Water Resources
"Executed municipal water agreements authorized up to 1.25 million to 4 million gallons per day of potable water capacity across Elliott Road hyperscale campuses during Colorado River Tier 1 shortage conditions, prompting Mesa, Chandler, and Phoenix to adopt strict data center zoning and water caps in 2025 and 2026."

Researcher view · basis and source tier on every row · docket and Census GEOIDs · citation and export tools

Commercial and bulk data