Edged Mesa data center

Mesa, Maricopa County, AZDeveloper: EdgedCensus GEOID 04013

Stage
Running
Operational since 2025 (1 year)
Power
36 MW
the developer's figure
Buildings
1 building
operator page
Undisclosed in public filings
Land, Water

Edged operates its 36 MW Edged Phoenix (PHX01) data center at 8927 E Ray Rd in Mesa, Maricopa County, Arizona, using a waterless closed loop cooling system. It is running, since April 7, 2026.

How much water it would use and who would use it have not been disclosed.

Last verified · 4 sources, 1 primary · Reviewed by a person, every entry sourced. · How to read this page

  • This record: Running, ringed
  • data center
  • Smaller pins: 34 other published records in Arizona
Details
  • this record's location, ringed
  • parcel outline, from the county parcel record
  • city limits, U.S. Census Bureau, on a town level record
  • county boundary

The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.

How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.

What is known

Each figure as its source gave it. The number in brackets is its place in the source list.

Commissioned
Operational since 2025 (1 year)
Buildings
1 building operator page
[1] edged.us
Power it would draw
36 MW the developer's figure About 0 percent of New York City's summer peak demand in 2024.
[1] edged.us
Who leads it
Edged as stated by the source
How it is cooled
Closed loop liquid as stated by the source
[1] edged.us
Undisclosed in public filings
Land, Water, Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Edged Mesa data center, capacity: 36 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 36 ÷ 10,245 = 0 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Every field, with who said it and when (Researcher view)

Impact figures

FieldValueWho says soSourceLast verified
How much power it needs 36 MW the developer's figure [1] edged.us (opens in a new tab) October 26, 2026
How much water it would use
How loud it would be
Jobs once it runs
Tax it would pay each year

The record's fields

FieldValueWho says soSourceLast verified
Who is building it Edged as stated by the source October 26, 2026
Who is constructing it
How much land
Buildings 1 building operator page [1] edged.us (opens in a new tab) October 26, 2026
Where its power comes from
Grid connection
How it is cooled Closed loop liquid as stated by the source [1] edged.us (opens in a new tab) October 26, 2026
Cooling fluid

A blank value cell means not disclosed by any source on file; a blank basis cell means the source gave the figure without saying on what basis.

The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Maricopa County and Mesa about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Glendale Glendale Commission recommended rezoning for a data center plan. linkedin.com (opens in a new tab)
Gilbert Gilbert leaders want strict rules on data centers to make it hard for server farms to set up shop; new rules expected in September but delayed to October or November. watereducation.org (opens in a new tab)
Chandler case by case Chandler capped data center water use youtube.com (opens in a new tab)
Maricopa County case by case Maricopa County adopted a new ordinance clarifying guidelines for data center development bizjournals.com (opens in a new tab)
Maricopa County case by case It is the first time data centers have been defined in county zoning rules kjzz.org (opens in a new tab)
Maricopa County case by case The modernized ordinance updated how the county defines a data center and restricts them to industrial areas kjzz.org (opens in a new tab)
8 earlier decisions on the county's rows
DateWhoDecisionSource
Maricopa County case by case Maricopa County Board of Supervisors overhauled its zoning ordinance at a meeting Wednesday in December 2025 kjzz.org (opens in a new tab)
Mesa case by case Mesa data centers will need City Council approval to build under new regulations kjzz.org (opens in a new tab)
Mesa case by case New Mesa zoning amendments direct data centers to heavy industrial zones and general industrial zones kjzz.org (opens in a new tab)
Mesa case by case Mesa data center ordinance restricts future projects to land zoned for industrial use themesatribune.com (opens in a new tab)
Mesa case by case Mesa City Council adopted new zoning rules for data centers and their operations in a City Council vote in July 2025 kjzz.org (opens in a new tab)
Mesa case by case Mesa City Council unanimously approved data center amendments on July 8, 2025, with two members absent themesatribune.com (opens in a new tab)
Mesa case by case Proposed 60 foot height limit for data centers themesatribune.com (opens in a new tab)
Mesa case by case Proposed 400 foot setback from residential areas for data centers themesatribune.com (opens in a new tab)

What happened

  1. · Status: running (content date)

    Edged US opened a waterless AI data center in Mesa, Arizona

    [4] datacenter.news

  2. · Status: being built (content date)

    Edged Energy broke ground on a 36 MW, 210,000 sq ft high density AI data center in Mesa, Arizona, expected to come online in late 2025, powered by Salt River Project.

    [2] datacenterdynamics.com

The full Edged Mesa data center timeline, in order

3 corrections to this record

Every correction, with its reason
  1. · the kind of source of a history entry

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change. The day's label corrections.

  2. · the kind of source of a history entry

    The source was labeled with the Google News search that found it; it now carries its outlet's tier: datacenter.news is a news outlet (tiered by kind, the record's rules of September 23, 2026). The link did not change. The day's label corrections.

Every correction on the record is on the corrections page.

The site

The pin is the site's address.

The site map is at the top of the page.

Where
8927 E Ray Rd, Mesa, AZ 85212, Mesa, Maricopa County, Arizona [1] edged.us (opens in a new tab)
How exactly it is located
Exact, at the address
The parcel
No parcel outline in the public record
Nearest homes
Not computed for a record placed at a place center
Nearest records
By the straight line between two exact points.

USGS NAIP aerial view of Edged Mesa data center
LAT 33.32100 / LON -111.63850 Imagery: U.S. Geological Survey / USDA NAIP (Public Domain)

Questions about this project

5 questions answered from the record

Answered from the rows on this page.

How big is Edged Mesa data center?

The record has 2 measures of its size: 36 MW (the developer's figure, edged.us (opens in a new tab)) and 1 building (operator page, edged.us (opens in a new tab)). Its acreage is not disclosed.

Who is building Edged Mesa data center?

Edged is the developer. No construction contractor is named on the record yet.

How much power and water does Edged Mesa data center say it needs?

Power: 36 MW (the developer's figure, edged.us (opens in a new tab)). Water: not disclosed by any source on file.

Where does Edged Mesa data center stand today?

It is running, since April 7, 2026. The newest entry, April 7, 2026: Edged US opened a waterless AI data center in Mesa, Arizona [4].

What has Mesa or Maricopa County decided about it?

Glendale: Glendale Commission recommended rezoning for a data center plan (September 28, 2026, linkedin.com (opens in a new tab)); and Gilbert: Gilbert leaders want strict rules on data centers to make it hard for server farms to set up shop; new rules expected in September but delayed to October or November (reported September 23, 2026, watereducation.org (opens in a new tab)). 14 events are on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Primary documents

  1. Edged US: Edged Phoenix (8927 E Ray Rd, Mesa, AZ) Facility Specifications (opens in a new tab), Edged

Reporting

  1. Edged breaks ground on data center in Phoenix, Arizona - Data Center Dynamics (opens in a new tab), Data Center Dynamics, August 16, 2024, query feed
  2. Growing Data Center Developer Plans New Project In Phoenix Area - Bisnow (opens in a new tab), Bisnow, July 17, 2023, query feed
  3. Edged US opens waterless AI data centre in Mesa, Arizona (opens in a new tab), datacenter.news, April 7, 2026, news outlet

4 sources on file.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Commercial, enterprise, financial or AI training use needs a commercial license. Prose stays under copyright.
Cite this page Data Center Record, "Edged Mesa data center", https://datacenterrecord.org/projects/edged-mesa-data-center-az, last verified October 26, 2026. CSV · JSON
Cite this page

Data Center Record, "Edged Mesa data center", https://datacenterrecord.org/projects/edged-mesa-data-center-az. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
reviewed in depth
Tags
Reviewed in depth
Coordinates
33.321, -111.6385
How the location is known
Location from the site's street address.
Location source
Edged Phoenix (PHX01) facility specification page at 8927 E Ray Rd, Mesa, Maricopa County, Arizona.
Coordinate source
operator address point
Location last verified
September 23, 2026
Cooling
Closed loop liquid
How capacity was disclosed
the developer's figure
Capacity, if disclosed
36 MW, the developer's figure
Rating of the county's rows
Case by case
Published
September 8, 2026
Last verified
October 26, 2026
Undisclosed in public filings
Location source number, EPA registry id, Uses, Tenancy, How water was disclosed, How acreage was disclosed, Interconnection

Researcher view · Edged Mesa data center · 4 sources, 2 entries, 14 decisions nearby · basis and source tier on every row · verified October 26, 2026