Data Center Record.

Data centers in Spanish Fork, Utah

Spanish Fork has 1 data center on the record; it is proposed. Spanish Fork decides new data centers one at a time. The latest decision on the record: Spanish Fork City Council members limited the city to only one data center unless city leaders vote to change that in the future, reported September 24, 2026. Utah County's own decisions are on the Utah County page.

How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.

The data center in Spanish Fork

Every Spanish Fork record 1 record · blank cell: not disclosed · sort by any column

Facility and countyStageOperatorPower (MW)Latest entry
Volition Industries Spanish Fork Spanish Fork, Utah County Proposed Volition 250 The proposed Volition data center would be a billion dollar, self powered facility generating between 250 and 400 megawatts of its own power using natural gas fox13now.com (opens in a new tab) local outlet reported September 2, 2026

A blank cell means not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.

RecordPlaceStageOperatorMWBasisLocatedTierVerified
Volition Industries Spanish Fork Spanish Fork, Utah Proposed Volition 250 the developer's figure site 1 2026-10-23

Tier 1: an official or company source. Tier 2: a news report resolving to the outlet's own page. Located: a site coordinate from a permit, a parcel or an address, or the county or town centroid. Verified: the last day a person read the source. A blank cell means not disclosed by any source on file.

What Spanish Fork has decided 1 body, 6 decisions on the record

What the city has done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement one tap away, newest first, with its source.

BodyLevelRatingIn force untilLatest actActsVerified
Spanish Forkcitycase by caseSpanish Fork City Council voted to approve changes to city code for a data center. ksl.com (opens in a new tab) local outlet Sep 24, 20266 acts on this row
Every act on the Spanish Fork row
  1. event

    Spanish Fork City Council members limited the city to only one data center unless city leaders vote to change that in the future.

    ksl.com (opens in a new tab) local outlet

  2. approval

    Spanish Fork City Council voted to approve changes to city code for a data center.

    ksl.com (opens in a new tab) local outlet

    Also reported by 1 source
  3. event

    Spanish Fork City Council delayed the Title 15 amendment vote a second time, for another two weeks.

    fox13now.com (opens in a new tab) local outlet

  4. ordinance

    City council tabled resolution to amend ordinance allowing data centers to generate their own power

    fox13now.com (opens in a new tab) local outlet

  5. hearing

    Spanish Fork city council held five hour public hearing on data center proposal with dozens of commenters

    fox13now.com (opens in a new tab) local outlet

  6. event

    After a six hour public hearing, Spanish Fork City Council tabled a vote on Title 15 amendments that would set rules for self powered data centers until September 1.

    heraldextra.com (opens in a new tab) local outlet

    Also reported by 1 source

Last verified September 24, 2026.

62026-09-24

Reported: the source's date; the item names no day of its own. A rating rests only on a binding act in force; "not rated" means no person has set one. A blank cell means the record holds nothing for it.

The rules across Utah

What was said

Spanish Fork City Council member Kevin Oyler stated that the Novva data center campus five miles away in West Jordan is quiet.
Kevin Oyler, City Council Member, Spanish Fork City Council · October 21, 2026 · paraphrased · The Salt Lake Tribune (opens in a new tab) local outlet
Jeff Chavez, CEO of Volition, said the company's closed loop cooling system uses about the amount of water equivalent to one or two Utah households.
Jeff Chavez, CEO of Volition · September 24, 2026 · paraphrased · ksl.com (opens in a new tab) local outlet

Every Utah statement, by speaker

57 more on this page, one per speaker and claim; 65 statements in all

Spanish Fork Mayor Mike Mendenhall said the council has listened to people's concerns, including the amount of water a data center requires.

ksl.com (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ksl.com (opens in a new tab).

Volition would create high paying jobs and generate millions in local tax revenue

Scott McKane, FOX 13 News reporter YouTube (opens in a new tab) video project record
· Scott McKane · YouTube · September 2, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

Volition claims its data center would use natural gas powered fuel cells producing substantially lower emissions and heat and requiring significantly less water than traditional data centers

Jeff Chavez, Volition CEO KSL News (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KSL News (opens in a new tab).

CEO Jeff Chavez previously sought to build a 30 to-40 megawatt fuel cell powered data center in nearby Provo before pivoting to Spanish Fork

Volition CEO Hoodline (opens in a new tab) national outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Hoodline (opens in a new tab).

Residents opposed the proposal, with Tom Thomas stating residents deserve more than unsubstantiated promises and citing data centers' documented track record of water contamination, air pollution, and noise pollution

Spanish Fork resident KSL News (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KSL News (opens in a new tab).

Mona City government said they had not received any formal data center application or development requests and have not made a commitment of water, sewer, or electricity for this data center

Mona City leaders Deseret News (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Deseret News (opens in a new tab).

Called the Volition proposal an opportunity for the city and said it warrants moving forward to see if a private business can deliver on what it proposes, with guard rails in place.

Mike Mendenhall, Mayor, Spanish Fork City Facebook post KSL (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Setting: Facebook post.

Primary source: KSL (opens in a new tab).

Volition CEO Jeff Chavez stated the company generates their own power using natural gas powered fuel cells that do not connect to the existing power grid

KSL.com (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KSL.com (opens in a new tab).

Also reported by: The Salt Lake Tribune (opens in a new tab) local outlet .

Said again: August 21, 2026 ( The Salt Lake Tribune (opens in a new tab) local outlet ), September 1, 2026 ( KSL News (opens in a new tab) local outlet ).

Volition CEO Jeff Chavez said the proposed facility would use two households' worth of water to fill when first starting operations, then only one household's worth annually

CEO, Volition KSL News (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KSL News (opens in a new tab).

Property owner John Bankhead stated he has received many offers for the warehouse site and considers Volition a better option than a distribution center that would increase truck traffic

KSL.com (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KSL.com (opens in a new tab).

Volition plans to create a community fund contributing at least $500,000 per year for addiction recovery, food security, housing support and other community needs

Jeff Chavez, Volition CEO KSL.com (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KSL.com (opens in a new tab).

Residents expressed concerns over noise pollution, water resource impacts, location over a fault line, and whether the facility would be a test site

Spanish Fork residents ABC4 Utah (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ABC4 Utah (opens in a new tab).

Jeff Chavez, Volition CEO, stated data center developers should reuse existing infrastructure instead of buying thousands of acres

· Jeff Chavez · YouTube · August 18, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

Teresa Pierce, Spanish Fork resident, expressed concern that data centers should not be built in residential backyards regardless of need

· Teresa Pierce · YouTube · August 18, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

Residents expressed concerns that Volition has not provided sufficient data or evidence to support claims of minimal community impact

Mapleton resident identified as Crosby ABC4 Utah (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ABC4 Utah (opens in a new tab).

Facility would generate its own power with natural gas fuel cells, never connect to the grid, use closed loop cooling with a one time 500,000 gal fill and 250,000 gal per year, and request no tax breaks.

Jeff Chavez, CEO, Volition Industries Spanish Fork City Council public hearing Daily Herald (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Setting: Spanish Fork City Council public hearing.

Primary source: Daily Herald (opens in a new tab).

Jack Urquhart, Spanish Fork communications manager, explained the municipal code amendment is needed because the developer proposes generating its own power

· Jack Urquhart · YouTube · August 18, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

Volition officials stated their data center will not strain local resources due to being self powered, will be in an existing building, and will have reduced emissions and increased property tax revenue

ABC4 Utah (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ABC4 Utah (opens in a new tab).

Volition officials stated their data center will not strain local resources due to being self powered, will have no diesel generation, is dry cooled, and has noise limits

ABC4 Utah (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ABC4 Utah (opens in a new tab).

Volition's data centers produce zero draw on Spanish Fork's municipal power grid and use no local utility power

Jeff Chavez YouTube (opens in a new tab) video project record
· Jeff Chavez · YouTube · August 5, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

The fuel cell technology generates electricity through an electrochemical reaction with no combustion, flame, or fumes

Jeff Chavez, Volition YouTube (opens in a new tab) video project record
· Jeff Chavez · YouTube · August 5, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

Computer chips transform electricity into heat, creating a large thermal output that should be regulated as heavy industrial use

Allen Westmind YouTube (opens in a new tab) video project record
· Allen Westmind · YouTube · August 5, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

Volition is not requesting any additional water rights from the city

Jeff Chavez YouTube (opens in a new tab) video project record
· Jeff Chavez · YouTube · August 5, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

Volition will include enforceable covenants in the development agreement covering water caps, noise limits, no grid connection, and no diesel

Jeff Chavez YouTube (opens in a new tab) video project record
· Jeff Chavez · YouTube · August 5, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

The proposed data center facility is a good reuse of the existing building and resolves water and heat concerns

Dan Davis YouTube (opens in a new tab) video project record
· Dan Davis · YouTube · August 5, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

Volition commits to providing more than 500,000 dollars per year in direct community contributions and educational partnerships

Jeff Chavez YouTube (opens in a new tab) video project record
· Jeff Chavez · YouTube · August 5, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

Transparency from the developer and rigorous questioning by the planning commission changed resident sentiment toward supporting the project

Rod Yelm YouTube (opens in a new tab) video project record
· Rod Yelm · YouTube · August 5, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

Data centers pose environmental and fire concerns and benefit wealthy entities at the expense of local residents

Megan Banks YouTube (opens in a new tab) video project record
· Megan Banks · YouTube · August 5, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

Converting the existing industrial building to a data center reduces traffic from 3,500 trucks per month to 100-200 employee car trips per day with zero heavy truck traffic

Jeff Chavez, Volition YouTube (opens in a new tab) video project record
· Jeff Chavez · YouTube · August 5, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

Enforceable contractual guardrails and community benefit agreements are necessary to protect clean air and water for future data center projects

Carla Shade YouTube (opens in a new tab) video project record
· Carla Shade · YouTube · August 5, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

Volition received a New Minor Source air quality permit approval from the Utah Department of Environmental Quality

Jeff Chavez YouTube (opens in a new tab) video project record
· Jeff Chavez · YouTube · August 5, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

Volition Industries proposes a data center inside Spanish Fork City powered entirely on site without connection to the city electric grid

Dave Anderson YouTube (opens in a new tab) video project record
· Dave Anderson · YouTube · August 5, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

The proposed 250 megawatt facility would produce more than double the peak power draw of the entire city of Spanish Fork

Paul Dayton YouTube (opens in a new tab) video project record
· Paul Dayton · YouTube · August 5, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: YouTube (opens in a new tab).

Jesse Harrison, local IT expert, stated that many data center promises get broken repeatedly based on historical patterns

· Jesse Harrison · YouTube · March 11, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

Traditional data centers require massive grid power and two to four years of utility infrastructure upgrades

unnamed narrator YouTube (opens in a new tab) video project record
· unnamed narrator · YouTube · October 24, 2025 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

Volition facilities deploy in six to nine months using on site fuel cell electricity generation

unnamed narrator YouTube (opens in a new tab) video project record
· unnamed narrator · YouTube · October 24, 2025 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

The county and nearby counties

The county Utah County: its decisions and every record in it.
40 miles away Salt Lake County: 13 data centers on the record.
65 miles away Carbon County: 1 data center on the record.
114 miles away Uintah County: 1 data center on the record.
127 miles away Box Elder County: 1 data center on the record. A pause is on the record.

Distances run between the centers the Census Bureau gives each place. Every Utah county.

Disclosed figures

250 MW power, water from 1 record

Power, water, jobs and tax, summed only where a data center disclosed the figure; what each facility is for; how each is cooled. Nothing here is estimated.

Power, water, jobs and tax

FigureDisclosed totalDisclosedWithout a figureBasis
Power250 MW101 the developer's figure
Water, stated per year250,000 gallons a year101 the developer's figure
Permanent jobs01
Tax each year$40,000,000 to $44,000,000101 the developer's figure

A blank total means no record disclosed the figure; the count without one says how many.

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

By what the facilities are for

UseRecordsPowerWaterJobsTax each year
AI, type not stated1250 MW250,000 gallons a year$40,000,000 to $44,000,000

A blank cell means no record with that use disclosed the figure.

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

What the facilities are for

UseFacilitiesShare of facilitiesAttributed MWShare of attributed MW
AI, type not stated1100%250 MW100%

A blank cell means no source attributes power to that use.

1 facility in Spanish Fork. Capacity is attributed to a use only where a source states the share, or where a facility lists a single use. Nothing is divided by estimate.

How the facilities are cooled

No source on file states how any of the 1 tracked facility in Spanish Fork is cooled.

Sources read for Spanish Fork

1 source

1 source is read for Spanish Fork. State and national sources are on the Utah page.

Agendas and notices
Spanish Fork public notices
Every feed, with its kind and tier

What is read for Spanish Fork: feeds every four hours, pages daily. A headline from any of these becomes a record only after a person reads the source and publishes it.

Agendas and notices

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Only what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Commercial, enterprise, financial or AI training use needs a commercial license. Prose stays under copyright.
Cite this page Data Center Record, "Data centers in Spanish Fork, Utah County, Utah", https://datacenterrecord.org/states/ut/utah-county/spanish-fork, updated October 23, 2026. CSV · JSON
Cite this page

Data Center Record, "Data center records in Spanish Fork, Utah County, Utah", https://datacenterrecord.org/states/ut/utah-county/spanish-fork. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
Level
city
Census GEOID
4971290
Census geography
Incorporated place, Spanish Fork city
Rating
Case by case

Researcher view · Spanish Fork, Utah County, Utah · 1 record, 1 rule row · Census GEOID 4971290 · basis and source tier on every row · verified October 23, 2026

Download CSV JSON