Nottingham conservation committee and master plan update subcommittee member
Kristen Lamb expressed concerns about water quality impacts, increased electricity bills and noise pollution from the data center
Nottingham has 1 data center on the record; it is proposed. Nottingham limits new data centers. The latest decision on the record: Nottingham residents voted in favor of a 12 month moratorium on data center development with 1,335 votes in favor to 143 against, September 9, 2026. Rockingham County's own decisions are on the Rockingham County page.
How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.
Each row is one site with its stage, its latest dated entry and what its sources disclose. A figure no source gives reads Not disclosed.
Nottingham, Rockingham County · Thomas Moulton
Latest, reported September 9, 2026: A feasibility study is planned in Bow for a hyperscale data center likely on the site of the former coal fired power plant owned by Granite Shore Power, LLC nenc.news local outlet
Drag with one finger to move the map, pinch to zoom. Tap a pin for the data center, a county for its rules
1 data center in Nottingham: proposed. A dashed edge means the exact site is not in the public record; every pin here marks a town or the county.
What the city has done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement behind its toggle, newest first, with its source.
Reported: the source's date; the item names no day of its own.
Nottingham residents voted in favor of a 12 month moratorium on any data center development within town limits, reported September 9, 2026.
Nottingham residents voted in favor of a 12 month moratorium on any data center development within town limits
Nottingham held a town vote on 12 month moratorium on data center construction by 2026-07-03
· Nottingham
Moratorium: Nottingham residents voted in favor of a 12 month moratorium on any data center development within town limits ctpublic.org local outlet
· Nottingham
Moratorium: Nottingham held a town vote on 12 month moratorium on data center construction by 2026-07-03 nhpr.org local outlet
· Nottingham Data Center (unnamed developer)
Now reported: Moulton withdrew his application hours before the planning board meeting last Wednesday businessnhmagazine.com local outlet
Governor Kelly Ayotte proposed a statewide moratorium on data centers in next state budget
Kristen Lamb said residents want to move forward with a moratorium or make it explicit that data centers cannot be approved
Every New Hampshire statement, by speaker
Nottingham conservation committee and master plan update subcommittee member
Kristen Lamb expressed concerns about water quality impacts, increased electricity bills and noise pollution from the data center
| Figure | Disclosed total | Disclosed | Not disclosed | Basis | |
|---|---|---|---|---|---|
| Power | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record | |
| Water, stated per day | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record | |
| Water, stated per year | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record | |
| Permanent jobs | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record | |
| Tax each year | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record |
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
| Use | Records | Power | Water | Jobs | Tax each year | |
|---|---|---|---|---|---|---|
| Not disclosed | 1 | Not disclosed | Not disclosed | Not disclosed | Not disclosed | Not disclosed: power, water, jobs, tax each year |
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
No source on file states what any of the 1 tracked facility in Nottingham is for.
No source on file states how any of the 1 tracked facility in Nottingham is cooled.
Data Center Record, "Data centers in Nottingham, Rockingham County, New Hampshire", https://datacenterrecord.org/states/nh/rockingham-county/nottingham, updated September 25, 2026.
Data Center Record, "Data center records in Nottingham, Rockingham County, New Hampshire", https://datacenterrecord.org/states/nh/rockingham-county/nottingham. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.
The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.
The rows here are part of the New Hampshire export.