Data Center Record.

Data centers in Mesa, Arizona

Mesa has 9 data centers on the record: 7 running, 1 being built and 1 proposed. Mesa decides new data centers one at a time. The latest decision on the record: Mesa City Council unanimously approved data center amendments on July 8, 2025, with two members absent. Maricopa County's own decisions are on the Maricopa County page.

How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.

The 9 data centers in Mesa

Every Mesa record 9 records · blank cell: not disclosed · sort by any column

Facility and countyStageOperatorPower (MW)Latest entry
Apple Mesa data center Mesa, Maricopa County Running Apple
Centersquare Phoenix data center Mesa, Maricopa County Running Centersquare
EdgeConneX Mesa data center campus Mesa, Maricopa County Running EdgeConneX
Novva Mesa data center Mesa, Maricopa County Running Novva Data Centers
Google Mesa data center Mesa, Maricopa County Being built In court Google Google Mesa data center began functioning within the past year abc15.com (opens in a new tab) local outlet August 25, 2026
NTT Mesa data center campus Mesa, Maricopa County Running NTT DATA Project grandfathered under Mesa's tighter data center rules because NTT submitted application August 4, 2025, four days before city's new data center ordinance took effect coppercourier.com (opens in a new tab) local outlet June 9, 2026
Edged Mesa data center Mesa, Maricopa County Running Edged 36 Edged US opened a waterless AI data center in Mesa, Arizona datacenter.news (opens in a new tab) news outlet April 7, 2026
EdgeCore Mesa North Campus Mesa, Maricopa County Proposed Waiting on permits EdgeCore Generator testing restricted to 9 a.m. to 9 p.m. at EdgeCore facility bisnow.com (opens in a new tab) trade press March 16, 2026

A blank cell means not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.

RecordPlaceStageOperatorMWBasisLocatedTierVerified
Apple Mesa data center Mesa, Maricopa Running Apple EPA registry 2 2026-10-25
Centersquare Phoenix data center Mesa, Maricopa Running Centersquare site 2 2026-10-25
EdgeConneX Mesa data center campus Mesa, Maricopa Running EdgeConneX EPA registry 1 2026-10-25
Novva Mesa data center Mesa, Maricopa Running Novva Data Centers site 1 2026-10-25
Google Mesa data center Mesa, Maricopa Being built Google site 2 2026-10-25
NTT Mesa data center campus Mesa, Maricopa Running NTT DATA EPA registry 2 2026-10-25
Edged Mesa data center Mesa, Maricopa Running Edged 36 the developer's figure site 1 2026-10-26
EdgeCore Mesa North Campus Mesa, Maricopa Proposed EdgeCore EPA registry 2 2026-10-25
Meta Mesa Data Center Mesa, Maricopa Running Meta EPA registry 2 2026-10-25

Tier 1: an official or company source. Tier 2: a news report resolving to the outlet's own page. Located: a site coordinate from a permit, a parcel or an address, or the county or town centroid. Verified: the last day a person read the source. A blank cell means not disclosed by any source on file.

What Mesa has decided 1 body, 2 decisions on the record

What the city has done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement one tap away, newest first, with its source.

BodyLevelRatingIn force untilLatest actActsVerified
Mesacitycase by caseMesa City Council unanimously approved data center amendments on July 8, 2025, with two members absent. themesatribune.com (opens in a new tab) local outlet Jul 8, 20252 acts on this row
Every act on the Mesa row
  1. event

    Mesa City Council unanimously approved data center amendments on July 8, 2025, with two members absent

    themesatribune.com (opens in a new tab) local outlet

  2. event

    Mesa City Council adopted new zoning rules for data centers and their operations in a City Council vote in July 2025

    kjzz.org (opens in a new tab) local outlet

Last verified September 8, 2026.

22026-09-08

A month with no day: the source names the month and not the day. A rating rests only on a binding act in force; "not rated" means no person has set one. A blank cell means the record holds nothing for it.

The rules across Arizona

What happened

  1. Now waiting on permitsNTT Mesa data center campus

    Data center project in Mesa moving forward

  2. Went liveEdged Mesa data center

    Edged US opened a waterless AI data center in Mesa, Arizona

  3. AcquisitionEdgeCore Mesa North Campus

    EdgeCore acquired 43.87 acres in Mesa for $43.95 million in May 2025

  4. Now waiting on permitsEdgeCore Mesa North Campus

    EdgeCore data center campus in Mesa being scaled back

  5. Broke groundNTT Mesa data center campus

    NTT Data Centers planning sixth building, phase PH6, at 10256 E. Elliot Road in Mesa

Arizona, year by year

What was said

Nathan Taylor Taft, Mesa High School student and co director of East Valley Unite, urged Mesa City Council on June 8 to reject the proposed NTT data center
Nathan Taylor Taft, Mesa High School student and co-director of East Valley Unite · June 10, 2026 · paraphrased · Copper Courier (opens in a new tab) local outlet
Mesa Mayor John Giles said the City of Mesa is thrilled to welcome Google and the decision underscores confidence in the city
John Giles, Mesa Mayor · September 9, 2023 · paraphrased · AZ Big Media (opens in a new tab) local outlet

Every Arizona statement, by speaker

32 more on this page, one per speaker and claim; 34 statements in all

EdgeCore project not subject to Mesa's July 2025 data center ordinance because initial application submitted January 2024

Mesa city staff Bisnow (opens in a new tab) trade press project record
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: Bisnow (opens in a new tab).

Google, Meta, Microsoft, OpenAI, xAI, Oracle and Amazon Web Services signed a ratepayer protection pledge committing to ensure data center growth will not drive up consumer energy costs

Meta, Microsoft, OpenAI, xAI, Oracle, Amazon Web Services themesatribune.com (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: themesatribune.com (opens in a new tab).

"These renewable energy centers will generate low-cost, homegrown energy and provide millions of dollars in additional revenue to both Maricopa and Pinal counties over the life of the projects"
Anthony Pedroni, Unknown, SRP or NextEra TD World article TD World (opens in a new tab) trade press project record
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: TD World article.

Primary source: TD World (opens in a new tab).

Joe Kava, VP of Data Centers at Google, stated data centers are economic anchors in communities

VP of Data Centers, Google AZ Family (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: AZ Family (opens in a new tab).

Also reported by: Construction Dive (opens in a new tab) news outlet .

Said again: September 8, 2023 ( Construction Dive (opens in a new tab) news outlet ).

Mesa Vice Mayor Jenn Duff said the driest 12 months in 126 years occurred at the time of the vote and data centers are an irresponsible use of water

NBC News (opens in a new tab) national outlet project record
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: NBC News (opens in a new tab).

Landon Marston, lead author of a Virginia Tech paper, stated researchers are unsure about the degree to which environmental considerations are in data center siting decisions

Virginia Tech Researcher NBC News (opens in a new tab) national outlet project record
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: NBC News (opens in a new tab).

Venkatesh Uddameri, professor and director of the Water Resources Center at Texas Tech University, stated the typical data center uses about 3-5 million gallons of water per day, equivalent to the water use of a city of 30,000-50,000 people

Professor and Director, Texas Tech University Water Resources Center NBC News (opens in a new tab) national outlet project record
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: NBC News (opens in a new tab).

Sergio Loureiro, vice president of core operations for Microsoft, said the company has pledged to be water positive by 2030, meaning it plans to replenish more water than it consumes globally

Vice President of Core Operations, Microsoft NBC News (opens in a new tab) national outlet project record
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: NBC News (opens in a new tab).

Gary Demasi, senior director of energy and location operations at Google, said the company is working to utilize water more efficiently and exploring ways to incorporate circularity

Senior Director of Energy and Location Operations, Google NBC News (opens in a new tab) national outlet project record
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: NBC News (opens in a new tab).

The county and nearby counties

The county Maricopa County: its decisions and every record in it.
71 miles away Pinal County: 1 data center on the record.

Distances run between the centers the Census Bureau gives each place. Every Arizona county.

Disclosed figures

36 MW power

Power, water, jobs and tax, summed only where a data center disclosed the figure; what each facility is for; how each is cooled. Nothing here is estimated.

Power, water, jobs and tax

FigureDisclosed totalDisclosedWithout a figureBasis
Power36 MW181 the developer's figure
Water, stated per day09
Water, stated per year09
Permanent jobs09
Tax each year09

A blank total means no record disclosed the figure; the count without one says how many.

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

By what the facilities are for

UseRecordsPowerWaterJobsTax each year
No stated use936 MW

A blank cell means no record with that use disclosed the figure.

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

What the facilities are for

No source on file states what any of the 9 tracked facilities in Mesa are for.

How the facilities are cooled

MethodFacilitiesShare of facilities
Air cooled111%
Closed loop liquid111%
No stated cooling type778%

9 facilities in Mesa. A facility carries one cooling method; nothing here is estimated.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Only what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Commercial, enterprise, financial or AI training use needs a commercial license. Prose stays under copyright.
Cite this page Data Center Record, "Data centers in Mesa, Maricopa County, Arizona", https://datacenterrecord.org/states/az/maricopa-county/mesa, updated October 26, 2026. CSV · JSON
Cite this page

Data Center Record, "Data center records in Mesa, Maricopa County, Arizona", https://datacenterrecord.org/states/az/maricopa-county/mesa. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
Level
city
Census GEOID
0446000
Census geography
Incorporated place, Mesa city
Rating
Case by case

Researcher view · Mesa, Maricopa County, Arizona · 9 records, 1 rule row · Census GEOID 0446000 · basis and source tier on every row · verified October 26, 2026