Data Center Record.
Census GEOID: 48139 Location Precision: permit coordinates Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 3 primary sources

● Running First recorded September 14, 2026 · 5 Buildings

Google Midlothian data center

Street address 3200 V V Jones Road, Midlothian, TX 76065, Ellis County permit coordinates Exact, the point of the EPA's facility record [3] EPA ECHO detailed facility report: Sharka Midlothian TX

Overview, regulatory gates and specifications

Google lists a data center at Midlothian, Texas among the sites it operates. [1] Filings on the record specify a 375 acre site footprint, 5 planned or operational buildings. [1] Google lists Google Midlothian data center at Midlothian, Texas on its own page of data center locations, read September 14, 2026. [2]

1. Land & Parcel
375 acres on file
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
EPA ECHO Facility Registry R
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water [1]
722,192 gal/day
measured

Equivalent to ~2,407 U.S. households (U.S. EPA 300 gal/day household baseline).

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
375 acres
measured

5 planned or operational data hall buildings.

Location: 3200 V V Jones Road, Midlothian, TX 76065.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
263,600,000 gallons a year (withdrawal) permitted Equivalent to the annual water use of about 2,410 average U.S. households based on the U.S. Environmental Protection Agency baseline of 109,500 gallons per year per home, or about 399 Olympic size swimming pools of 660,000 gallons each. What at most 2,407 American families use at home, at the EPA's more than 300 gallons a family a day (the EPA gives no year for it).
[1] sustainability.google
Land area
375 acres assessor parcel
elliscad.com (opens in a new tab)
Buildings
5 buildings permitted
[3] echo.epa.gov
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2023 (3 years)
Who leads it
Google as stated by the source
Permitted legal entity
Design LLC / Google LLC what a permit allows
[3] echo.epa.gov
State air permit registration
FRS 110070801654, TX0000004813901630, TXR000085686, TXR05GA53, TXR1510EL state air permit register
State permit status
EPA ECHO Facility Registry Record FRS 110070801654, Clean Air Act ID TX0000004813901630, RCRA ID TXR000085686 and TCEQ Stormwater Permits TXR05GA53 and TXR1510EL (3200 V V Jones Rd, Midlothian, TX 76065) and Texas Comptroller Qualified Data Center Registration (Sharka LLC / Google LLC) the state's permit register, last verified November 9, 2026
[3] echo.epa.gov
Official project website
datacenters.google (opens in a new tab) verified October 28, 2026
datacenters.google (opens in a new tab)
Archived promotional websites
datacenters.google (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Google Midlothian data center, water: 263,600,000 gallons a year.
  2. 263,600,000 gallons a year ÷ 365 = 722,192 gallons a day.
  3. Water used at home each day by the average American family, more than: 300 gallons a day.
  4. 722,191.78 ÷ 300 = 2,407.31 (gallons a day over gallons a day).

Sources:

The two count different water: the data center figure is water withdrawn from its source, and the EPA's is water used at home, which the EPA does not split into water consumed and water returned.

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Google · Parent: Alphabet · Applicant / Shell LLC: Design LLC
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Google Midlothian data center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres) 375 acres 375 acres measured
Data Hall Buildings 5 buildings 5 5 data center buildings across Phase 1 and Phase 2 at 3200 V V Jones Road per Ellis Appraisal District commercial improvements and City of Midlothian site plan approvals [3] echo.epa.gov
Cooling & Water System 263,600,000 gal/yr measured [1] sustainability.google
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

June 14, 2019 Midlothian, TX Google chooses Midlothian for new Data Center Midlothian City Council 1 clip

Midlothian City Council approval of tax abatement and water agreements for the $600 million Google Project Shavano data center campus in Ellis County (June 14, 2019).

  1. Midlothian Economic Development and Applicant Presentation Developer Representative transcribed from local broadcast report
    "million dollars and creating a number of high paying, high tech jobs and hundreds of construction jobs over the next several years. Texas is a huge part of Google's story and we are so excited for Midlothian to be the next chapter. Google's mission has always been to make the world's information universally accessible and useful. And this is possible because of these"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Google lists Google Midlothian data center at Midlothian, Texas on its own page of data center locations, read September 14, 2026.

    [2] datacenters.google

1 correction to this record

Every correction, with its reason
  1. · Building count (2 buildings to 5 buildings)

    Updated to 5 operational and expanded data center buildings on the 375 acre campus at 3200 V V Jones Road per Ellis Appraisal District commercial parcel records and EPA ECHO FRS 110070801654.

Every correction on the record is on the corrections page.

Nearest data centers in Texas

Verified data center records in Texas within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
DataBank Red Oak Campus Red Oak, Ellis County 15 mi Being built DataBank 480 MW
Compass Red Oak campus Red Oak, Ellis County 16 mi Being built Compass Datacenters 4 buildings
Google Red Oak data center Red Oak, Ellis County 16 mi Being built Google 1 building
STACK DFW02 Lancaster, Dallas County 18 mi Running STACK Infrastructure 2 buildings
QTS South Dallas Wilmer, Dallas County 23 mi Being built QTS Data Centers 3 buildings
Google Wilmer Data Center Wilmer, Dallas County 25 mi Running Google 1 building

Blank cell: not disclosed by any source on file.

Common questions about Google Midlothian data center

Answered directly from the verified filings and local actions on this page.

Who is building Google Midlothian data center?

Google is the developer. No construction contractor is named on the record yet.

How much power and water does Google Midlothian data center say it needs?

Power: not disclosed by any source on file. Water: 263,600,000 gallons a year (withdrawal) (measured, sustainability.google (opens in a new tab)).

Where does Google Midlothian data center stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Google 2026 Environmental Report (Page 97: Water use by data center location, 2025) (opens in a new tab), Google
  2. Google: Data center locations (opens in a new tab), Google, September 14, 2026
  3. EPA ECHO detailed facility report: Sharka Midlothian TX (opens in a new tab), U.S. Environmental Protection Agency

3 sources on file.

Regional grid context

This site is in the ERCOT All (ERCT) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Google Midlothian data center", https://datacenterrecord.org/projects/google-midlothian-data-center-tx, last verified November 9, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Google Midlothian data center", https://datacenterrecord.org/projects/google-midlothian-data-center-tx. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
reviewed in depth
Tags
Reviewed in depth
Coordinates
32.447971, -97.056184
How the location is known
Location from an EPA facility record.
Location source
EPA ECHO Detailed Facility Report (FRS ID 110070801654) for Google Sharka campus in Midlothian, Ellis County, Texas.
Coordinate source
EPA ECHO FRS ID 110070801654
Location last verified
September 14, 2026
How water was disclosed
measured
How acreage was disclosed
measured
Published
September 14, 2026
Last verified
November 9, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Google Midlothian data center · 3 sources, 1 entry · basis and source tier on every row · verified November 9, 2026

Download CSV JSON