Data Center Record.
Census GEOID: 39045 Location Precision: permit coordinates Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 2 primary and 1 reporting sources

● Running Reported September 19, 2026 · 2 Buildings

Google Lancaster data center

Street address 35 Whiley Road, Lancaster, OH 43130, Fairfield County permit coordinates Exact, the point of the EPA's facility record [2] EPA ECHO detailed facility report: Google Lancaster Data Center (110071854363)

Overview, regulatory gates and specifications

Google lists a data center at Lancaster, Ohio among the sites it operates. [3] Filings on the record specify 2 planned or operational buildings. [3] Google's Lancaster data center opened in 2023 [3]

Verified Site & Permit Summary
Verified address
35 Whiley Road, Lancaster, OH 43130, Fairfield County permit coordinates
Operator / developer
Google
Permit / registry ID
streamlinefeed.co.ke on file [1]

How much power it needs, how much water it would use and who would use it have not been disclosed.

What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
2 buildings operator page
google.com (opens in a new tab)
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2023 (3 years)
Who leads it
Google as stated by the source
Official project website
datacenters.google (opens in a new tab) verified October 28, 2026
datacenters.google (opens in a new tab)
Archived promotional websites
datacenters.google (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Brooks R.

Resident · Greenfield Township, Ohio

DID Recorded statement at Greenfield Township, Ohio (October 26, 2026)
SAID The character of our community has changed completely (October 26, 2026) nbc4i.com (opens in a new tab)
Jon Husted

Jon Husted

U.S. Senator · U.S. Senate

DID Recorded statement at politifact.com (September 23, 2026)
SAID Jon Husted said that artificial intelligence and data centers were crucial to America's economic superiority because they drive innovation, support high tech industries, and help analyze vast data essential for global competitiveness (September 23, 2026) politifact.com (opens in a new tab)
Sherrod Brown

Sherrod Brown

2026 candidate for U.S. Senate · Ohio

DID Recorded statement at streamlinefeed.co.ke (September 19, 2026) [3]
SAID Brown's campaign placed an ad on September 4 attacking data centers in Ohio (September 19, 2026) [3]

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Google · Parent: Alphabet
UTILITIES
Electric utility: Not disclosed

View all 4 statements on the record in Ohio →

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Google Lancaster data center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings 2 buildings 2 operator page
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    Google's Lancaster data center opened in 2023

    [3] streamlinefeed.co.ke

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Google lists Google Lancaster data center at Lancaster, Ohio on its own page of data center locations, read September 14, 2026.

    [1] datacenters.google

Nearest data centers in Ohio

Verified data center records in Ohio within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Ashville data center project Ashville, Pickaway County ~14 mi Proposed EdgeConneX
Microsoft Hebron datacenter Hebron, Licking County 19 mi Running Microsoft 1 building
Google Columbus data center Columbus, Franklin County 19 mi Running Google 2 buildings
Stream Data Centers Grove City campus Grove City, Franklin County ~23 mi Proposed Stream Data Centers 310 acres
Google New Albany data center New Albany, Franklin County 23 mi Running Google 3 buildings
Microsoft Heath datacenter Heath, Licking County 24 mi Running Microsoft 1 building

Blank cell: not disclosed by any source on file.

Common questions about Google Lancaster data center

Answered directly from the verified filings and local actions on this page.

Who is building Google Lancaster data center?

Google is the developer. No construction contractor is named on the record yet.

How much power and water does Google Lancaster data center say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Google Lancaster data center stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. The newest entry, reported September 19, 2026: Google's Lancaster data center opened in 2023 [3].

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Google: Data center locations (opens in a new tab), Google, September 14, 2026
  2. EPA ECHO detailed facility report: Google Lancaster Data Center (110071854363) (opens in a new tab), U.S. Environmental Protection Agency

Reporting

  1. Brown's data center ad meets scrutiny over Google campaign donations - streamlinefeed.co.ke (opens in a new tab), streamlinefeed.co.ke, September 19, 2026, international outlet

3 sources on file.

Regional grid context

This site is in the RFC West (RFCW) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Google Lancaster data center", https://datacenterrecord.org/projects/google-lancaster-data-center-oh, last verified October 25, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Google Lancaster data center", https://datacenterrecord.org/projects/google-lancaster-data-center-oh. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
reviewed in depth
Tags
Reviewed in depth
Coordinates
39.727336, -82.683034
How the location is known
Location from an EPA facility record.
Location source
EPA ECHO Detailed Facility Report (FRS ID 110071854363, NPDES OH0151653 / OHR120001) at 35 Whiley Road, Lancaster, Fairfield County, Ohio.
Coordinate source
EPA ECHO FRS ID 110071854363
Location last verified
September 14, 2026
Published
September 14, 2026
Last verified
October 25, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Google Lancaster data center · 3 sources, 2 entries · basis and source tier on every row · verified October 25, 2026