Stream Data Centers and Headwaters Site Development proposed a data center campus on 310 acres southwest of Grove City near Rensch Road and Beatty Road in Franklin County, Ohio. [1]
How much power it needs, how much water it would use and who would use it have not been disclosed.
Connected government officials, corporate entities, utilities and local rules on the public record.
We are extremely proud. We are extremely grateful for the residents of Grove City who showed up to make their voices heard because that's what Issue 28 has been all about all along. This is just, this is one step of many to make sure that the residents have a voice on the largest developments that could change the landscape of the city.(November 4, 2026)
I can't even begin to even vocalize how I feel, just knowing that the rest of Grove City came together and to back the township. It's just now setting in with me that this actually passed and that we are going to have a voice through the neighbors that live in town.(November 4, 2026)
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Stream Data Centers Grove City campus.
| Field / Parameter | Permitted / Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | |||
| Site Footprint (Acres) | 310 acres | 310 acres | the developer's figure [2] nbc4i.com |
| Data Hall Buildings | |||
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Acts of Franklin County and Grove City about data centers, on the record with their source. A rule about the area is not a decision about this record.
| Date | Who | Decision | Source |
|---|---|---|---|
| Grove City | Grove City voters approved Issue 28, the Community Consent charter amendment requiring a citywide vote before approval of heavy industrial developments of 50 or more acres, more than 20 megawatts at peak, or more than 500,000 gallons of water a day, on November 3, 2026, voting 11,317 in favor (54.61 percent) to 9,411 against (45.39 percent). | wosu.org (opens in a new tab) | |
| Grove City | Grove City voters voted on Issue 28 on November 3, 2026, the Community Consent charter amendment requiring a citywide vote before approval of heavy industrial developments of 50 or more acres, more than 20 megawatts at peak or more than 500,000 gallons of water a day. | vote.franklincountyohio.gov (opens in a new tab) |
Chronological regulatory, corporate and permitting events on the record, newest first.
No dated entry is on the record yet.
Verified data center records in Ohio within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| Google Columbus data center Columbus, Franklin County | ~3 mi | Running | 2 buildings | |
| Ashville data center project Ashville, Pickaway County | ~12 mi | Proposed | EdgeConneX | |
| Expedient Columbus - Upper Arlington Upper Arlington, Franklin County | ~13 mi | Running | Expedient | 1 building |
| Expedient Columbus - Dublin Dublin, Franklin County | ~16 mi | Running | Expedient | 1 building |
| Cologix Columbus Columbus, Franklin County | ~18 mi | Running | Cologix | 4 buildings |
| QTS Data Centers New Albany New Albany, Franklin County | ~20 mi | Being built | QTS Data Centers | 4 buildings |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
Stream Data Centers is the developer, nbc4i.com (opens in a new tab). No construction contractor is named on the record yet.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
It is proposed; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.
Grove City: Grove City voters approved Issue 28, the Community Consent charter amendment requiring a citywide vote before approval of heavy industrial developments of 50 or more acres, more than 20 megawatts at peak, or more than 500,000 gallons of water a day, on November 3, 2026, voting 11,317 in favor (54.61 percent) to 9,411 against (45.39 percent), wosu.org (opens in a new tab); and Grove City: Grove City voters voted on Issue 28 on November 3, 2026, the Community Consent charter amendment requiring a citywide vote before approval of heavy industrial developments of 50 or more acres, more than 20 megawatts at peak or more than 500,000 gallons of water a day, vote.franklincountyohio.gov (opens in a new tab). 2 events are on the county's rows; a rule about the area is not a decision about this record.
2 sources on file.
This site is in the RFC West (RFCW) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Stream Data Centers Grove City campus. Last verified October 31, 2026. https://datacenterrecord.org/projects/stream-data-centers-grove-city-oh. Accessed November 17, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page. Report a correction · Send a tip about Stream Data Centers Grove City campus
Data Center Record, "Stream Data Centers Grove City campus", https://datacenterrecord.org/projects/stream-data-centers-grove-city-oh. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.