Data Center Record.
Census GEOID: 39049 Location Precision: permit coordinates Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 2 primary and 16 reporting sources

● Running First recorded September 14, 2026 · 4 Buildings

Cologix Columbus

Street address 535 Scherers Court, Columbus, OH 43085, Franklin County permit coordinates Exact, the point of the EPA's facility record [2] EPA ECHO detailed facility report: Cologix (0125043211)

Overview, regulatory gates and specifications

Cologix lists 7 data centers at Columbus, Ohio among the sites it operates. [3] Filings on the record specify 4 planned or operational buildings. [3] Cologix lists Cologix COL1, Cologix COL2, Cologix COL3, Cologix COL4, Cologix COL5, Cologix COL7, Cologix COL8 at Columbus, Ohio on its own page of data center locations, read September 14, 2026. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
EPA air permit on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
4 buildings
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 535 Scherers Court, Columbus, OH 43085.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
4 buildings operator page
cologix.com (opens in a new tab)
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2018 (8 years)
Who leads it
Cologix as stated by the source
Official project website
cologix.com (opens in a new tab) verified October 28, 2026
cologix.com (opens in a new tab)
Archived promotional websites
cologix.com (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Cologix
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Cologix Columbus.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings 4 buildings 4 operator page
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

2025 to 2026 hearings
March 11, 2026 Columbus, OH Columbus City Council Public Hearing on Central Ohio Data Center Water and Tax Impacts Columbus City Council 2 clips

Columbus City Council President Shannon Hardin convened a public hearing on March 11, 2026 examining how hyperscale data centers across Central Ohio affect Columbus municipal water supply, electric grid capacity, and local taxpayers.

  1. WBNS 10TV Broadcast Report Broadcast Report transcribed from local broadcast report
    "The goal of the hearing was to develop the city's strategy on how to address the challenges that come with these developments. Although most of the data centers located across central Ohio are not built within the city of Columbus, City council President Shannon Hardin said Columbus residents and service providers still bear the responsibility of supplying the electricity. and water they require, he noted that data centers use millions of gallons of water each day."
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "Data centers for me are a test of if we can get that balance right. 83% of data centers in Virginia use the same or less water than an average office building. some even use less than a typical household. Large data centers may require up to 5 million gallons of water per day. That compares to, to the water needs of a city of about 50,000 residents, about the size of the city of Dublin. Now,"
2019 to 2024 hearings
June 26, 2023 Columbus, OH Amazon Web Services to invest $7.8 billion in central Ohio data center expansion Columbus City Council 1 clip

Columbus and Franklin County municipal tax abatement and utility infrastructure record for the $7.8 billion Central Ohio hyperscale data center expansion (June 26, 2023).

  1. Hilliard Economic Development and Applicant Presentation Developer Representative transcribed from local broadcast report
    "possible location could be New Albany in January the company paid nearly 117 million dollars for Parcels on Beach Road Northwest near the Intel site since 2015 AWS has invested 6.3 billion dollars in Ohio supporting an average of more than 3 500 full time equivalent jobs annually we'll certainly have more on that major announcement tonight on"
May 8, 2023 Hilliard, OH "We are going to fight every step of the way" Hilliard residents oppose Amazon data center Hilliard City Council 3 clips

Hilliard City Council public hearing on resident opposition and school board revenue sharing for Amazon Web Services Community Reinvestment Area property tax abatements (May 8, 2023).

  1. WSYX ABC 6 Broadcast Report Broadcast Report transcribed from local broadcast report
    "it would be one of the top reasons to leave is this fuel cell and data centers. The AEP managed fuel cell plant will use natural gas to help produce energy, putting in a pipeline that will produce multiple gaseous chemicals as a byproduct. But the concern goes beyond just pollution. Like, will that cause problems with gas or emissions or explosions or ruin the food we're eating? The Ohio EPA has signed off on the project, while concern has expanded to"
  2. WSYX ABC 6 Broadcast Report Broadcast Report transcribed from local broadcast report
    "fight the best we can, appeal the EPA decision, which was still in the appealable period, and file what we can and really examine the process that was done. Data center plans originally enticing to the city, now it's different. When Amazon first came, they were a good business partner. They're in our schools, they've got the lab, but they've gotten away from that. With the project originally up to a review, citing a state statute, AEP removed city oversight site requirements, proceeding"
  3. Resident public comment Resident Public Comment transcribed from local broadcast report
    "with approval just from the state. A city councilor telling me that's to avoid community accountability. Yeah, they saw it coming. They saw the fact that they could the planning and zoning commission even saw it that hey, this isn't been vetted. While the project is set to begin construction in January, appeals have been put in by city and community members, saying the future will look the same for both the city and its community. Honestly, we are going to"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Cologix lists Cologix COL1, Cologix COL2, Cologix COL3, Cologix COL4, Cologix COL5, Cologix COL7, Cologix COL8 at Columbus, Ohio on its own page of data center locations, read September 14, 2026.

    [1] cologix.com

Nearest data centers in Ohio

Verified data center records in Ohio within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Centersquare Columbus data center Delaware County 4 mi Running Centersquare 1 building
Expedient Columbus - Upper Arlington Upper Arlington, Franklin County 6 mi Running Expedient 1 building
Expedient Columbus - Dublin Dublin, Franklin County 8 mi Running Expedient 1 building
QTS Data Centers New Albany New Albany, Franklin County 11 mi Being built QTS Data Centers 4 buildings
Amazon Sunbury data center campus Sunbury, Delaware County ~11 mi Proposed Amazon Web Services
Edged New Albany data center New Albany, Franklin County 12 mi Running Edged 24 MW

Blank cell: not disclosed by any source on file.

Common questions about Cologix Columbus

Answered directly from the verified filings and local actions on this page.

Who is building Cologix Columbus?

Cologix is the developer. No construction contractor is named on the record yet.

How much power and water does Cologix Columbus say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Cologix Columbus stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Cologix: Data centers (opens in a new tab), Cologix, September 14, 2026
  2. EPA ECHO detailed facility report: Cologix (0125043211) (opens in a new tab), U.S. Environmental Protection Agency

Reporting

  1. Cologix Acquires DataCenter.BZ in Columbus, Ohio - Data Center Knowledge (opens in a new tab), Data Center Knowledge, May 30, 2024, news outlet
  2. Cologix and Lambda Launch First NVIDIA HGX B200-Accelerated AI Clusters in Columbus at COL4 - The Manila Times (opens in a new tab), The Manila Times, June 3, 2025, international outlet
  3. Cologix to build a new 40MW data on greenfield land in Columbus Ohio - Data Center Dynamics (opens in a new tab), Data Center Dynamics, March 3, 2021, news outlet
  4. Cologix to build $130 million data center on Far North Side - dispatch.com (opens in a new tab), dispatch.com, September 7, 2016, local outlet
  5. Cologix sets $130M data center expansion in Columbus, tripling capacity at major internet traffic hub - The Business Journals (opens in a new tab), The Business Journals, September 7, 2016, local outlet
  6. Cologix Building $130M Data Center in Growing Columbus Metro - Data Center Knowledge (opens in a new tab), Data Center Knowledge, September 7, 2016, news outlet
  7. Cologix announces $130m data center expansion in Columbus - Data Center Dynamics (opens in a new tab), Data Center Dynamics, September 8, 2016, news outlet
  8. Lambda and Cologix launch Nvidia HGX B200 clusters in Columbus, Ohio - Data Center Dynamics (opens in a new tab), Data Center Dynamics, June 5, 2025, news outlet
  9. Cologix opens fourth Central Ohio data center - Columbus Business First - The Business Journals (opens in a new tab), The Business Journals, May 24, 2024, local outlet
  10. Cologix completes work on COL4 data center in Columbus, Ohio - Data Center Dynamics (opens in a new tab), Data Center Dynamics, May 24, 2024, news outlet
  11. Columbus Cologix data center to house Lambda's AI computing installation worth "hundreds of millions" - The Business Journals (opens in a new tab), The Business Journals, June 3, 2025, local outlet
  12. Cologix re-announces COL4 data center in Columbus, Ohio - Data Center Dynamics (opens in a new tab), Data Center Dynamics, August 30, 2022, news outlet
4 more sources
  1. Cologix Expands Central Ohio Footprint with Completion of AI-Ready Data Center in Columbus - Data Center Frontier (opens in a new tab), Data Center Frontier, May 24, 2024, news outlet
  2. Supermicro & Lambda Deploy GPU Servers at Cologix - Quantum Zeitgeist (opens in a new tab), Quantum Zeitgeist, August 25, 2025, news outlet
  3. Cologix is the First Colocation Provider to Complete an AI-Ready Data Center in Columbus - GlobeNewswire (opens in a new tab), GlobeNewswire, May 23, 2024, press release
  4. Cologix Data Center Pact Supercharges AI for the Columbus, Ohio Region - Data Center Frontier (opens in a new tab), Data Center Frontier, June 11, 2025, news outlet

18 sources on file.

Regional grid context

This site is in the RFC West (RFCW) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Cologix Columbus", https://datacenterrecord.org/projects/cologix-columbus-oh, last verified October 25, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Cologix Columbus", https://datacenterrecord.org/projects/cologix-columbus-oh. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
reviewed in depth
Tags
Reviewed in depth
Coordinates
40.11656, -83.00258
How the location is known
Location from an EPA facility record.
Location source
https://echo.epa.gov/detailed-facility-report?fid=110071706391
Coordinate source
https://echo.epa.gov/detailed-facility-report?fid=110071706391
Location source number
[2]
Location last verified
October 4, 2026
EPA registry id
110071706391
Published
September 14, 2026
Last verified
October 25, 2026
Not disclosed
Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Cologix Columbus · 18 sources, 1 entry · basis and source tier on every row · verified October 25, 2026