Data centers in Baltimore city, Maryland
Baltimore city has 3 data centers on the record: 3 running. No county rule about data centers is on the record for Baltimore city itself; Baltimore City, inside it, decides new data centers one at a time. The latest decision on the record: City Council discussed data center pros and cons during a Public Health and Environment Committee hearing (Baltimore City), reported September 24, 2026.
The 3 data centers in Baltimore city
Every Baltimore city record 3 records · blank cell: not disclosed · sort by any column
| Facility and county | Stage | Operator | Power (MW) | Latest entry | Basis | Located | Tier | Verified |
|---|---|---|---|---|---|---|---|---|
| Lumen Technologies Baltimore Carrier Hotel Data Center Baltimore, Baltimore city | Running Maryland Department of the Environment Stationary Emergency Generator and Commercial Facility Record (300 West Lexington Street, Baltimore, MD 21201) | Lumen Technologies | 6 | the developer's figure | site | 1 | 2026-11-06 | |
| Zayo and Candler Building Baltimore Carrier Hotel (111 Market Place) Baltimore, Baltimore city | Running Maryland Department of the Environment Stationary Emergency Generator and Commercial Facility Record (111 Market Place, Baltimore, MD 21202) | Zayo Group | 6 | the developer's figure | site | 1 | 2026-11-06 | |
| TierPoint Baltimore Russell Street Data Center Baltimore, Baltimore city | Running | TierPoint | 6 | the developer's figure | site | 2 | 2026-10-27 |
Blank cell: not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.
The cities in Baltimore city on the record (2)
| City | Census GEOID | Projects | Rules | How it treats data centers |
|---|---|---|---|---|
| Baltimore | 2404000 | 0 | ||
| Baltimore City | 2404000 | 1 |
A blank rating cell means no person has set one for the city. A city without a record is listed, not linked.
What Baltimore city has decided 1 body, 3 decisions on the record
What the county and the cities in it have done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement one tap away, newest first, with its source.
| Body | Level | Rating | In force until | Latest act | Acts | Verified |
|---|---|---|---|---|---|---|
| Baltimore City | city | Baltimore has staunched the creation of data centers within city limits. baltimoresun.com (opens in a new tab) local outlet Sep 24, 20263 acts on this rowEvery act on the Baltimore City row
| 3 | 2026-09-24 |
Reported: the source's date; the item names no day of its own. A month with no day: the source names the month and not the day. A rating rests only on a binding act in force; "not rated" means no person has set one. Blank cell: no end date or count on the record for that column.
The rules across Maryland · Report missing data or a local act
What happened
-
HearingBaltimore City
baltimoresun.com (opens in a new tab) local outlet -
MoratoriumBaltimore City
wmar2news.com (opens in a new tab) local outlet -
MoratoriumBaltimore City
Baltimore city bill proposed to pause data center construction
wbaltv.com (opens in a new tab) local outlet
Nearby places with records
Distances run between the centers the Census Bureau gives each place. Every Maryland county.
Disclosed figures
18 MW power
Power, water, jobs and tax
| Figure | Disclosed total | Disclosed | Without a figure | Basis |
|---|---|---|---|---|
| Power | 18 MW | 3 | 0 | 3 the developer's figure |
| Water, stated per day | 0 | 3 | ||
| Water, stated per year | 0 | 3 | ||
| Permanent jobs | 0 | 3 | ||
| Tax each year | 0 | 3 |
A blank total means no record disclosed the figure; the count without one says how many.
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
By what the facilities are for
| Use | Records | Power | Water | Jobs | Tax each year |
|---|---|---|---|---|---|
| No stated use | 3 | 18 MW |
A blank cell means no record with that use disclosed the figure.
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
What the facilities are for
No source on file states what any of the 3 tracked facilities in Baltimore city are for.
How the facilities are cooled
No source on file states how any of the 3 tracked facilities in Baltimore city are cooled.
About this data
Report a correction · Send a tip about Baltimore city · The rows here are part of the Maryland export.
Cite this page
Data Center Record, "Data center records in Baltimore city, Maryland", https://datacenterrecord.org/states/md/baltimore-city. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.
For researchers
- Level
- county
- Census GEOID
- 24510
- Census geography
- County, Baltimore city
- Rating
- Not rated