Data centers in Louisville, Kentucky
Louisville has 3 data centers on the record: 2 running and 1 proposed. Louisville limits new data centers, and a pause on new data centers is on the record. The latest decision on the record: Louisville has implemented an active moratorium on data center projects, reported October 1, 2026. Jefferson County's own decisions are on the Jefferson County page.
The 3 data centers in Louisville
Every Louisville record 3 records · blank cell: not disclosed · sort by any column
| Facility and county | Stage | Operator | Power (MW) | Latest entry | Basis | Located | Tier | Verified |
|---|---|---|---|---|---|---|---|---|
| Flexential Louisville Downtown Campus (LOU02 / LOU03 / LOU04) Louisville, Jefferson County | Running Kentucky Energy and Environment Cabinet and Louisville Metro APCD Stationary Emergency Generator Permit (NAICS 518210, 752 Barret Ave, Louisville, KY 40204) | Flexential | EPA registry | 1 | 2026-10-21 | |||
| Flexential Louisville East (LOU05) Louisville, Jefferson County | Running Kentucky Energy and Environment Cabinet and Louisville Metro APCD Stationary Emergency Generator Permit (NAICS 518210, 2101 Nelson Miller Pkwy, Louisville, KY 40223) | Flexential | EPA registry | 1 | 2026-10-21 | |||
| West Louisville Data Center Louisville, Jefferson County | Proposed | PowerHouse Data Centers and Poe Companies proposed a 550 acre data center campus near Louisville, Jefferson County, Kentucky. datacenterdynamics.com (opens in a new tab) trade press July 15, 2026 | centroid | 3 | 2026-09-17 |
Blank cell: not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.
What Louisville has decided 1 body, 7 decisions on the record
What the city has done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement one tap away, newest first, with its source.
| Body | Level | Rating | In force until | Latest act | Acts | Verified |
|---|---|---|---|---|---|---|
| Louisville | city | until February 14, 2027 | 2027-02-14 | Louisville mayor signs 6 month moratorium on new data center projects on August 14, 2026. wdrb.com (opens in a new tab) local outlet Aug 14, 20267 acts on this rowEvery act on the Louisville row
| 7 | 2026-10-01 |
Reported: the source's date; the item names no day of its own. A rating rests only on a binding act in force; "not rated" means no person has set one. Blank cell: no end date or count on the record for that column.
January 20, 2025 Louisville, KY Louisville to welcome Kentucky’s first Hyperscale Data Center
WAVE News - Louisville, KY report on Louisville City Council and community proceedings in Louisville, KY: Louisville to welcome Kentucky’s first Hyperscale Data Center (January 20, 2025).
- WAVE News - Louisville, KY Broadcast Report Broadcast Report transcribed from local broadcast report
"the future. Reporter this is the site that is expected to be developed with that data center, 150 acres off of Campground Road. The developer tells us that it will bring hundreds of jobs and the booming tech industry to the city. This is going to be the first one of these types of projects in Kentucky. How companies announced this week plans for a hyperscale data center in southwest Louisville. The head of the company, Hank Hildebrand, says the project will provide cloud storage, artificial intelligence, computing and other"
- Resident public comment Resident Public Comment transcribed from local broadcast report
"dollars in tax revenue every year. Data centers across the globe connect billions of people with numerous services like Facebook. Times have changed, and we are now driven by technology. It was January last year when it was announced meta would be bringing a similar data center to Jeffersonville, Indiana. That facility is also expected to be complete next year. Hildebrand says while it's unclear which company will utilize the"
Using this data in a report? Support the record.
The rules across Kentucky · Report missing data or a local act
What happened
-
Moratorium adoptedLouisville
Louisville has implemented an active moratorium on data center projects.
wlky.com (opens in a new tab) local outlet -
OrdinanceLouisville
lpm.org (opens in a new tab) local outlet -
Scorecard eventLouisville
lpm.org (opens in a new tab) local outlet -
HearingLouisville
lpm.org (opens in a new tab) local outlet -
StatementLouisville
Louisville Planning Commission recommended stricter data center regulations
lpm.org (opens in a new tab) local outlet -
Scorecard eventLouisville
courier-journal.com (opens in a new tab) news outlet
What was said
District 3 Council Member Shameka Parrish Wright agreed with Hawkins in opposing data center development
District 1 Council Member Tammy Hawkins expressed concerns about the potential environmental and health impacts of data centers, particularly for her West End constituents where a hyperscale data center is already being built
Beshear said that any data center in Kentucky would have to pay for all of its own power
The county and nearby counties
Distances run between the centers the Census Bureau gives each place. Every Kentucky county.
Disclosed figures
nothing disclosed by 3 records
Power, water, jobs and tax
| Figure | Disclosed total | Disclosed | Without a figure | Basis |
|---|---|---|---|---|
| Power | 0 | 3 | ||
| Water, stated per day | 0 | 3 | ||
| Water, stated per year | 0 | 3 | ||
| Permanent jobs | 0 | 3 | ||
| Tax each year | 0 | 3 |
A blank total means no record disclosed the figure; the count without one says how many.
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
By what the facilities are for
| Use | Records | Power | Water | Jobs | Tax each year |
|---|---|---|---|---|---|
| No stated use | 3 |
A blank cell means no record with that use disclosed the figure.
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
What the facilities are for
No source on file states what any of the 3 tracked facilities in Louisville are for.
How the facilities are cooled
No source on file states how any of the 3 tracked facilities in Louisville are cooled.
About this data
Report a correction · Send a tip about Louisville · The rows here are part of the Kentucky export.
Cite this page
Data Center Record, "Data center records in Louisville, Jefferson County, Kentucky", https://datacenterrecord.org/states/ky/jefferson-county/louisville. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.
For researchers
- Level
- city
- Census GEOID
- 2148000
- Census geography
- Incorporated place, Louisville city
- Rating
- Restrictive