Kentucky governor
Beshear said that any data center in Kentucky would have to pay for all of its own power
A proposed data center in west Louisville was placed on hold during a zoning review. It is reported; the record holds no sourced date for when it reached that stage.
How much power it needs, how much water it would use and who would use it have not been disclosed.
How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.
Each figure as its source gave it. The number in brackets is its place in the source list.
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| How much power it needs | Not disclosed | |||
| How much water it would use | Not disclosed | |||
| How loud it would be | Not disclosed | |||
| Jobs once it runs | Not disclosed | |||
| Tax it would pay each year | Not disclosed |
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| Who is building it | Not disclosed | |||
| Who is constructing it | Not disclosed | |||
| How much land | Not disclosed | |||
| Where its power comes from | Not disclosed | |||
| Grid connection | Not disclosed | |||
| How it is cooled | Not disclosed |
How much power it needs, also reported: 154 acres, 2026 (Yahoo: Proposed hyperscale data center campus on Camp Ground Road, Louisville, by PowerHouse Data Centers and Poe Companies, approximately 154 acres, 1.8 million square feet, hundreds of megawatts capacity) .
The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.
The record adds each the day a source gives it. Why these documents.
Acts of Jefferson County and Louisville about data centers, on the record with their source. A rule about the area is not a decision about this record.
| Date | Who | Decision | Source |
|---|---|---|---|
| Louisville | Louisville Planning Commission recommended rules prohibiting future hyperscale data centers | yahoo.com | |
| Louisville | The Planning and Zoning Committee is scheduled to meet again in two weeks | lpm.org | |
| Louisville | Planning Commission recommended requiring rezoning for most data center projects to allow scrutiny by Planning Commission and Metro Council with public comment opportunities | lpm.org | |
| Louisville | Planning Commission recommended requiring data centers to use closed loop cooling systems that utilize less water | lpm.org | |
| Louisville | Any new data centers would need to be at least a quarter mile from nearby schools, community centers and other data centers | lpm.org | |
| Louisville | Planning Commission recommendations include a ban on data centers with more than 500,000 square feet of equipment | lpm.org |
| Date | Who | Decision | Source |
|---|---|---|---|
| Louisville | There is currently a moratorium on new data center approvals in Jefferson County until February or whenever Metro Council passes new regulations | lpm.org | |
| Louisville | Louisville Metro Council debated proposed regulations for data center construction for the first time Tuesday during its Planning and Zoning Committee meeting | lpm.org | |
| Louisville | Louisville Planning Commission recommended stricter data center regulations | lpm.org | |
| Louisville | Louisville advanced stricter data center rules | courier-journal.com | |
| Louisville | Louisville mayor signs 6 month moratorium on new data center projects on 2026-08-14 | wdrb.com |
No dated entry is on the record yet.
· the kind of source of a history entry
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.
Every correction on the record is on the corrections page.
District 3 Council Member Shameka Parrish Wright agreed with Hawkins in opposing data center development
District 1 Council Member Tammy Hawkins expressed concerns about the potential environmental and health impacts of data centers, particularly for her West End constituents where a hyperscale data center is already being built
Every statement about data centers in Kentucky, by speaker
Kentucky governor
Beshear said that any data center in Kentucky would have to pay for all of its own power
Where in Jefferson County is not in the public record. The pin marks the county seat, not a building, and the outline is the county.
Tap a pin for the data center, the parcel for its record
The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.
Not disclosed. No source on file gives its capacity, its acreage or a count of buildings. What the record holds instead is under Disclosed.
Not disclosed. No source on file names the developer. The sources read for this record are listed under Sources.
Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
It is reported; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.
Louisville: Louisville Planning Commission recommended rules prohibiting future hyperscale data centers (reported September 18, 2026, source); and Louisville: The Planning and Zoning Committee is scheduled to meet again in two weeks (reported September 15, 2026, source). 11 events are on the county's rows; a rule about the area is not a decision about this record.
Not disclosed by any source on file: how much power it needs, how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is building it, who is constructing it, how much land, where its power comes from, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.
2 sources on file.
Data Center Record, "West Louisville Data Center", https://datacenterrecord.org/projects/west-louisville-data-center-ky, last verified September 17, 2026.
Data Center Record, "West Louisville Data Center", https://datacenterrecord.org/projects/west-louisville-data-center-ky. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.
The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.