Data centers in Allen County, Indiana

Allen County has 1 data center on the record; it is running. No county rule about data centers is on the record for Allen County itself; 1 body inside it has a scorecard row. The latest decision on the record: Fort Wayne City Council delays decision on data center moratorium by three weeks (Fort Wayne), September 23, 2026.

Updated · Every line below links to its source · How the record works

How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.

The data center in Allen County

Each row is one site with its stage, its latest dated entry and what its sources disclose. A figure no source gives reads Not disclosed.

  1. Running Built from one source

    Google Fort Wayne data center

    Fort Wayne, Allen County · Google

    Latest, reported September 23, 2026: Google data center under construction on Adams Center Road in southeast Fort Wayne is exempt from proposed moratorium legislation wboi.org local outlet

    Land
    900 acresthird party estimate
    Power
    Not disclosed
    Water
    Not disclosed
    Tenant
    Not disclosed

Where

1 data center in Allen County: running. A dashed edge means the exact site is not in the public record; every pin here marks a town or the county.

The outline is Allen County's boundary from the U.S. Census Bureau. Tap a pin for that data center's facts and a link to its page.

The cities in Allen County on the record (1)

1 of 1 city has a record. A city without one is listed, not linked, until its first published record.

CityProjectsRules
Fort Wayne11

What Allen County has decided

1 body, 2 decisions on the record

What the county and the cities in it have done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement behind its toggle, newest first, with its source.

Reported: the source's date; the item names no day of its own.

  1. Fort Wayne City Council delays decision on data center moratorium by three weeks, reported September 23, 2026.

    wboi.org local outlet

    no published rating
    2 acts on this row
    1. moratorium

      Fort Wayne City Council delays decision on data center moratorium by three weeks

      wboi.org local outlet

    2. moratorium

      Fort Wayne City Council held vote on one year data center moratorium and postponed final vote to October 13, 2026

      journalgazette.net local outlet

      Also reported by 1 source

    Last verified September 23, 2026.

The rules across Indiana.

What happened

  1. · Fort Wayne

    Moratorium: Fort Wayne City Council delays decision on data center moratorium by three weeks wboi.org local outlet

  2. · Fort Wayne

    Moratorium: Fort Wayne City Council held vote on one year data center moratorium and postponed final vote to October 13, 2026 journalgazette.net local outlet

  3. · Google Fort Wayne data center

    Went live: Google held an open house on August 21 to discuss data center project fwbusiness.com local outlet

Indiana, year by year · Every milestone, by month

What was said

Councilwoman Rohli Booker introduced ordinance creating committee and moratorium on data centers
Rohli Booker, Fort Wayne City Councilwoman · September 23, 2026 · paraphrased · WBOI local outlet
Broderick Green, Public Affairs Manager for the Google Data Center, says company should have shared information earlier
Broderick Green, Public Affairs Manager for the Google Data Center · December 11, 2025 · paraphrased · WPTA | 21Alive | Fort Wayne, IN local outlet
Blaine Sefton, forum attendee, expresses frustration with offloading questions to website and email
Blaine Sefton, forum attendee · December 11, 2025 · paraphrased · WPTA | 21Alive | Fort Wayne, IN local outlet

Every Indiana statement, by speaker

5 more statements on this page

Google says the generators will use ultra low sulfur diesel or a renewable alternative.

September 22, 2026, 963xke.com · 963xke.com local outlet · the record (Paraphrased; said in the source itself)

via spokesperson

Google says new generators are strictly for emergency operations and legally mandated maintenance checks.

September 21, 2026, WBOI · WBOI local outlet · the record (Paraphrased; said in the source itself)

Geoff Paddock, Councilman, says Google employees live in Fort Wayne with families and will be part of the community

December 11, 2025, WPTA | 21Alive | Fort Wayne, IN · WPTA | 21Alive | Fort Wayne, IN local outlet · the record (Paraphrased; said in the source itself)

Director of Economic Development at Indiana Michigan Power

Ashley Savieo, Director of Economic Development at I&M, says Google data center is not causing rates to increase and I&M has ample capacity

December 11, 2025, WPTA | 21Alive | Fort Wayne, IN · WPTA | 21Alive | Fort Wayne, IN local outlet · the record (Paraphrased; said in the source itself)

Matthew Wirtz, Deputy Director of Engineering at City Utilities, says City Utilities has capacity and ability to serve Google

December 11, 2025, WPTA | 21Alive | Fort Wayne, IN · WPTA | 21Alive | Fort Wayne, IN local outlet · the record (Paraphrased; said in the source itself)

Disclosed figures

nothing disclosed by 1 record

Power, water, jobs and tax, summed only where a data center disclosed the figure; what each facility is for; how each is cooled. Nothing here is estimated.

Power, water, jobs and tax

FigureDisclosed totalDisclosedNot disclosedBasis
PowerNot disclosed01Not disclosed by any of the 1 record
Water, stated per dayNot disclosed01Not disclosed by any of the 1 record
Water, stated per yearNot disclosed01Not disclosed by any of the 1 record
Permanent jobsNot disclosed01Not disclosed by any of the 1 record
Tax each yearNot disclosed01Not disclosed by any of the 1 record

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

By what the facilities are for

UseRecordsPowerWaterJobsTax each year
Not disclosed1Not disclosedNot disclosedNot disclosedNot disclosedNot disclosed: power, water, jobs, tax each year

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

What the facilities are for

No source on file states what any of the 1 tracked facility in Allen County is for.

How the facilities are cooled

No source on file states how any of the 1 tracked facility in Allen County is cooled.

Cite this page

Data Center Record, "Data centers in Allen County, Indiana", https://datacenterrecord.org/states/in/allen-county, updated October 6, 2026.

Cite this page

Data Center Record, "Data center records in Allen County, Indiana", https://datacenterrecord.org/states/in/allen-county. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.

The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change

The rows here are part of the Indiana export.