Census GEOID: 18003 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 2 primary and 33 reporting sources

● Running Reported August 21, 2026 · 12 Buildings

Google Fort Wayne data center

Street address 7025 Adams Center Road, Fort Wayne, IN 46816, Allen County verified address Exact, at the address [2] Google: Data center locations

Overview, regulatory gates and specifications

Google operates a 12 building hyperscale data center campus at 7025 Adams Center Road in Fort Wayne, Allen County, Indiana. [3] Filings on the record specify disclosed capacity of 400 MW (the developer's figure). [2] Google data center under construction on Adams Center Road in southeast Fort Wayne is exempt from proposed moratorium legislation [30]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Not yet on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [2]
400 MW
the developer's figure

Equivalent to ~332,000 U.S. homes (U.S. EIA 830 homes/MW baseline) · 19% of Hoover Dam nameplate capacity (2,080 MW).

Electric utility: ultra-low sulfur diesel or Hydrotreated Vegetable Oil (HVO).

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [2]
12 buildings
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 7025 Adams Center Road, Fort Wayne, IN 46816.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
400 MW developer figure Equivalent to the continuous electricity demand of about 332,000 average U.S. homes based on U.S. Energy Information Administration residential consumption data. About 4 percent of New York City's summer peak demand in 2024.
[2] datacenters.google
Water usage
Not disclosed
Land area
Not disclosed
Buildings
12 buildings operator page
[2] datacenters.google
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2025 (1 year)
Who leads it
Google as stated by the source
Where its power comes from
ultra-low sulfur diesel or Hydrotreated Vegetable Oil (HVO) as stated by the source
[33] 21alivenews.com
Official project website
datacenters.google (opens in a new tab) verified October 28, 2026
datacenters.google (opens in a new tab)
Archived promotional websites
datacenters.google (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Google Fort Wayne data center, capacity: 400 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 400 ÷ 10,245 = 0.04 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Marlin Stutzman

Marlin Stutzman

Congressman · Indiana

DID Recorded statement at WOWO (October 15, 2026)
SAID Stutzman said data center operators should provide their own power and pay those costs upfront instead of receiving substantial tax abatements and write offs at the beginning of a project (October 15, 2026) wowo.com (opens in a new tab)

Rohli Booker

Fort Wayne City Councilwoman

DID Recorded statement at WBOI (September 23, 2026) [30]
SAID Councilwoman Rohli Booker introduced ordinance creating committee and moratorium on data centers (September 23, 2026) [30]

Google

Public Record Speaker

DID Recorded statement at 963xke.com (September 22, 2026) [31]
SAID Google says the generators will use ultra low sulfur diesel or a renewable alternative. (September 22, 2026) [31]

Blaine Sefton

forum attendee

DID Recorded statement at WPTA | 21Alive | Fort Wayne, IN (December 11, 2025)
SAID Blaine Sefton, forum attendee, expresses frustration with offloading questions to website and email (December 11, 2025) 21alivenews.com (opens in a new tab)

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Google · Parent: Alphabet
UTILITIES
Electric utility: ultra-low sulfur diesel or Hydrotreated Vegetable Oil (HVO)

View all 11 statements on the record in Indiana →

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Google Fort Wayne data center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 400 MW 400 MW the developer's figure [2] datacenters.google
Site Footprint (Acres)
Data Hall Buildings 12 buildings 12 operator page [2] datacenters.google
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. Moratorium (source date; the content gives no date of its own)

    Google data center under construction on Adams Center Road in southeast Fort Wayne is exempt from proposed moratorium legislation

    [30] wboi.org

  2. (source date; the content gives no date of its own)

    Google's data center was first proposed as Project Zodiac and officially announced in spring 2024

    [32] journalgazette.net

  3. (source date; the content gives no date of its own)

    Earlier permit included 140 emergency generators, five smaller generators, dozens of diesel fuel tanks and nearly 50 cooling towers

    [29] inkfreenews.com

  4. (source date; the content gives no date of its own)

    Google filed request for 228 additional diesel generators at Fort Wayne data center

    [29] inkfreenews.com

  5. (source date; the content gives no date of its own)

    IDEM approved request in April to increase backup generators from 34 to 179.

    [34] 1039waynefm.com

  6. (source date; the content gives no date of its own)

    IDEM approved Google's request in April 2026 to increase backup generators from 34 to 179.

    [31] 963xke.com

  7. Air permit review (source date; the content gives no date of its own)

    Google filed an air permit modification application in September 2026 requesting 228 more generators at the Fort Wayne data center.

    [31] 963xke.com

  8. (source date; the content gives no date of its own)

    IDEM approved previous air permit modification in April allowing more than 140 additional emergency generators

    [26] wowo.com

17 earlier entries
  1. (source date; the content gives no date of its own)

    In September of last year, IDEM approved a similar request to fill more than two acres of wetlands in an earlier expansion phase.

    [33] 21alivenews.com

  2. (source date; the content gives no date of its own)

    The department approved developers' request to fill just over two acres of wetlands earlier this month.

    [33] 21alivenews.com

  3. (source date; the content gives no date of its own)

    IDEM first approved 34 main diesel generators for the project back in 2024.

    [33] 21alivenews.com

  4. (source date; the content gives no date of its own)

    In April, IDEM approved a request to add more than 140 emergency diesel generators to the data center campus.

    [33] 21alivenews.com, also [26] wowo.com

  5. Filing (source date; the content gives no date of its own)

    Google submitted a request to the Indiana Department of Environmental Management to add 228 emergency generators to its Fort Wayne data center.

    [33] 21alivenews.com

  6. (source date; the content gives no date of its own)

    Google must not clear trees at Fort Wayne data center from April 1 to September 30 to protect federally protected Indiana bat habitat.

    [25] wboi.org

  7. (source date; the content gives no date of its own)

    Google must purchase wetland credits from Openings Wetland Mitigation Bank and Indiana Stream and Wetland Mitigation Program to mitigate wetland impact.

    [25] wboi.org

  8. (source date; the content gives no date of its own)

    IDEM approved Google's request to fill in additional four acres of wetlands on Fort Wayne data center property.

    [25] wboi.org

  9. (source date; the content gives no date of its own)

    This is Google's third air permit modification for the Fort Wayne data center since introduction.

    [25] wboi.org

  10. (source date; the content gives no date of its own)

    Original request for Fort Wayne data center was 34 diesel generators.

    [25] wboi.org

  11. (source date; the content gives no date of its own)

    Google requests 228 additional diesel emergency generators for Fort Wayne data center on top of 174 existing generators.

    [25] wboi.org

  12. (source date; the content gives no date of its own)

    Google filed request for 200+ additional emergency generators at Fort Wayne data center

    [28] wndu.com

  13. (source date; the content gives no date of its own)

    Google received approval to add 140+ generators at Fort Wayne data center five months prior to this new request

    [27] insideindianabusiness.com

  14. (source date; the content gives no date of its own)

    Google submitted request for 200+ additional backup generators at Fort Wayne data center

    [27] insideindianabusiness.com

  15. (source date; the content gives no date of its own)

    Developers must provide proof of purchase for wetland credits within one year

    [24] ipm.org

  16. (source date; the content gives no date of its own)

    Developers must purchase 4.26 acres of forested wetland mitigation

    [24] ipm.org

  17. · running (source date; the content gives no date of its own)

    Google held an open house on August 21 to discuss data center project

    [35] fwbusiness.com

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Google lists Google Fort Wayne data center at Fort Wayne, Indiana on its own page of data center locations, read September 14, 2026.

    [2] datacenters.google

Nearest data centers in Indiana

Verified data center records in Indiana within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Lifeline Data Centers Fort Wayne Fort Wayne, Allen County 5 mi Running Lifeline Data Centers 6 MW

Blank cell: not disclosed by any source on file.

Comparisons

2 metrics with more than one figure

Every figure on the record for the same thing, each with who gave it, its date and its basis.

Permanent jobs

1 figure, 1 source
Show each source's words
  • 200 jobs, InkFreeNews.com: Google expects facility to add about 200 jobs as operations expand

Tax each year

1 figure, 1 source
1,000,000 USD Reported

The Journal Gazette, Sep 23, 2026

Show each source's words
  • 1,000,000 USD, The Journal Gazette: Google's data center is top 10 taxpayer for the county and all tax increment financing revenue would be used for southeast development with only $1 million used so far

Common questions about Google Fort Wayne data center

Answered directly from the verified filings and local actions on this page.

Who is building Google Fort Wayne data center?

Google is the developer. No construction contractor is named on the record yet.

Who will use Google Fort Wayne data center?

Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.

How much power and water does Google Fort Wayne data center say it needs?

Power: 400 MW (the developer's figure, datacenters.google (opens in a new tab)). Water: not disclosed by any source on file.

Where does Google Fort Wayne data center stand today?
What is still unknown about Google Fort Wayne data center?

Not disclosed by any source on file: how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is constructing it, how much land, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. City of Fort Wayne, Greater Fort Wayne Inc. to Host Community Information Forum About Google - Fort Wayne City (.gov) (opens in a new tab), Fort Wayne City (.gov), December 8, 2025
  2. Google: Data center locations (opens in a new tab), Google, September 14, 2026

Reporting

  1. Google data center’s third phase under environmental review - WANE 15 (opens in a new tab), WANE 15, March 16, 2026, local outlet
  2. Fort Wayne resident, expert question Google data center website claims - WPTA | 21Alive | Fort Wayne, IN (opens in a new tab), WPTA | 21Alive | Fort Wayne, IN, February 25, 2026, local outlet
  3. Representatives from Google, Indiana Michigan Power, and City of Fort Wayne hold public forum on data center - WANE 15 (opens in a new tab), WANE 15, December 11, 2025, local outlet
  4. Google to fund water tower for data center use, public comment accepted - WANE 15 (opens in a new tab), WANE 15, December 29, 2025, local outlet
  5. ‘Political malpractice’: City Council holds off approving drainage for new Google data center - WANE 15 (opens in a new tab), WANE 15, December 9, 2025, local outlet
  6. Fort Wayne’s Google data center launches website - WANE 15 (opens in a new tab), WANE 15, February 17, 2026, local outlet
  7. City to hold public forum to inform community about Google data center - WANE 15 (opens in a new tab), WANE 15, December 8, 2025, local outlet
  8. Google explains upcoming water vapor near Fort Wayne data center - WPTA | 21Alive | Fort Wayne, IN (opens in a new tab), WPTA | 21Alive | Fort Wayne, IN, July 20, 2026, local outlet
  9. Advocates protest Google Data Center amid energy cost, public health concerns - WPTA | 21Alive | Fort Wayne, IN (opens in a new tab), WPTA | 21Alive | Fort Wayne, IN, November 18, 2025, local outlet
  10. Google inks demand response deal with Midwest utility to support grid reliability - Renewable Energy World (opens in a new tab), Renewable Energy World, August 4, 2025, news outlet
  11. 61526 Fort Wayne leader addresses city council member’s Google data center resolutions, highlights misinformation - WPTA | 21Alive | Fort Wayne, IN (opens in a new tab), WPTA | 21Alive | Fort Wayne, IN, June 15, 2026, local outlet
  12. Indiana may lose acres of federally protected wetlands to Google's next data center phase - The Cool Down (opens in a new tab), The Cool Down, August 13, 2026, national outlet
21 more sources
  1. Google suffers setback in attempt to establish construction staging area in Allen County - The Journal Gazette (opens in a new tab), The Journal Gazette, April 16, 2026, local outlet
  2. Google to Work with Fort Wayne on Water Saving Project - WIBC 93.1 FM (opens in a new tab), WIBC 93.1 FM, May 2, 2026, local outlet
  3. Google creates website to address questions, concerns about Fort Wayne data center - WPTA | 21Alive | Fort Wayne, IN (opens in a new tab), WPTA | 21Alive | Fort Wayne, IN, February 17, 2026, local outlet
  4. Google requests permit for third phase of Fort Wayne data center - WPTA | 21Alive | Fort Wayne, IN (opens in a new tab), WPTA | 21Alive | Fort Wayne, IN, March 17, 2026, local outlet
  5. Google announces Fort Wayne data center is operational ahead of Thursday night community forum - WPTA | 21Alive | Fort Wayne, IN (opens in a new tab), WPTA | 21Alive | Fort Wayne, IN, December 11, 2025, local outlet
  6. Fort Wayne City Council shoots down drainage, asks Google to pay amid data center drama - WANE 15 (opens in a new tab), WANE 15, January 13, 2026, local outlet
  7. Google, I&M Strike Landmark Deal to Share Clean Capacity and Flex AI Load - POWER Magazine (opens in a new tab), POWER Magazine, August 6, 2025, news outlet
  8. $2 billion data center now operational in Fort Wayne, Google outlines its plans for the community - WANE 15 (opens in a new tab), WANE 15, December 11, 2025, local outlet
  9. Google plans public forum about Fort Wayne data center following calls from community, City leaders - WPTA | 21Alive | Fort Wayne, IN (opens in a new tab), WPTA | 21Alive | Fort Wayne, IN, December 8, 2025, local outlet
  10. IDEM approves data center request to fill in wetlands - Indiana Public Media (opens in a new tab), Indiana Public Media, September 15, 2026, local outlet
  11. Google says it needs more emergency generators at its Fort Wayne data center - WBOI (opens in a new tab), WBOI, September 21, 2026, local outlet
  12. Google submits new air permit application for additional Fort Wayne data center generators - wowo.com (opens in a new tab), wowo.com, September 21, 2026, local outlet
  13. Google seeks approval for over 200 backup generators at Fort Wayne data center - Inside INdiana Business (opens in a new tab), Inside INdiana Business, September 21, 2026, local outlet
  14. Google files request for 200+ additional emergency generators at Fort Wayne data center - WNDU (opens in a new tab), WNDU, September 21, 2026, local outlet
  15. Google Seeks Approval For 228 Backup Generators At Fort Wayne Data Center - InkFreeNews.com (opens in a new tab), InkFreeNews.com, September 23, 2026, news outlet
  16. Fort Wayne City Council delays decision on data center moratorium - WBOI (opens in a new tab), WBOI, September 23, 2026, local outlet
  17. Google wants 200+ more generators at Fort Wayne data center - 963xke.com (opens in a new tab), 963xke.com, September 22, 2026, news outlet
  18. Fort Wayne City Council takes some time to work on data center task force, moratorium - The Journal Gazette (opens in a new tab), The Journal Gazette, September 23, 2026, local outlet
  19. Google files request for 200+ additional emergency generators at Fort Wayne data center - WPTA | 21Alive | Fort Wayne, IN (opens in a new tab), WPTA | 21Alive | Fort Wayne, IN, September 21, 2026, local outlet
  20. Google wants 200+ more generators at Fort Wayne data center - 1039waynefm.com (opens in a new tab), 1039waynefm.com, September 22, 2026, news outlet
  21. Aug. 21: Google open house answers questions on data center | News - Fort Wayne Business Weekly (opens in a new tab), Fort Wayne Business Weekly, August 21, 2026, local outlet

35 sources on file.

Regional grid context

This site is in the RFC West (RFCW) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Google Fort Wayne data center", https://datacenterrecord.org/projects/google-fort-wayne-data-center-in, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Google Fort Wayne data center", https://datacenterrecord.org/projects/google-fort-wayne-data-center-in. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
41.0881396, -85.1426619
How the location is known
Location from the site's street address.
Location source
https://datacenters.google/locations/
Coordinate source
Google Fort Wayne specification and Allen County parcel record
Location last verified
September 14, 2026
How capacity was disclosed
the developer's figure
Capacity, if disclosed
400 MW, the developer's figure
Published
September 14, 2026
Last verified
October 27, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows