● 3 Facilities on Record 1 local rule row · 104 MW disclosed

Data centers in Sacramento, California

Sacramento has 3 data centers on the record: 3 running. Sacramento has a scorecard row with no rating yet. The latest decision on the record: Sacramento Mayor Kevin McCarty announces policy development for data center impacts on energy, water, and infrastructure, reported September 18, 2026. Sacramento County's own decisions are on the Sacramento County page.

The 3 data centers in Sacramento

Every Sacramento record 3 records · blank cell: not disclosed · sort by any column

Facility and county Stage Operator Power (MW) Latest entry Basis Located Tier Verified
NTT Global Data Centers Sacramento Campus (CA1, CA2, and CA3) Sacramento, Sacramento County Running NTT Global Data Centers 58 the developer's figure site 1 2026-10-27
QTS Sacramento Data Center Sacramento, Sacramento County Running QTS Data Centers 18 the developer's figure site 2 2026-10-27
Prime Data Centers Sacramento McClellan Campus (SAC01 and SAC02) Sacramento, Sacramento County Running Prime Data Centers 28 Prime Data Centers landed an 8 MW project in Sacramento, California. datacenterfrontier.com (opens in a new tab) news outlet April 20, 2021 the developer's figure site 1 2026-11-06

Blank cell: not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.

What Sacramento has decided 1 body, 1 decision on the record

What the city has done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement one tap away, newest first, with its source.

BodyLevelRatingIn force untilLatest actActsVerified
Sacramentocitynot ratedSacramento Mayor Kevin McCarty announces policy development for data center impacts on energy, water, and infrastructure. thecentersquare.com (opens in a new tab) national outlet Reported Sep 181 act on this row
Every act on the Sacramento row
  1. event

    Sacramento Mayor Kevin McCarty announces policy development for data center impacts on energy, water, and infrastructure

    thecentersquare.com (opens in a new tab) national outlet

Last verified September 18, 2026.

12026-09-18

Reported: the source's date; the item names no day of its own. A rating rests only on a binding act in force; "not rated" means no person has set one. Blank cell: no end date or count on the record for that column.

The rules across California · Report missing data or a local act

What happened

  1. Now proposedPrime Data Centers Sacramento McClellan Campus (SAC01 and SAC02)

    Prime Data Centers landed an 8 MW project in Sacramento, California.

California, year by year

The county and nearby counties

The county Sacramento County: its decisions and every record in it.
35 miles away Solano County: 1 data center on the record.
36 miles away San Joaquin County: 1 data center on the record. A pause is on the record.
37 miles away Amador County: 1 data center on the record.
49 miles away Contra Costa County: 1 data center on the record. A pause is on the record.

Distances run between the centers the Census Bureau gives each place. Every California county.

Disclosed figures

104 MW power

Power, water, jobs and tax, summed only where a data center disclosed the figure; what each facility is for; how each is cooled. Nothing here is estimated.

Power, water, jobs and tax

FigureDisclosed totalDisclosedWithout a figureBasis
Power104 MW303 the developer's figure
Water, stated per day03
Water, stated per year03
Permanent jobs03
Tax each year03

A blank total means no record disclosed the figure; the count without one says how many.

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

By what the facilities are for

UseRecordsPowerWaterJobsTax each year
No stated use3104 MW

A blank cell means no record with that use disclosed the figure.

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

What the facilities are for

No source on file states what any of the 3 tracked facilities in Sacramento are for.

How the facilities are cooled

No source on file states how any of the 3 tracked facilities in Sacramento are cooled.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Only what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Data centers in Sacramento, Sacramento County, California", https://datacenterrecord.org/states/ca/sacramento-county/sacramento, updated November 6, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Data center records in Sacramento, Sacramento County, California", https://datacenterrecord.org/states/ca/sacramento-county/sacramento. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Level
city
Census GEOID
0664000
Census geography
Incorporated place, Sacramento city
Rating
Not rated

Researcher view · Sacramento, Sacramento County, California · 3 records, 1 rule row · Census GEOID 0664000 · basis and source tier on every row · verified November 6, 2026