Yukon Data Center

Location Yukon, Canadian County, Oklahoma county centroid County level, the county seat

Overview, regulatory gates and specifications

Yukon, Oklahoma city leaders were still deliberating on a proposed data center as of July 28, 2026. [1] Beltline Energy is the developer of the proposed data center [2]

1. Land & Parcel
Location tracked
2. Local Zoning
Not yet on file
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Not yet on file
5. Air & Water Permits
Not yet on file
What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings
Not disclosed
Acreage not stated in public filings yet

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Parcel boundaries and municipal zoning tracked.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
Not disclosed
Backup generators
Not disclosed
Capital investment
Not disclosed
Not disclosed
Who leads it, Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Charles S.

Yukon resident

DID Recorded statement at KGOU (August 5, 2026)
SAID Resident Charles S. stated the community does not want data centers during city council comment period (August 5, 2026) kgou.org (opens in a new tab)

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Not disclosed
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Yukon Data Center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Who is behind it A land record, a zoning application or a company's own announcement.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

August 24, 2026 Piedmont, OK Piedmont City Council Data Center Rezoning Hearing Piedmont City Council 3 clips

At a packed late night meeting on August 24, 2026, the Piedmont City Council heard developer presentations and extensive resident objections over water supply, rural land use, and tax incentives for a proposed hyperscale data center in Canadian County.

  1. Kurt Mayabb, Mayor, City of Piedmont Elected Official transcribed from local broadcast report
    "Zoning the land for a data center was the main item on the agenda. You can hear the phone call. You can hear the quail. Quail. Lots of Piedmont residents valued their quality of life near the city. I’ll be honest with you. What? Know of the data center this time? But it almost brings tears to my eyes. And all residents that gave public comments do not want a data center to change that lifestyle. We need to take."
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "A spokesperson from cimarron project co LLC, a developer, said the facility would require 75,000 gallons of water a day, but that would be a closed loop system, meaning it would only need to be filled once. Only new water required daily would be for restrooms and basic plumbing. They also said they’d be willing to build a new water tower if needed, and they agreed to not drill any water wells if they get the 75,000 gallon, one time commitment from the city."
  3. KOCO 5 News Broadcast Report Broadcast Report transcribed from local broadcast report
    "I’m asking you that you slow down where answers are still missing and wait for the answers before you cast your vote. The plan presented monday included over 630 acres for the facility, with several buildings part of it in Piedmont city limits and part of it in kingfisher county near northwest, 248th street and richland road northwest. Supporters see economic opportunity. Opponents may see the risks to their property and quality of life."

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. · Status: rumored (source date; the content gives no date of its own)

    Beltline Energy is the developer of the proposed data center

    [2] news9.com

Every event in order

2 corrections to this record

Every correction, with its reason
  1. · Project summary

    the record's rules: the sentence was the source's wording or carried a number not in the card's facts; written again from the article

  2. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

Every correction on the record is on the corrections page.

Nearest data centers in Oklahoma

Verified data center records in Oklahoma within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Piedmont Area Data Center Piedmont, Canadian County Less than 1 mi Proposed
El Reno Bitcoin Mining Data Center El Reno, Canadian County Less than 1 mi Proposed
TierPoint Oklahoma City Data Centers Oklahoma City, Oklahoma County ~25 mi Running TierPoint
Grady County Data Center Grady County ~34 mi Proposed

Blank cell: not disclosed by any source on file.

Common questions about Yukon Data Center

Answered directly from the verified filings and local actions on this page.

Who is building Yukon Data Center?

Not disclosed. No source on file names the developer. The sources read for this record are listed under Sources.

How much power and water does Yukon Data Center say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Yukon Data Center stand today?

It is reported, as reported June 30, 2026. The newest entry, reported June 30, 2026: Beltline Energy is the developer of the proposed data center [2].

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Yukon city leaders still contemplating proposed data center - KFOR (opens in a new tab), KFOR, July 28, 2026, local outlet
  2. Yukon City Council set to discuss proposed Beltline Energy data center project - News 9 (opens in a new tab), News 9, June 30, 2026, local outlet
  3. New data center coming to Yukon, generating contention - KOKH (opens in a new tab), KOKH, August 22, 2025, local outlet

3 sources on file.

Regional grid context

This site is in the SPP South (SPSO) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Yukon Data Center", https://datacenterrecord.org/projects/yukon-data-center-ok, last verified September 17, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Yukon Data Center", https://datacenterrecord.org/projects/yukon-data-center-ok. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
built from one source
Tags
Built from one source
Coordinates
35.53028, -97.9575
How the location is known
Location is the county seat; exact site not disclosed.
Location source
County seat (El Reno), Wikidata, placed at county level
Coordinate source
wikidata county seat
Location last verified
September 16, 2026
Published
September 5, 2026
Last verified
September 17, 2026
Not disclosed