Data Center Record.
Census GEOID: 13121 Location Precision: assessor parcel Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 2 primary and local sources

● Proposed Campus Announced October 29, 2026 · 4 Buildings · B9 Union City Owner LLC

The Crossing Business Park Data Center Campus (Union City, DRI #4825)

Street address East of Roosevelt Hwy, Union City, GA 30291, Fulton County assessor parcel Exact, on the parcel [2] apps.dca.ga.gov

Overview, regulatory gates and specifications

B9 Union City Owner LLC filed Georgia DCA DRI #4825 on October 29, 2026 (updating earlier DRI #4617) for The Crossing Business Park, a 1,501,400 square foot data center development on 232.15 acres east of Roosevelt Highway in Union City, Fulton County. [1] Filings on the record specify 4 planned or operational buildings. [2] On the regulatory record, state permit status is Georgia DCA DRI #4825 regional review filing. [1]

1. Land & Parcel
232.15 acres on file
2. Local Zoning
In local review
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Not yet on file
5. Air & Water Permits
Georgia DCA DRI #4825 region
What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [2]
232.15 acres
the developer's figure

4 planned or operational data hall buildings.

Location: East of Roosevelt Hwy, Union City, GA 30291.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
232.15 acres developer figure
[2] apps.dca.ga.gov
Buildings
4 buildings permitted
[2] apps.dca.ga.gov
Backup generators
Not disclosed
Capital investment
Not disclosed
Who leads it
B9 Union City Owner LLC as stated by the source
[1] apps.dca.ga.gov
Permitted legal entity
B9 Union City Owner LLC the developer's figure
[2] apps.dca.ga.gov
State air permit registration
Georgia DCA DRI #4825, Georgia DCA DRI #4617 state air permit register
State permit status
Georgia DCA DRI #4825 regional review filing the state's permit register, as of October 29, 2026, last verified November 11, 2026
[1] apps.dca.ga.gov
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: B9 Union City Owner LLC
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for The Crossing Business Park Data Center Campus (Union City, DRI #4825).

Field / Parameter Permitted / Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres) 232.15 acres 232.15 acres the developer's figure [2] apps.dca.ga.gov
Data Hall Buildings 4 buildings Georgia DCA DRI Initial Form [2] apps.dca.ga.gov
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Fulton County and Union City about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Atlanta case by case Atlanta City Council introduced new legislation aimed at regulating local data centers and eliminating their tax breaks theatlantavoice.com (opens in a new tab)
Atlanta case by case Atlanta City Council members introduced zoning ordinances restricting data centers near transit stations and the BeltLine corridor and barring local tax incentives. fox5atlanta.com (opens in a new tab)
Atlanta case by case The City of Atlanta established a Data Center Task Force to evaluate municipal zoning, grid load and neighborhood rules for urban data centers. usatoday.com (opens in a new tab)
Atlanta case by case Communities placing moratoriums on data center development citing concerns about power and water usage, traffic, environmental impacts and noise wsbradio.com (opens in a new tab)

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. · Status: permitting (content date)

    B9 Union City Owner LLC filed Georgia DCA DRI #4825 on October 29, 2026 (updating earlier DRI #4617) for The Crossing Business Park, a 1,501,400 square foot data center development on 232.15 acres east of Roosevelt Highway in Union City, Fulton County.

    [1] apps.dca.ga.gov

Every event in order

Nearest data centers in Georgia

Verified data center records in Georgia within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Vantage Data Centers Atlanta GA1 Campus (Stacks Road) South Fulton, Fulton County 1 mi Being built Vantage Data Centers 1 building
ATL03 Red Oak Data Center Campus (Union City) Union City, Fulton County 1 mi Proposed TA Realty / Burr Computer Environments 67.8 acres
RSC South Fulton Parkway Data Center Campus (DRI #4342) South Fulton, Fulton County 1 mi Proposed RSC Investment Management LLC 59 acres
Microsoft Union City ATL50 Campus (DRI #4843) Union City, Fulton County 2 mi Proposed Microsoft Corporation 88.01 acres
EdgeConneX Union City Campus (ATL11) Union City, Fulton County 2 mi Running EdgeConneX 3 buildings
Microsoft East Point Data Center (ATL06) East Point, Fulton County 3 mi Running Microsoft Corporation 1 building

Blank cell: not disclosed by any source on file.

Common questions about The Crossing Business Park Data Center Campus (Union City, DRI #4825)

Answered directly from the verified filings and local actions on this page.

Who is building The Crossing Business Park Data Center Campus (Union City, DRI #4825)?

B9 Union City Owner LLC is the developer, apps.dca.ga.gov (opens in a new tab). No construction contractor is named on the record yet.

How much power and water does The Crossing Business Park Data Center Campus (Union City, DRI #4825) say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does The Crossing Business Park Data Center Campus (Union City, DRI #4825) stand today?
What has Union City or Fulton County decided about it?

Atlanta (rated case by case): Atlanta City Council introduced new legislation aimed at regulating local data centers and eliminating their tax breaks (reported August 26, 2026, theatlantavoice.com (opens in a new tab)); and Atlanta: Atlanta City Council members introduced zoning ordinances restricting data centers near transit stations and the BeltLine corridor and barring local tax incentives (August 20, 2026, fox5atlanta.com (opens in a new tab)). 4 events are on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Primary documents

  1. Georgia DCA DRI #4825 Application Summary (The Crossing Business Park Data Center Campus (Union City, DRI #4825)) (opens in a new tab), Georgia Department of Community Affairs, October 29, 2026
  2. Georgia DCA DRI #4825 Initial Form (The Crossing Business Park Data Center Campus (Union City, DRI #4825)) (opens in a new tab), Georgia Department of Community Affairs, October 29, 2026

2 sources on file.

Regional grid context

This site is in the SERC South (SRSO) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "The Crossing Business Park Data Center Campus (Union City, DRI #4825)", https://datacenterrecord.org/projects/the-crossing-business-park-union-city-ga, last verified October 29, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "The Crossing Business Park Data Center Campus (Union City, DRI #4825)", https://datacenterrecord.org/projects/the-crossing-business-park-union-city-ga. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
built from one source
Tags
Built from one source
Coordinates
33.59527, -84.5463
How the location is known
Location from the county parcel record.
Location source
https://apps.dca.ga.gov/DRI/InitialForm.aspx?driid=4825
Coordinate source
https://apps.dca.ga.gov/DRI/InitialForm.aspx?driid=4825
Location last verified
November 11, 2026
How acreage was disclosed
the developer's figure
Rating of the county's rows
Case by case
Published
November 11, 2026
Last verified
October 29, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, Interconnection, Capacity, if disclosed

Researcher view · The Crossing Business Park Data Center Campus (Union City, DRI #4825) · 2 sources, 1 entry, 4 decisions nearby · basis and source tier on every row · verified October 29, 2026

Download CSV JSON