● Running Announced March 25, 2026 · 3 Buildings · EdgeConneX

EdgeConneX Union City Campus (ATL11)

Street address 4850 Stonewall Tell Rd, Union City, GA 30349, Fulton County permit coordinates Exact, the point of the EPA's facility record [2] air.gaepd.org

Overview, regulatory gates and specifications

EdgeConneX ATL11, LLC operates a multi building hyperscale data center campus along Stonewall Tell Road in Union City, Fulton County with 126 permitted backup diesel generators under Georgia EPD Synthetic Minor Air Quality Permit Amendment No. 7374-121-0977 (S 01 to 1) issued March 25, 2026. [2] On the regulatory record, state permit status is Georgia EPD Air Quality Permit No. 7374-121-0977 (S 01-1) issued. [2]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Georgia EPD Air Quality Perm
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [2]
3 buildings
GA EPD Air Quality Permit

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 4850 Stonewall Tell Rd, Union City, GA 30349.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
3 buildings permitted
[2] air.gaepd.org
Backup generators
126 generators permitted
[2] air.gaepd.org
Capital investment
Not disclosed
Who leads it
EdgeConneX attributed via corporate HQ or property filing
[2] air.gaepd.org
Permitted legal entity
EdgeConneX ATL11, LLC what a permit allows
[2] air.gaepd.org [2] air.gaepd.org
State air permit registration
GA EPD AIRS 121-00977, GA EPD Permit 7374-121-0977-S-01-1, EPA FRS 110071821914 state air permit register
[2] air.gaepd.org
State permit status
Georgia EPD Air Quality Permit No. 7374-121-0977 (S 01-1) issued the state's permit register, as of March 25, 2026, last verified November 11, 2026
[2] air.gaepd.org
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: EdgeConneX
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for EdgeConneX Union City Campus (ATL11).

Field / Parameter Permitted / Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings 3 buildings 3 GA EPD Air Quality Permit [2] air.gaepd.org
Cooling & Water System
Backup Diesel / Gas Generators 126 units what a permit allows [2] air.gaepd.org
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Fulton County and Union City about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Atlanta case by case Atlanta City Council introduced new legislation aimed at regulating local data centers and eliminating their tax breaks theatlantavoice.com (opens in a new tab)
Atlanta case by case Atlanta City Council members introduced zoning ordinances restricting data centers near transit stations and the BeltLine corridor and barring local tax incentives. fox5atlanta.com (opens in a new tab)
Atlanta case by case The City of Atlanta established a Data Center Task Force to evaluate municipal zoning, grid load and neighborhood rules for urban data centers. usatoday.com (opens in a new tab)
Atlanta case by case Communities placing moratoriums on data center development citing concerns about power and water usage, traffic, environmental impacts and noise wsbradio.com (opens in a new tab)

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. · Status: running (content date)

    EdgeConneX ATL11, LLC operates a multi building hyperscale data center campus along Stonewall Tell Road in Union City, Fulton County with 126 permitted backup diesel generators under Georgia EPD Synthetic Minor Air Quality Permit Amendment No. 7374-121-0977 (S 01 to 1) issued March 25, 2026.

    [2] air.gaepd.org

Every event in order

Nearest data centers in Georgia

Verified data center records in Georgia within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Microsoft Union City ATL50 Campus (DRI #4843) Union City, Fulton County Less than 1 mi Proposed Microsoft Corporation 88.01 acres
RSC South Fulton Parkway Data Center Campus (DRI #4342) South Fulton, Fulton County Less than 1 mi Proposed RSC Investment Management LLC 59 acres
Vantage Data Centers Atlanta GA1 Campus (Stacks Road) South Fulton, Fulton County 2 mi Being built Vantage Data Centers 1 building
The Crossing Business Park Data Center Campus (Union City, DRI #4825) Union City, Fulton County 2 mi Proposed B9 Union City Owner LLC 232.15 acres
Microsoft East Point Data Center (ATL06) East Point, Fulton County 3 mi Running Microsoft Corporation 1 building
ATL03 Red Oak Data Center Campus (Union City) Union City, Fulton County 3 mi Proposed TA Realty / Burr Computer Environments 67.8 acres

Blank cell: not disclosed by any source on file.

Common questions about EdgeConneX Union City Campus (ATL11)

Answered directly from the verified filings and local actions on this page.

Who is building EdgeConneX Union City Campus (ATL11)?

EdgeConneX is the developer, air.gaepd.org (opens in a new tab). No construction contractor is named on the record yet.

How much power and water does EdgeConneX Union City Campus (ATL11) say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does EdgeConneX Union City Campus (ATL11) stand today?
What has Union City or Fulton County decided about it?

Atlanta (rated case by case): Atlanta City Council introduced new legislation aimed at regulating local data centers and eliminating their tax breaks (reported August 26, 2026, theatlantavoice.com (opens in a new tab)); and Atlanta: Atlanta City Council members introduced zoning ordinances restricting data centers near transit stations and the BeltLine corridor and barring local tax incentives (August 20, 2026, fox5atlanta.com (opens in a new tab)). 4 events are on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Primary documents

  1. EPA ECHO Detailed Facility Report (110071821914) (opens in a new tab), U.S. Environmental Protection Agency, March 25, 2026

Reporting

  1. Georgia EPD Air Quality Permit 7374-121-0977-S-01-1 (EdgeConneX Union City Campus (ATL11)) (opens in a new tab), Georgia Environmental Protection Division, March 25, 2026, news outlet

2 sources on file.

Regional grid context

This site is in the SERC South (SRSO) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "EdgeConneX Union City Campus (ATL11)", https://datacenterrecord.org/projects/edgeconnex-union-city-atl11-ga, last verified March 25, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "EdgeConneX Union City Campus (ATL11)", https://datacenterrecord.org/projects/edgeconnex-union-city-atl11-ga. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
33.62326, -84.56102
How the location is known
Location from an EPA facility record.
Location source
https://air.gaepd.org/Permits/View/OP-29820
Coordinate source
https://echo.epa.gov/detailed-facility-report?fid=110071821914
Location last verified
November 11, 2026
Rating of the county's rows
Case by case
Published
November 11, 2026
Last verified
March 25, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed

Researcher view · EdgeConneX Union City Campus (ATL11) · 2 sources, 1 entry, 4 decisions nearby · basis and source tier on every row · verified March 25, 2026