Switch lists a data center at Atlanta, Georgia among the sites it operates. [1] Filings on the record specify 4 planned or operational buildings. [3] Switch lists Switch Atlanta campus at Atlanta, Georgia on its own page of data center locations, read September 14, 2026. [3]
How much power it needs, how much water it would use and who would use it have not been disclosed.
Connected government officials, corporate entities, utilities and local rules on the public record.
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Switch The Keep Campus (Atlanta).
| Field / Parameter | Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | |||
| Site Footprint (Acres) | |||
| Data Hall Buildings | 4 buildings | 4 | operator page [3] switch.com |
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Chronological regulatory, corporate and permitting events on the record, newest first.
No dated entry is on the record yet.
Read on September 14, 2026 (the day the page was read; it gives no date of its own)
Switch lists Switch Atlanta campus at Atlanta, Georgia on its own page of data center locations, read September 14, 2026.
Every correction on the record is on the corrections page.
Verified data center records in Georgia within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| Google Douglas County Data Center Lithia Springs, Douglas County | Less than 1 mi | Running | 3 buildings | |
| Flexential Atlanta Douglasville (ATL5) Douglasville, Douglas County | 1 mi | Running | Flexential | 22.5 MW |
| Aligned ATL-01 Lithia Springs, Douglas County | 1 mi | Running | Aligned Data Centers | 180 MW |
| DC BLOX Atlanta West Campus (Douglasville) Douglasville, Douglas County | 1 mi | Being built | DC BLOX | 2 buildings |
| Microsoft Douglasville Data Center Campus (FTY01 / FTY02) Douglasville, Douglas County | 1 mi | Running | Microsoft | 3 buildings |
| Rock House Road Data Center Campus (DRI #4078) Lithia Springs, Douglas County | 2 mi | Proposed | Taylor & Mathis | 4 buildings |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
Switch is the developer. No construction contractor is named on the record yet.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.
Official operator or facility campus page verified in 50 state website discovery pass.
6 sources on file.
This site is in the SERC South (SRSO) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Switch The Keep Campus (Atlanta). Last verified September 14, 2026. https://datacenterrecord.org/projects/switch-atlanta-campus-ga. Accessed November 22, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified and first recorded . Every correction is logged on the corrections page and under What happened. Report a correction · Send a tip about Switch The Keep Campus (Atlanta)
Data Center Record, "Switch The Keep Campus (Atlanta)", https://datacenterrecord.org/projects/switch-atlanta-campus-ga. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.