Data Center Record.

Proposed Built from one source

Stream Data Centers Western New York STAMP Hyperscale Campus

Basom, Genesee County, NYDeveloper: Stream Data CentersCensus GEOID 36037

Stage
Proposed
Power
250 MW
the developer's figure
Buildings
3 buildings
zoning filing, verified October 27, 2026
Undisclosed in public filings
Land, Water

Stream Data Centers received Genesee County Economic Development Center incentive and site approval for a 3 building, 250 MW hyperscale data center campus at the Science and Technology Advanced Manufacturing Park (STAMP) in the Town of Alabama, Genesee County, New York. It is approved; the record holds no sourced date for when it reached that stage.

How much water it would use and who would use it have not been disclosed.

Last verified · 3 sources, 0 primary · Built from one source, not yet reviewed in depth by a person. · How to read this page

  • This record: Proposed, ringed
  • data center
  • Smaller pins: 31 other published records in New York
Details
  • this record's location, ringed
  • parcel outline, from the county parcel record
  • city limits, U.S. Census Bureau, on a town level record
  • county boundary

The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.

How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.

What is known

Each figure as its source gave it. The number in brackets is its place in the source list.

Buildings
3 buildings zoning filing, verified October 27, 2026
Power it would draw
250 MW the developer's figure About 2 percent of New York City's summer peak demand in 2024.
Who leads it
Stream Data Centers as stated by the source
Undisclosed in public filings
Land, Water, Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Stream Data Centers Western New York STAMP Hyperscale Campus, capacity: 250 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 250 ÷ 10,245 = 0.02 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Every field, with who said it and when (Researcher view)

Impact figures

FieldValueWho says soSourceLast verified
How much power it needs 250 MW the developer's figure gcedc.com (opens in a new tab) October 27, 2026
How much water it would use
How loud it would be
Jobs once it runs
Tax it would pay each year

The record's fields

FieldValueWho says soSourceLast verified
Who is building it Stream Data Centers as stated by the source October 27, 2026
Who is constructing it
How much land
Buildings 3 buildings zoning filing, verified October 27, 2026 gcedc.com (opens in a new tab) October 27, 2026
Where its power comes from
Grid connection
How it is cooled

A blank value cell means not disclosed by any source on file; a blank basis cell means the source gave the figure without saying on what basis.

The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What happened

  1. · Status: stalled or cancelled (content date)

    Stream Data Centers proposed a 2.2 million square foot data center at the STAMP industrial park in Genesee County with a $1.46 billion tax incentive request; the project faces uncertainty from the state moratorium and a lawsuit challenging the underlying zoning agreement.

    [1] investigativepost.org

The full Stream Data Centers Western New York STAMP Hyperscale Campus timeline, in order

The site

The pin is the site's address.

The site map is at the top of the page.

Where
6840 Crosby Road, Basom, NY 14013, Basom, Genesee County, New York [source] (opens in a new tab)
How exactly it is located
Exact, at the address
The parcel
No parcel outline in the public record
Nearest homes
Not computed for a record placed at a place center

USGS NAIP aerial view of Stream Data Centers Western New York STAMP Hyperscale Campus
LAT 43.09120 / LON -78.38450 Imagery: U.S. Geological Survey / USDA NAIP (Public Domain)

Questions about this project

5 questions answered from the record

Answered from the rows on this page.

How big is Stream Data Centers Western New York STAMP Hyperscale Campus?

The record has 2 measures of its size: 250 MW (the developer's figure, gcedc.com (opens in a new tab)) and 3 buildings (zoning filing, verified October 27, 2026, gcedc.com (opens in a new tab)). Its acreage is not disclosed.

Who is building Stream Data Centers Western New York STAMP Hyperscale Campus?

Stream Data Centers is the developer. No construction contractor is named on the record yet.

How much power and water does Stream Data Centers Western New York STAMP Hyperscale Campus say it needs?

Power: 250 MW (the developer's figure, gcedc.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Stream Data Centers Western New York STAMP Hyperscale Campus stand today?

It is approved; the date it reached that stage is not sourced, only the day a page was read. The newest entry, July 15, 2026: Stream Data Centers proposed a 2.2 million square foot data center at the STAMP industrial park in Genesee County with a $1.46 billion tax incentive request; the project faces uncertainty from the state moratorium and a lawsuit challenging the underlying zoning agreement. [1]

What has Basom or Genesee County decided about it?

No decision by Basom or Genesee County about data centers is on the record. The Genesee County page and the New York scorecard list every rated row the day a person publishes one.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Future of STAMP data center uncertain due to Hochul order, lawsuit - Investigative Post (opens in a new tab), Investigative Post, July 15, 2026, query feed
  2. Hochul's data center moratorium raises questions for proposed Genesee County project - 13wham.com (opens in a new tab), 13wham.com, July 14, 2026, query feed
  3. New York County Agency Tries to Force Data Center on Locals - Sierra Club (opens in a new tab), Sierra Club, June 24, 2026, query feed

3 sources on file.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Stream Data Centers Western New York STAMP Hyperscale Campus", https://datacenterrecord.org/projects/stream-data-centers-stamp-genesee-county-ny, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Stream Data Centers Western New York STAMP Hyperscale Campus", https://datacenterrecord.org/projects/stream-data-centers-stamp-genesee-county-ny. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
built from one source
Tags
Built from one source
Coordinates
43.0912, -78.3845
How the location is known
Location from the site's street address.
Location source
https://www.gcedc.com/
Coordinate source
Genesee County Economic Development Center (GCEDC) STAMP Project Docket
How capacity was disclosed
the developer's figure
Capacity, if disclosed
250 MW, the developer's figure
Published
September 28, 2026
Last verified
October 27, 2026
Undisclosed in public filings
Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · Stream Data Centers Western New York STAMP Hyperscale Campus · 3 sources, 1 entry, 0 decisions nearby · basis and source tier on every row · verified October 27, 2026

Download CSV JSON