Data Center Record.
Census GEOID: 06085 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 1 reporting source

● Running First recorded October 21, 2026 · 1 Building

Serverfarm Santa Clara Data Center (SV1)

Street address 5101 Lafayette Street, Santa Clara, CA 95054, Santa Clara County verified address Exact, at the address [1] serverfarmllc.com

Overview, regulatory gates and specifications

Serverfarm operates its SV1 Silicon Valley enterprise colocation data center at 5101 Lafayette Street in Santa Clara, Santa Clara County, California, with 14 MW of power capacity. [1] Filings on the record specify 1 planned or operational building. [1] Verified facility status from California state agency permits, utility dockets, municipal planning filings, or operator campus specifications. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Not yet on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [1]
14 MW
the developer's figure

Equivalent to ~11,620 U.S. homes (U.S. EIA 830 homes/MW baseline) · 0.7% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
1 building
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 5101 Lafayette Street, Santa Clara, CA 95054.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
14 MW developer figure Equivalent to the continuous electricity demand of about 11,600 average U.S. homes based on U.S. Energy Information Administration residential consumption data. About 0.1 percent of New York City's summer peak demand in 2024.
[1] serverfarmllc.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
1 building operator page
[1] serverfarmllc.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2017 (9 years)
Who leads it
Serverfarm as stated by the source
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Serverfarm Santa Clara Data Center (SV1), capacity: 14 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 14 ÷ 10,245 = 0.0014 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Serverfarm
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Serverfarm Santa Clara Data Center (SV1).

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 14 MW 14 MW the developer's figure [1] serverfarmllc.com
Site Footprint (Acres)
Data Hall Buildings 1 building 1 operator page [1] serverfarmllc.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

August 19, 2026 San Jose, CA City of San Jose Data Centers and Large Energy Projects Community Session City of San Jose Office of the City Manager 3 clips

On August 19, 2026, the City of San Jose hosted an official public hearing on data centers and large energy projects to establish municipal regulations on grid capacity, backup diesel generators, and water efficiency.

  1. City of San Jose Administration Official Board & Planning Staff transcribed from the official recording
    "data center might mean. And that's why we're holding this session because community input helps guide what our priorities are, what our regulations are, what the rules of the road are in San Jose. And I want to be really clear, we are not here tonight to persuade you to be pro- data center. That is not the point of this. The goal of tonight is to understand what your concerns are and"
  2. Resident public comment Resident Public Comment transcribed from the official recording
    "industrial land and want to consider a data center project and more importantly with the entire community what the standards are. And my view is that if a data center gets built in San Jose in the future, it ought to be under the strongest standards around labor, environment, both protecting rateayers"
  3. City of San Jose Office of the City Manager Member Elected Official transcribed from the official recording
    "beginning of our process. This is our first community listening session. As I mentioned we are in a process of developing regulations to cover all of those areas of concern. But unless we first start by hearing from you and understanding what those concerns are and really teasing out the details and what your experience is, we won't have the best possible regulatory environment. So, I'm looking forward to kicking this off. I'm going to introduce"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on October 27, 2026 (the day the page was read; it gives no date of its own)

    Verified facility status from California state agency permits, utility dockets, municipal planning filings, or operator campus specifications.

    [1] serverfarmllc.com

Nearest data centers in California

Verified data center records in California within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Centersquare Silicon Valley (SFO2 Santa Clara) Santa Clara, Santa Clara County Less than 1 mi Running Centersquare 1 building
QTS Santa Clara Campus (SJC1 / SJC2) Santa Clara, Santa Clara County Less than 1 mi Running QTS Data Centers 1 building
QTS Santa Clara Data Center Campus (SJC1 and SJC2) Santa Clara, Santa Clara County 1 mi Running QTS Data Centers 25 MW
EdgeCore Silicon Valley Laurelwood Data Center Campus Santa Clara, Santa Clara County 2 mi Running EdgeCore Digital Infrastructure 72 MW
Equinix Santa Clara Campus (SV2, SV14, SV15, SV16, and SV17) Santa Clara, Santa Clara County 2 mi Running Equinix 52 MW
CoreSite Santa Clara Campus (SV3, SV4, SV7, SV8, and SV9) Santa Clara, Santa Clara County 2 mi Running CoreSite 85 MW

Blank cell: not disclosed by any source on file.

Common questions about Serverfarm Santa Clara Data Center (SV1)

Answered directly from the verified filings and local actions on this page.

Who is building Serverfarm Santa Clara Data Center (SV1)?

Serverfarm is the developer. No construction contractor is named on the record yet.

How much power and water does Serverfarm Santa Clara Data Center (SV1) say it needs?

Power: 14 MW (the developer's figure, serverfarmllc.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Serverfarm Santa Clara Data Center (SV1) stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Serverfarm Santa Clara Data Center (SV1) Official Disclosure (opens in a new tab), Serverfarm, news outlet

1 source on file.

Regional grid context

This site is in the WECC California (CAMX) regional power market.

Sources and data

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Serverfarm Santa Clara Data Center (SV1)", https://datacenterrecord.org/projects/serverfarm-sc1-santa-clara-ca, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Serverfarm Santa Clara Data Center (SV1)", https://datacenterrecord.org/projects/serverfarm-sc1-santa-clara-ca. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
37.4052, -121.9692
How the location is known
Location from the site's street address.
Location source
https://www.serverfarmllc.com/locations/santa-clara-ca/
Coordinate source
Santa Clara County Assessor / Serverfarm SV1 specification
How capacity was disclosed
the developer's figure
Capacity, if disclosed
14 MW, the developer's figure
Published
October 21, 2026
Last verified
October 27, 2026
Not disclosed
Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · Serverfarm Santa Clara Data Center (SV1) · 1 source, 1 entry · basis and source tier on every row · verified October 27, 2026

Download CSV JSON