Segra operates a commercial colocation data center at 465 Charles Babbage Lane on the North Carolina Research Campus in Kannapolis, Cabarrus County, North Carolina. [1] Filings on the record specify disclosed capacity of 4 MW (the developer's figure), 1 planned or operational building. [2] Verified facility status from North Carolina DEQ permits, municipal zoning filings, or operator campus specifications. [1]
Equivalent to ~3,320 U.S. homes (U.S. EIA 830 homes/MW baseline) · 0.2% of Hoover Dam nameplate capacity (2,080 MW).
Grid interconnection and utility service tracked on file.
U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.
No local property tax abatement amount disclosed in public filings.
Assessor parcel acreage and building square footage are added when municipal or county filings are published.
Location: 465 Charles Babbage Lane, Kannapolis, NC 28081.
State and local tax abatement agreements and permanent job commitments are recorded when filed.
No local property tax abatement amount disclosed in public filings.
Sources:
A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).
Connected government officials, corporate entities, utilities and local rules on the public record.
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Segra Kannapolis Data Center.
| Field / Parameter | Permitted / Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | 4 MW | 4 MW | the developer's figure [2] segra.com |
| Site Footprint (Acres) | |||
| Data Hall Buildings | 1 building | 1 | operator page [2] segra.com |
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Acts of Cabarrus County and Kannapolis about data centers, on the record with their source. A rule about the area is not a decision about this record.
The National Desk report on Harrisburg City Council and community proceedings in Harrisburg, NC: Data center debate: Family TURNS DOWN $26 million to keep farmland (March 24, 2026).
"half of that property with plans to make it an AI data center. Now, they aren't the only ones here. Dozens of other landowners in the area they've also been approached by a major AI company land in Mason County is reportedly valued at about $6,000 per acre. The offer that came in was roughly 10 times that amount. They call us old stupid farmers, you know, but we're not."
"disappearing, and we don't have any water and poison. We know we've had it. Now, despite that refusal the Huddleston family said the company revised its plans using land from owners who did agree to sell meaning that data center likely still going up in Mason County."
Using this data in a report? Support the record.
Chronological regulatory, corporate and permitting events on the record, newest first.
No dated entry is on the record yet.
Read on October 27, 2026 (the day the page was read; it gives no date of its own)
Verified facility status from North Carolina DEQ permits, municipal zoning filings, or operator campus specifications.
Verified data center records in North Carolina within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| Flexential Charlotte North (CLT4 and CLT5) Charlotte, Mecklenburg County | 15 mi | Running | Flexential | 12 MW |
| H5 Charlotte Charlotte, Mecklenburg County | 15 mi | Running | H5 Data Centers | 12 MW |
| Historic Charlotte building site data center Charlotte, Mecklenburg County | 23 mi | Proposed | 1 building | |
| Digital Realty Charlotte Charlotte, Mecklenburg County | 23 mi | Running | Digital Realty | 6 MW |
| Digital Realty Moores Chapel Road Data Center Charlotte, Mecklenburg County | ~24 mi | Proposed | Digital Realty | |
| DC74 Data Centers Charlotte (CLT1) Charlotte, Mecklenburg County | 28 mi | Running | DC74 Data Centers | 5 MW |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
Segra is the developer, segra.com (opens in a new tab). No construction contractor is named on the record yet.
Power: 4 MW (the developer's figure, segra.com (opens in a new tab)). Water: not disclosed by any source on file.
It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.
No decision by Kannapolis or Cabarrus County about data centers is on the record. The Cabarrus County page and the North Carolina scorecard list every rated row the day a person publishes one.
2 sources on file.
This site is in the SERC Virginia and Carolina South (SRVC-S) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Segra Kannapolis Data Center. Last verified November 6, 2026. https://datacenterrecord.org/projects/segra-kannapolis-nc. Accessed November 17, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page. Report a correction · Send a tip about Segra Kannapolis Data Center
Data Center Record, "Segra Kannapolis Data Center", https://datacenterrecord.org/projects/segra-kannapolis-nc. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.