● Stalled or Cancelled Announced December 18, 2024 · Lightfield Energy LLC

Lightfield Energy Ottawa Data Center (Proximity Park)

Location Ottawa, Franklin County, Kansas city centroid Town level, the center of the city

Overview, regulatory gates and specifications

The Ottawa City Commission voted 5 to 0 on September 25, 2026 to end its land sales contract with Lightfield Energy LLC for 300 acres at Proximity Park in Ottawa, Franklin County, Kansas, after the developer did not submit a required development agreement by the deadline; KSHB 41 reported the vote and the official Ottawa City Commission minutes are the pending primary record. [1]

1. Land & Parcel
300 acres on file
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Not yet on file
5. Air & Water Permits
Not yet on file
What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [2]
300 acres
City of Ottawa sales contract (City Commission action, December 18, 2024), reported by KSHB 41, pending the contract

Building count not yet itemized in public filings.

Parcel boundaries and municipal zoning tracked.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
300 acres permitted
[2] kshb.com [1] kshb.com
Buildings
Not disclosed
Backup generators
Not disclosed
Capital investment
Not disclosed
Who leads it
Lightfield Energy LLC as stated by the source
[2] kshb.com
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Lightfield Energy LLC
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Lightfield Energy Ottawa Data Center (Proximity Park).

Field / Parameter Permitted / Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres) 300 acres 300 acres City of Ottawa sales contract (City Commission action, December 18, 2024), reported by KSHB 41, pending the contract [2] kshb.com
Data Hall Buildings
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Franklin County and Ottawa about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Ottawa Ottawa voters approved Question 2, the citizen initiative prohibiting construction of data centers using more than 25 megawatts of power, on November 3, 2026, voting 2,882 in favor (71.85 percent) to 1,129 against (28.15 percent). ballotpedia.org (opens in a new tab)
Ottawa Ottawa City Commission votes 5 to 0 to terminate data center sales contract with Lightfield Energy kshb.com (opens in a new tab)
Ottawa Franklin County judge ruled data center ordinance question will go on November ballot kshb.com (opens in a new tab)
Ottawa Franklin County judge ruled that a data center question will go on Ottawa's November ballot kshb.com (opens in a new tab)
Ottawa Ottawa city commissioners took no action on Ottawa United initiative petition for data center ordinance based on city attorney opinion that petition is administrative in nature kshb.com (opens in a new tab)
September 25, 2026 Ottawa, KS Ottawa Ends Lightfield Energy Data Center Contract Ottawa City Commission 2 clips

KSHB 41 report on Ottawa City Commission and community proceedings in Ottawa, KS: Ottawa Ends Lightfield Energy Data Center Contract (September 25, 2026).

  1. KSHB 41 Broadcast Report Broadcast Report transcribed from local broadcast report
    "times as he's fought data center development in Ottawa. That fight included a petition to put a hyperscale data center ban on the November ballot and a lawsuit against the city. When action needs to be taken, somebody's got to do it. An Ottawa City Commissioner says this 300 acre site is still open for business even after the commission terminated its data center contract with developer Lightfield Energy this week. That's the truth. It was it's we're"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "Energy for a data center and a natural gas power plant. After two extensions, the city says developers haven't submitted the required documents to close the sale by the October 30th deadline. They are out of time. [clears throat] And so yeah, I I think it's time to move on it. The commission voted 5-0 on Wednesday to terminate its sales contract almost 2 years after it was made. I'm going to be blunt. the last 2 years has felt like an"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. · Status: stalled or cancelled (content date)

    The Ottawa City Commission voted 5 to 0 on September 25, 2026 to end its land sales contract with Lightfield Energy LLC for 300 acres at Proximity Park after the developer did not submit a required development agreement by the deadline; KSHB 41 reported the vote and the official Ottawa City Commission minutes are the pending primary record.

    [2] kshb.com

  2. · Status: permitting (content date)

    Lightfield Energy LLC entered a sales contract in December 2024 for 300 acres at Proximity Park in Ottawa for $5.3 million, with an entitlement period running through October 30, 2026, now facing a citizen ballot petition to ban data centers over 25 MW within city limits.

    [1] kshb.com

  3. · Status: proposed (content date)

    The Ottawa City Commission approved a $5.3 million land sales contract with Lightfield Energy LLC on December 18, 2024 for 300 acres at Proximity Park in Ottawa, reported by KSHB 41, pending the contract itself.

    [2] kshb.com

Every event in order

1 correction to this record

Every correction, with its reason
  1. · Site acreage disclosure

    The 300 acres is the figure in the City of Ottawa sales contract with Lightfield Energy LLC (Ottawa City Commission action, December 18, 2024), as reported by KSHB 41, pending the contract itself; it is not an estimate.

Every correction on the record is on the corrections page.

Nearest data centers in Kansas

Verified data center records in Kansas within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Data Center Edgerton Edgerton, Johnson County ~31 mi Proposed
TierPoint Kansas City - Lenexa Data Center Lenexa, Johnson County ~36 mi Running TierPoint 1 building
QTS Overland Park (OVP1) Overland Park, Johnson County ~38 mi Running QTS Data Centers 1 building
DataBank Kansas City Southlake (MCI2 Overland Park) Overland Park, Johnson County ~40 mi Running DataBank 1 building
Data Center Leavenworth Leavenworth, Leavenworth County ~52 mi Proposed

Blank cell: not disclosed by any source on file.

Common questions about Lightfield Energy Ottawa Data Center (Proximity Park)

Answered directly from the verified filings and local actions on this page.

Who is building Lightfield Energy Ottawa Data Center (Proximity Park)?

Lightfield Energy LLC is the developer, kshb.com (opens in a new tab). No construction contractor is named on the record yet.

How much power and water does Lightfield Energy Ottawa Data Center (Proximity Park) say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Lightfield Energy Ottawa Data Center (Proximity Park) stand today?
What has Ottawa or Franklin County decided about it?

Ottawa: Ottawa voters approved Question 2, the citizen initiative prohibiting construction of data centers using more than 25 megawatts of power, on November 3, 2026, voting 2,882 in favor (71.85 percent) to 1,129 against (28.15 percent), ballotpedia.org (opens in a new tab); and Ottawa: Ottawa City Commission votes 5 to 0 to terminate data center sales contract with Lightfield Energy (September 25, 2026, kshb.com (opens in a new tab)). 5 events are on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Primary documents

  1. Ottawa commissioners face deadline after data center petition gains enough signatures - KSHB 41 Kansas City (opens in a new tab), KSHB 41 Kansas City, August 13, 2026
  2. 'Out of time': Ottawa ends data center contract as ballot fight continues - KSHB 41 Kansas City (opens in a new tab), KSHB 41 Kansas City, September 25, 2026

2 sources on file.

Regional grid context

This site is in the SPP North (SPNO) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Lightfield Energy Ottawa Data Center (Proximity Park)", https://datacenterrecord.org/projects/lightfield-energy-ottawa-data-center-proximity-park-ks, last verified September 25, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Lightfield Energy Ottawa Data Center (Proximity Park)", https://datacenterrecord.org/projects/lightfield-energy-ottawa-data-center-proximity-park-ks. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Stalled or cancelled
Tier
built from one source
Tags
Built from one source
Coordinates
38.60008, -95.26278
How the location is known
Location is the city center; exact site not disclosed.
Location source
U.S. Census Bureau TIGERweb city centroid, public domain
Coordinate source
tigerweb city centroid
Location last verified
November 5, 2026
How acreage was disclosed
City of Ottawa sales contract (City Commission action, December 18, 2024), reported by KSHB 41, pending the contract
Published
September 29, 2026
Last verified
September 25, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Lightfield Energy Ottawa Data Center (Proximity Park) · 2 sources, 3 entries, 5 decisions nearby · basis and source tier on every row · verified September 25, 2026