Data Center Leavenworth

Location Leavenworth, Leavenworth County, Kansas county centroid County level, the county seat

Overview, regulatory gates and specifications

A massive data center proposed in Leavenworth, Kansas has drawn organized community protest. [1] Developers proposed a commercial data center campus in Leavenworth County, Kansas. [2]

1. Land & Parcel
Location tracked
2. Local Zoning
Not yet on file
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Not yet on file
5. Air & Water Permits
Not yet on file
What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings
Not disclosed
Acreage not stated in public filings yet

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Parcel boundaries and municipal zoning tracked.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
Not disclosed
Backup generators
Not disclosed
Capital investment
Not disclosed
Not disclosed
Who leads it, Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Not disclosed
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Data Center Leavenworth.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Who is behind it A land record, a zoning application or a company's own announcement.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

May 15, 2026 Tonganoxie, KS Opposition to data centers growing in Kansas Tonganoxie City Council 2 clips

KCTV5 News report on Tonganoxie City Council and community proceedings in Tonganoxie, KS: Opposition to data centers growing in Kansas (May 15, 2026).

  1. KCTV5 News Broadcast Report Broadcast Report transcribed from local broadcast report
    "County this week passed a 90 day pause on proposals for new data center developments. And this group in Tonganoxie is looking to have the city pass an 18 month moratorium. A Gallup poll finds seven in 10 Americans oppose AI data centers in their communities. Would you want an AI data center in your community? Tell me in the comments."
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "developments. And this group in Tonganoxie is looking to have the city pass an 18 month moratorium. A Gallup poll finds seven in 10 Americans oppose AI data centers in their communities. Would you want an AI data center in your community? Tell me in the comments."

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. · Status: proposed (content date)

    Developers proposed a commercial data center campus in Leavenworth County, Kansas.

    [2] kcur.org

Every event in order

1 correction to this record

Every correction, with its reason
  1. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

Every correction on the record is on the corrections page.

Nearest data centers in Kansas

Verified data center records in Kansas within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
DataBank Kansas City Southlake (MCI2 Overland Park) Overland Park, Johnson County ~26 mi Running DataBank 1 building
TierPoint Kansas City - Lenexa Data Center Lenexa, Johnson County ~27 mi Running TierPoint 1 building
Data Center Edgerton Edgerton, Johnson County ~30 mi Proposed
QTS Overland Park (OVP1) Overland Park, Johnson County ~32 mi Running QTS Data Centers 1 building
Lightfield Energy Ottawa Data Center (Proximity Park) Ottawa, Franklin County ~52 mi Stalled or cancelled Lightfield Energy LLC 300 acres

Blank cell: not disclosed by any source on file.

Common questions about Data Center Leavenworth

Answered directly from the verified filings and local actions on this page.

Who is building Data Center Leavenworth?

Not disclosed. No source on file names the developer. The sources read for this record are listed under Sources.

How much power and water does Data Center Leavenworth say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Data Center Leavenworth stand today?

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Leavenworth County farmers concerned proposed data center could threaten crops, local business - KSHB 41 Kansas City (opens in a new tab), KSHB 41 Kansas City, September 16, 2026, local outlet
  2. To stop a massive data center from moving in, Leavenworth protesters are showing up and getting loud - kcur.org (opens in a new tab), kcur.org, August 14, 2026, local outlet

2 sources on file.

Regional grid context

This site is in the SPP North (SPNO) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Data Center Leavenworth", https://datacenterrecord.org/projects/data-center-leavenworth-ks, last verified September 17, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Data Center Leavenworth", https://datacenterrecord.org/projects/data-center-leavenworth-ks. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
built from one source
Tags
Built from one source
Coordinates
39.3111, -94.9225
How the location is known
Location is the county seat; exact site not disclosed.
Location source
County seat (Leavenworth), Wikidata, placed at county level
Coordinate source
wikidata county seat
Location last verified
September 16, 2026
Published
September 5, 2026
Last verified
September 17, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Data Center Leavenworth · 2 sources, 1 entry · basis and source tier on every row · verified September 17, 2026