Data Center Record.
KS Ottawa City Commission September 25, 2026 Local Broadcast Report

Ottawa Ends Lightfield Energy Data Center Contract

KSHB 41 report on Ottawa City Commission and community proceedings in Ottawa, KS: Ottawa Ends Lightfield Energy Data Center Contract (September 25, 2026).

Jurisdiction Ottawa, KS
Governing Body Ottawa City Commission
Meeting Date September 25, 2026
Extracted Clips 2 clips · 1 opposed · 0 supporting
Local broadcast report · KSHB 41 Ready at Clip 1 (0:27 to 0:55) · KSHB 41 Broadcast Report
Open source video on YouTube ↗ (opens in a new tab)

Privacy enhanced player · zero third party requests until clicked

Ottawa Ends Lightfield Energy Data Center Contract

Ottawa City Commission · September 25, 2026

Timestamped Speaker & Testimony Ledger

2 verified timestamped clips extracted chronologically from the closed caption record. Select any clip to play that exact window in the master player or copy a canonical clip link.

  1. Clip 1 · 0:27 KSHB 41 Broadcast Report Broadcast Report Questioning transcribed from local broadcast report
    Zoning Power & Grid Water

    KSHB 41 broadcast report on Ottawa, KS covering Ottawa City Commission proceedings and community debate over moratorium proposals (Segment 1).

    "times as he's fought data center development in Ottawa. That fight included a petition to put a hyperscale data center ban on the November ballot and a lawsuit against the city. When action needs to be taken, somebody's got to do it. An Ottawa City Commissioner says this 300 acre site is still open for business even after the commission terminated its data center contract with developer Lightfield Energy this week. That's the truth. It was it's we're"

    YouTube at 0:27 ↗ (opens in a new tab)
  2. Clip 2 · 1:06 Resident public comment Resident Public Comment transcribed from local broadcast report

    Resident interview in the KSHB 41 report on Ottawa, KS addressing grid capacity and utility rates before Ottawa City Commission.

    "Energy for a data center and a natural gas power plant. After two extensions, the city says developers haven't submitted the required documents to close the sale by the October 30th deadline. They are out of time. [clears throat] And so yeah, I I think it's time to move on it. The commission voted 5-0 on Wednesday to terminate its sales contract almost 2 years after it was made. I'm going to be blunt. the last 2 years has felt like an"

    YouTube at 1:06 ↗ (opens in a new tab)
Read full auto generated transcript (2 segments)

[0:27] KSHB 41 Broadcast Report: times as he's fought data center development in Ottawa. That fight included a petition to put a hyperscale data center ban on the November ballot and a lawsuit against the city. When action needs to be taken, somebody's got to do it. An Ottawa City Commissioner says this 300 acre site is still open for business even after the commission terminated its data center contract with developer Lightfield Energy this week. That's the truth. It was it's we're

[1:06] Resident public comment: Energy for a data center and a natural gas power plant. After two extensions, the city says developers haven't submitted the required documents to close the sale by the October 30th deadline. They are out of time. [clears throat] And so yeah, I I think it's time to move on it. The commission voted 5-0 on Wednesday to terminate its sales contract almost 2 years after it was made. I'm going to be blunt. the last 2 years has felt like an