Applied Digital is constructing a 300 acre, $3.6 billion data center campus called Delta Forge 1 in Boyce, Louisiana, with 300 MW in its first phase and initial operations expected as soon as mid 2027. [5] Applied Digital building $3.6 billion Data Forge 1 data center near Boyce [5]
How much power it needs, how much water it would use and who would use it have not been disclosed.
Connected government officials, corporate entities, utilities and local rules on the public record.
Humans First is conducting a cross country bus tour with 34 stops across the nation demanding stronger guardrails on data center development.(September 14, 2026) kalb.com (opens in a new tab)
Gary Musgrove, a Save My Louisiana representative, stated that community concerns about data centers remain unanswered by politicians and local officials.(September 14, 2026) kalb.com (opens in a new tab)
Humans First, conservative group, touring nation to advocate for local control over AI data center construction(September 13, 2026) [5]
View all 4 statements on the record in Louisiana →
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Delta Forge 1.
| Field / Parameter | Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | 300 MW | Disclosed filing [5] thetowntalk.com | |
| Site Footprint (Acres) | |||
| Data Hall Buildings | |||
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Chronological regulatory, corporate and permitting events on the record, newest first.
(source date; the content gives no date of its own)
Meta building Hyperion data center approximately 30 miles east of Monroe in Richland Parish
(source date; the content gives no date of its own)
Applied Digital building $3.6 billion Data Forge 1 data center near Boyce
· Status: proposed (content date)
Cleco Power announced an agreement to supply electricity to the proposed Delta Forge 1 data center in Boyce, Rapides Parish, Louisiana.
Normalize vote tallies ('X to Y') and dollar figures ('$X million/billion') to house style.
· County (Rapides to Rapides Parish)
Louisiana's county equivalents are parishes, as the Census Bureau names them; the record stored Rapides, which the pages printed as Rapides County, and its page sat apart from the parish's own.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
Every correction on the record is on the corrections page.
Nearest records are not computed for a record placed at a parish seat. Browse all data centers in Louisiana.
Answered directly from the verified filings and local actions on this page.
Applied Digital is the developer. No construction contractor is named on the record yet.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
It is proposed, since May 27, 2026. The newest entry, reported September 13, 2026: Meta building Hyperion data center approximately 30 miles east of Monroe in Richland Parish [5].
8 sources on file.
This site is in the SERC Mississippi Valley (SRMV) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Delta Forge 1. Last verified October 6, 2026. https://datacenterrecord.org/projects/delta-forge-1-boyce-la. Accessed November 22, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page and under What happened. Report a correction · Send a tip about Delta Forge 1
Data Center Record, "Delta Forge 1", https://datacenterrecord.org/projects/delta-forge-1-boyce-la. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.