Data Center Record.
Projects / Delta Forge 1 / Timeline

Delta Forge 1, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

1 event, May 27, 2026. Also on the record, under the month each belongs to: 4 statements, 1 figure from another source and 2 dates when source pages were read and verified. The facts, newest first: the record; the place: Louisiana.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

Stages

  1. proposed

Now: proposed. A stage is the record's status after the entry that set it (the definitions).

2026 1 event

  1. (content date)

    proposed

    Cleco Power announced an agreement to supply electricity to the proposed Delta Forge 1 data center in Boyce, Rapides Parish, Louisiana. [2]

  2. Also in September 2026: 4 statements, 1 figure from another source and 2 dates when source pages were read and verified
    1. (source date; the content gives no date of its own)

      Entry

      Meta building Hyperion data center approximately 30 miles east of Monroe in Richland Parish [5]

    2. (source date; the content gives no date of its own)

      Entry

      Applied Digital building $3.6 billion Data Forge 1 data center near Boyce [5]

    3. (said in the source itself)

      Statement · Amy Kremer, Chair of Humans First

      Humans First, conservative group, touring nation to advocate for local control over AI data center construction thetowntalk.com (opens in a new tab) news outlet

    4. (said in the source itself)

      Statement · Humans First, activist group

      Humans First is conducting a cross country bus tour with 34 stops across the nation demanding stronger guardrails on data center development. KALB | News Channel 5 (opens in a new tab) local outlet

    5. (said in the source itself)

      Statement · Gary Musgrove, Save My Louisiana representative

      Gary Musgrove, a Save My Louisiana representative, stated that community concerns about data centers remain unanswered by politicians and local officials. KALB | News Channel 5 (opens in a new tab) local outlet

    6. (said in the source itself)

      Statement · Humans First, activist group

      Activist group Humans First organized a stop of its AI Data Center Revolt tour in Boyce, Louisiana on September 12, 2026 with local residents and activist groups in attendance. KALB | News Channel 5 (opens in a new tab) local outlet

    7. (source date; the content gives no date of its own)

      Figure · The Black Chronicle

      3,600,000,000 USD: Applied Digital data center in Rapides Parish has $3.6 billion investment The Black Chronicle (opens in a new tab) local outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Stage
proposed
Events on the timeline
1
Under the months
7
Stage changes
1
Decisions
0
Statements
4
Figures
1
Entries and decisions under the months
2

Researcher view · basis and source tier on every row · docket and Census GEOIDs · citation and export tools

Commercial and bulk data