  "projects": [
    {
      "slug": "delta-forge-1-boyce-la",
      "name": "Delta Forge 1",
      "summary": "Applied Digital is constructing a 300 acre, $3.6 billion data center campus called Delta Forge 1 in Boyce, Louisiana, with 300 MW in its first phase and initial operations expected as soon as mid 2027.",
      "state": "LA",
      "city": "Boyce",
      "county": "Rapides",
      "status": "rumored",
      "developer": "Applied Digital",
      "capacity_mw": 300,
      "latitude": 31.31125,
      "longitude": -92.44519,
      "location_precision": "county",
      "location_source": "County seat (Alexandria), Wikidata, placed at county level",
      "location_verified_at": "2026-09-16",
      "coordinate_source": "wikidata county seat",
      "location_last_verified": "2026-09-16",
      "site_address": "5941 La Hwy 121, Boyce, LA 70000",
      "site_address_source_url": "https://echo.epa.gov/detailed-facility-report?fid=110072183100",
      "published": "2026-09-05",
      "last_verified": "2026-10-06",
      "cooling_type": "not_disclosed",
      "cooling_type_source_url": null,
      "cooling_fluid": null,
      "cooling_fluid_source_url": null,
      "developer_source_url": null,
      "contractor": null,
      "contractor_source_url": null,
      "site_acres": null,
      "site_acres_disclosed_as": "not_disclosed",
      "site_acres_source_url": null,
      "power_source": null,
      "power_source_url": null,
      "interconnection_status": "not_disclosed",
      "interconnection_source_url": null,
      "water_measure": null,
      "record_url": "https://datacenterrecord.org/projects/delta-forge-1-boyce-la",
      "sources": [
        {
          "title": "Citizens 'have no seat at the table' on data centers, says organizer - thetowntalk.com",
          "url": "https://www.thetowntalk.com/story/news/2026/09/13/residents-support-ai-data-center-revolt-tour-stop-near-boyce-project/91747763007/",
          "publisher": "thetowntalk.com",
          "date": "2026-09-13",
          "source_tier": 4
        },
        {
          "title": "NDAs are hiding data center deals, drawing ire from locals — and attention from lawmakers - Oregon Public Broadcasting - OPB",
          "url": "https://www.opb.org/article/2026/08/27/ndas-are-hiding-data-center-deals-drawing-ire-from-locals-and-attention-from-lawmakers/",
          "publisher": "OPB (via Google News)",
          "date": "2026-08-27",
          "source_tier": 4
        },
        {
          "title": "Cleco to power planned Rapides Parish data center - Rapides Parish Journal",
          "url": "https://rapidesparishjournal.com/2026/05/27/cleco-to-power-planned-rapides-parish-data-center/",
          "publisher": "Rapides Parish Journal",
          "date": "2026-05-27",
          "source_tier": 1
        },
        {
          "title": "Applied Digital secures customer for new 210MW data center campus - Data Center Dynamics",
          "url": "https://www.datacenterdynamics.com/en/news/applied-digital-secures-customer-for-new-210mw-data-center-campus/",
          "publisher": "Data Center Dynamics",
          "date": "2026-06-09",
          "source_tier": 1
        },
        {
          "title": "NDAs are hiding data center deals, drawing ire from locals — and attention from lawmakers - NPR",
          "url": "https://www.npr.org/2026/08/27/nx-s1-5879528/data-center-nda-disclosure-louisiana",
          "publisher": "NPR",
          "date": "2026-08-27",
          "source_tier": 4
        },
        {
          "title": "Developer of Delta data center announces ‘revolutionary’ tech to turn natural gas into water - News From The States",
          "url": "https://www.newsfromthestates.com/article/developer-delta-data-center-announces-revolutionary-tech-turn-natural-gas-water",
          "publisher": "News From The States",
          "date": "2026-09-09",
          "source_tier": 4
        },
        {
          "title": "EPA ECHO detailed facility report: Beard Construction Group LLC, Applied Digital",
          "url": "https://echo.epa.gov/detailed-facility-report?fid=110072183100",
          "publisher": "U.S. Environmental Protection Agency",
          "date": null,
          "source_tier": 2
        }
      ],
      "use_types": [
        {
          "use_type": "not_disclosed",
          "share_percent": null,
          "source_url": null
        }
      ],
      "serves": {
        "tenants": [],
        "tenancy": "not_disclosed",
        "local_service_commitments": [],
        "source_url": null
      },
      "status_history": [
        {
          "status": "rumored",
          "effective_at": "2026-09-13",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-13",
          "summary": "Applied Digital building 3.6 billion dollar Data Forge 1 data center near Boyce",
          "source_url": "https://www.thetowntalk.com/story/news/2026/09/13/residents-support-ai-data-center-revolt-tour-stop-near-boyce-project/91747763007/",
          "source_tier": 4
        },
        {
          "status": "rumored",
          "effective_at": "2026-09-13",
          "date_basis": "source",
          "date_precision": "day",
          "planned": false,
          "source_date": "2026-09-13",
          "summary": "Meta building Hyperion data center approximately 30 miles east of Monroe in Richland Parish",
          "source_url": "https://www.thetowntalk.com/story/news/2026/09/13/residents-support-ai-data-center-revolt-tour-stop-near-boyce-project/91747763007/",
          "source_tier": 4
        }
      ]
    }
  ]
}