Data Center Record.

Running Built from one source

Aunalytics Kalamazoo Data Center

Kalamazoo, Kalamazoo County, MIDeveloper: AunalyticsCensus GEOID 26077

Stage
Running
Power
4 MW
the developer's figure
Buildings
1 building
operator page, verified October 27, 2026
Undisclosed in public filings
Land, Water

Aunalytics operates a commercial cloud and colocation data center at 6395 Technology Avenue in Kalamazoo, Kalamazoo County, Michigan. It is running; the record holds no sourced date for when it reached that stage.

How much water it would use and who would use it have not been disclosed.

1 hearing on the record, 2025

Last verified · 1 source, 0 primary · Built from one source, not yet reviewed in depth by a person. · How to read this page

  • This record: Running, ringed
  • data center
  • Smaller pins: 24 other published records in Michigan
Details
  • this record's location, ringed
  • parcel outline, from the county parcel record
  • city limits, U.S. Census Bureau, on a town level record
  • county boundary

The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.

How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.

What is known

Each figure as its source gave it. The number in brackets is its place in the source list.

Buildings
1 building operator page, verified October 27, 2026
[1] aunalytics.com
Power it would draw
4 MW the developer's figure About 0 percent of New York City's summer peak demand in 2024.
[1] aunalytics.com
Who leads it
Aunalytics as stated by the source
Undisclosed in public filings
Land, Water, Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Aunalytics Kalamazoo Data Center, capacity: 4 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 4 ÷ 10,245 = 0 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Every field, with who said it and when (Researcher view)

Impact figures

FieldValueWho says soSourceLast verified
How much power it needs 4 MW the developer's figure [1] aunalytics.com (opens in a new tab) October 27, 2026
How much water it would use
How loud it would be
Jobs once it runs
Tax it would pay each year

The record's fields

FieldValueWho says soSourceLast verified
Who is building it Aunalytics as stated by the source October 27, 2026
Who is constructing it
How much land
Buildings 1 building operator page, verified October 27, 2026 [1] aunalytics.com (opens in a new tab) October 27, 2026
Where its power comes from
Grid connection
How it is cooled

A blank value cell means not disclosed by any source on file; a blank basis cell means the source gave the figure without saying on what basis.

The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Kalamazoo County and Kalamazoo about data centers, on the record with their source. A rule about the area is not a decision about this record.

October 30, 2025 Kalamazoo, MI Pavilion Township Board Kalamazoo County Data Center Project Halt Pavilion Township Board of Trustees 3clips

On October 30, 2025, developers paused their proposed hyperscale data center in Pavilion Township, Kalamazoo County after intense resident opposition at township board hearings over agricultural zoning, groundwater wells, and noise.

  1. Pavilion Township Officials and Project Co Founder Developer Representative auto captions, unchecked
    "WHY THEY'RE PUTTING THE BRAKES ON THIS PROJECT FOR NOW. YEAH. THAT'S RIGHT. I SPOKE ON THE PHONE WITH DON SHOEMAKER WITH FRANKLIN PARTNERS LLC. HE TELLS ME HE WAS SURPRISED HOW MANY COMMUNITY MEMBERS DIDN'T WANT THEM TO MOVE FORWARD WITH THIS PROJECT, AND THAT THEY ARE LISTENING TO THOSE CONCERNS. THIS PLOT OF LAND ON SOUTH 26TH STREET AND EAST NORTH AVENUE IS WHERE THE REAL ESTATE COMPANY"
  2. Resident public comment Resident Public Comment auto captions, unchecked
    "TARGETED IT AS A GREAT SPOT TO BUILD A NEW DATA CENTER, BUT IT HASN'T GONE AS PLANNED. PEOPLE FELT VERY SURPRISED AND BLINDSIDED AND THAT IT WAS GOING VERY, VERY QUICKLY. KATELYN CLARY LIVES NEARBY AND SAYS THERE'S BEEN A MAJOR PUSHBACK FROM THE COMMUNITY, BEGINNING WITH CONCERNS OVER ELECTRICITY USAGE IN OTHER COMMUNITIES. THERE HAS BEEN"
  3. Pavilion Township Board of Trustees Member Elected Official auto captions, unchecked
    "SUPERVISOR JOHN SPEAR SAYS THE DATA CENTERS HIGH MONTHLY PAYMENTS SHOULDN'T SPILL OVER INTO THE SURROUNDING COMMUNITY. THAT ASIDE, CLARY SAYS RESIDENTS ARE WORRIED ABOUT THE THOUSANDS OF GALLONS OF WATER NEEDED FOR COOLING AT THE SITE AND ITS ENVIRONMENTAL IMPACT IN OTHER COMMUNITIES. WE'VE SEEN GENERATORS GET USED A LOT MORE FOR THESE PLANTS, AND IT WOULD AFFECT THE AIR QUALITY IN LOCAL COMMUNITIES. A LOT OF TIMES"

What happened

No dated entry is on the record yet.

  • Read on October 27, 2026 (the day the page was read; it gives no date of its own)

    Verified facility status from Michigan EGLE permits, MPSC dockets, township planning records, or operator campus specifications.

    [1] aunalytics.com

The site

The pin is the site's address.

The site map is at the top of the page.

Where
6395 Technology Avenue, Kalamazoo, MI 49009, Kalamazoo, Kalamazoo County, Michigan [1] aunalytics.com (opens in a new tab)
How exactly it is located
Exact, at the address
The parcel
No parcel outline in the public record
Nearest homes
Not computed for a record placed at a place center

USGS NAIP aerial view of Aunalytics Kalamazoo Data Center
LAT 42.24654 / LON -85.67511 Imagery: U.S. Geological Survey / USDA NAIP (Public Domain)

Questions about this project

5 questions answered from the record

Answered from the rows on this page.

How big is Aunalytics Kalamazoo Data Center?

The record has 2 measures of its size: 4 MW (the developer's figure, aunalytics.com (opens in a new tab)) and 1 building (operator page, verified October 27, 2026, aunalytics.com (opens in a new tab)). Its acreage is not disclosed.

Who is building Aunalytics Kalamazoo Data Center?

Aunalytics is the developer. No construction contractor is named on the record yet.

How much power and water does Aunalytics Kalamazoo Data Center say it needs?

Power: 4 MW (the developer's figure, aunalytics.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Aunalytics Kalamazoo Data Center stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

What has Kalamazoo or Kalamazoo County decided about it?

No decision by Kalamazoo or Kalamazoo County about data centers is on the record. The Kalamazoo County page and the Michigan scorecard list every rated row the day a person publishes one.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Aunalytics Kalamazoo Data Center Official Disclosure (opens in a new tab), Aunalytics, query feed

1 source on file.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Aunalytics Kalamazoo Data Center", https://datacenterrecord.org/projects/aunalytics-aunalytics-kalamazoo-datacenter-kalamazoo-mi, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Aunalytics Kalamazoo Data Center", https://datacenterrecord.org/projects/aunalytics-aunalytics-kalamazoo-datacenter-kalamazoo-mi. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
42.246545, -85.675111
How the location is known
Location from the site's street address.
Location source
https://aunalytics.com/
Coordinate source
Aunalytics Kalamazoo specification
How capacity was disclosed
the developer's figure
Capacity, if disclosed
4 MW, the developer's figure
Published
October 21, 2026
Last verified
October 27, 2026
Undisclosed in public filings
Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · Aunalytics Kalamazoo Data Center · 1 source, 1 entry, 0 decisions nearby · basis and source tier on every row · verified October 27, 2026

Download CSV JSON