Census GEOID: 37183 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 1 primary and local source

● Running Announced October 27, 2026 · 1 Building · American Tower

American Tower Raleigh Data Center (RA1)

Street address 6011 Chapel Hill Road, Raleigh, NC 27607, Wake County verified address Exact, at the address [1] americantower.com

Overview, regulatory gates and specifications

American Tower operates the RA1 edge colocation data center at 6011 Chapel Hill Road in Raleigh, Wake County, North Carolina. [1] Filings on the record specify disclosed capacity of 2 MW (the developer's figure), 1 planned or operational building. [1] Verified facility status from North Carolina DEQ permits, municipal zoning filings, or operator campus specifications. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Not yet on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [1]
2 MW
the developer's figure

Equivalent to ~1,660 U.S. homes (U.S. EIA 830 homes/MW baseline) · 0.1% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
1 building
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 6011 Chapel Hill Road, Raleigh, NC 27607.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
2 MW developer figure Equivalent to the continuous electricity demand of about 1,660 average U.S. homes based on U.S. Energy Information Administration residential consumption data. Less than 0.1 percent (0.02 percent) of New York City's summer peak demand in 2024.
[1] americantower.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
1 building operator page
[1] americantower.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2018 (8 years)
Who leads it
American Tower as stated by the source
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. American Tower Raleigh Data Center (RA1), capacity: 2 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 2 ÷ 10,245 = 0.0002 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: American Tower
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for American Tower Raleigh Data Center (RA1).

Field / Parameter Permitted / Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 2 MW 2 MW the developer's figure [1] americantower.com
Site Footprint (Acres)
Data Hall Buildings 1 building 1 operator page [1] americantower.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Wake County and Raleigh about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Raleigh Raleigh enacted a data center moratorium just last week bisnow.com (opens in a new tab)
Cary Cary approved an 18 month moratorium on data centers abc11.com (opens in a new tab)
Cary Cary, NC adopted a data center pause or moratorium govtech.com (opens in a new tab)
October 6, 2026 Raleigh, NC Raleigh City Council Six Month Data Center Moratorium Vote Raleigh City Council 3 clips

Raleigh City Council voted on October 6, 2026 to enact a six month moratorium suspending development approvals for large data centers while residents packed council chambers demanding a longer 32 month pause.

  1. Resident public comment Resident Public Comment transcribed from local broadcast report
    "concerns that folks in this community had tonight as they packed those council chambers. Six months, they tell me, just isn't long enough to do the research to find out more on those potential impacts. But city leaders say they're not starting at square one. They've done the research. They've been doing this research well before"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "Community advocates pushed back against data centers and the city's temporary pause on them. During a rally. Their concerns were made clear six months isn't long enough. There's a lot that the city does not know. Can it get all this information in six months? That that becomes a really big question. The same energy outside filled council chambers Tuesday"
  3. ABC11 Broadcast Report Broadcast Report transcribed from local broadcast report
    "Raleigh. This moratorium doesn't have a conditionality about it. It's simply time. So in six months, whether or not the city is able to do what it says it's going to do, the moratorium ends. In a 7 to 1 vote. The City Council approved a temporary pause on data centers development, a move that some say doesn't go far enough. What is the harm in giving Raleigh more time? We have a city of nearly half a million people, and there is still a"
May 19, 2026 Garner, NC Garner Town Council Regular Meeting Garner Town Council 2 clips

Garner Town Council took up Agenda Item 1.3 on May 19, 2026, with Planning Director Jeff Triezenberg presenting a temporary development moratorium on permitting and approvals for data centers, data processing facilities, and cryptocurrency mining operations.

  1. Buddy Gupton, Mayor, and Jeff Triezenberg, Planning Director, Town of Garner Board & Planning Staff transcribed from the official recording
    "in Garner. Thank you very much. With that, we'll move along to item 1.3, which is a moratorum for data centers to be considered. And we'll be calling from we'll be calling on our planning director, Mr. Jeff Treenberg, to give us an overview. This was something that council expressed some interest in at a recent meeting. there's a process to go through it. We just can't say no"
  2. Jeff Triezenberg, Planning Director, Town of Garner Board & Planning Staff transcribed from the official recording
    "to approve a temporary development moratorum on the permitting and issuance of various approvals for what we're terming data centers, data processing facilities, cryptocurrency mining operations and similar undefined uses. we don't expect this to be hopefully any longer than a year, perhaps sooner."
February 14, 2026 Apex, NC Inside the Fight over Data Centers in North Carolina State Lines Special Apex Town Council 3 clips

PBS North Carolina report on Apex Town Council and community proceedings in Apex, NC: Inside the Fight over Data Centers in North Carolina State Lines Special (February 14, 2026).

  1. PBS North Carolina Broadcast Report Broadcast Report transcribed from local broadcast report
    "Today we're going to have a fun conversation about data centers. Data centers are giant warehouses filled with thousands of computer servers. Every email, every stream, every photo you store, it all lives in a building like this. North Carolina already has several. Apple, Google, Meta, they've been here for years. But AI has triggered massive new demand and tech companies are proposing hyperscale data centers across"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "revenue, but they need enormous amounts of electricity and water. In the town of Apex, town leaders are weighing those trade offs right now. P I P Lorraine McEvoy lives in New Hill just outside of Apex close to the site of a proposed data center. I work for a health data technology company. So I'm very familiar with data centers. We use data centers every day. So not anti data center. However, anti hyperscale data center directly"
  3. PBS North Carolina Broadcast Report Broadcast Report transcribed from local broadcast report
    "near the Shearon Harris nuclear power plant. Four buildings designed to run around the clock powering AI and cloud services. No decision has been made, but the proposal has already drawn many neighbors to town hall. The number of people speaks volumes to the town council. We show up, we wear red, we try try pack out the house so that they can see, visibly, like people don't want this. Or, if it's going to have to be here, let's make sure it's something that we can all live with."

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on October 27, 2026 (the day the page was read; it gives no date of its own)

    Verified facility status from North Carolina DEQ permits, municipal zoning filings, or operator campus specifications.

    [1] americantower.com

Nearest data centers in North Carolina

Verified data center records in North Carolina within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Flexential Raleigh (RAL01, RAL02, and RAL03) Morrisville, Wake County 7 mi Running Flexential 11 MW
TierPoint Raleigh Raleigh, Wake County 9 mi Running TierPoint 5 MW
Southeast Raleigh data center Raleigh, Wake County 10 mi Stalled or cancelled Beacon Partners 1 building
Inflow Data Center Durham, Durham County 10 mi Running 11:11 Systems 4 MW
TierPoint Research Triangle Park (RTP) Durham, Durham County 11 mi Running TierPoint 14 MW
CyrusOne Durham DUR1 and DUR2 Durham, Durham County 13 mi Running CyrusOne 12 MW

Blank cell: not disclosed by any source on file.

Common questions about American Tower Raleigh Data Center (RA1)

Answered directly from the verified filings and local actions on this page.

Who is building American Tower Raleigh Data Center (RA1)?

American Tower is the developer. No construction contractor is named on the record yet.

How much power and water does American Tower Raleigh Data Center (RA1) say it needs?

Power: 2 MW (the developer's figure, americantower.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does American Tower Raleigh Data Center (RA1) stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

What has Raleigh or Wake County decided about it?

Raleigh: Raleigh enacted a data center moratorium just last week (October 1, 2026, bisnow.com (opens in a new tab)); and Cary: Cary approved an 18 month moratorium on data centers (reported August 28, 2026, abc11.com (opens in a new tab)). 3 events are on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. American Tower Raleigh Data Center (RA1) Official Disclosure (opens in a new tab), American Tower, news outlet

1 source on file.

Regional grid context

This site is in the SERC Virginia and Carolina South (SRVC-S) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "American Tower Raleigh Data Center (RA1)", https://datacenterrecord.org/projects/american-tower-ra1-raleigh-nc, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "American Tower Raleigh Data Center (RA1)", https://datacenterrecord.org/projects/american-tower-ra1-raleigh-nc. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
35.78812, -78.726568
How the location is known
Location from the site's street address.
Location source
https://www.americantower.com/us/data-centers/
Coordinate source
American Tower Raleigh RA1 specification
How capacity was disclosed
the developer's figure
Capacity, if disclosed
2 MW, the developer's figure
Published
October 21, 2026
Last verified
October 27, 2026
Not disclosed
Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · American Tower Raleigh Data Center (RA1) · 1 source, 1 entry, 3 decisions nearby · basis and source tier on every row · verified October 27, 2026

Download CSV JSON