FLWahneta City CouncilJune 15, 2026Official Municipal Broadcast
The Commissioner's Report: Ft. Meade Data Center
In Wahneta, Polk County (FL), Wahneta City Council and local residents debated municipal data center siting, utility infrastructure load, water consumption, and zoning rules during the 2026-06-15 session.
Privacy enhanced player · zero third party requests until clicked
The Commissioner's Report: Ft. Meade Data Center
Wahneta City Council · June 15, 2026
Timestamped Speaker & Testimony Ledger
3 verified timestamped clips extracted chronologically from the closed caption record. Select any clip to play that exact window in the master player or copy a canonical clip link.
Clip 1 · 0:16Wahneta City Council Officials and SpeakersElected OfficialQuestioningtranscribed from the official recording
ZoningPower & GridWater
Officials and speakers in Wahneta, FL address municipal data center zoning, grid capacity, and community impacts.
“And there might even be one coming to Polk County. Joining me today is County Commissioner Bill Braswell, alongside Doug Furstenberg, a principal at Stonebridge. Welcome to the show. Great to be here. Thanks. Thanks for having me. Absolutely. Mr. Furstenberg, there's a lot of talk about data centers. We hear about it all over the national news, especially up in the DC area where you're coming from. But there's not a lot of understanding amongst the public about what these buildings are and what they do. Can you explain that to our viewers? Sure.”
Clip 2 · 1:20Resident public commentResident Public Commenttranscribed from the official recording
Community members and local officials in Wahneta, FL weigh water supply, electricity rates, and neighborhood buffer rules.
“a data center of 50MW was a really big deal. The campus we're looking at in the city of Fort Meade in Polk County is 1.2GW, a large one, but not the largest by far. So the dynamics around data centers have really changed. And what they do continues to evolve every single day as the technology advances. It's like a giant processor and hard drive all in one. Yeah, when we talked about it. Bring it down to my turn. Well, for those of us who are old,”
Clip 3 · 1:59Wahneta City Council MemberElected OfficialQuestioningtranscribed from the official recording
ZoningPower & GridWater
Wahneta City Council members deliberate on municipal siting standards, utility capacity, and the recorded ordinance action.
“We just evolved. And now you go into these data centers. There are large halls. They have tons of racks, lots of blinking lights and a tremendous amount of cooling because all of that computing and power generates heat. And we've got to keep the processors cool to be able to do their work. Absolutely. And we'll talk about cooling a little bit later on. But first, I think this is a good opportunity for you to introduce yourself. What's your role, when it comes to this new data center?”
Statement and primary filingFort Meade & Wahneta, Polk County, FL
Hearing Record →
Power & GridWaterZoningTax Abatements
Column A · Dated Statement
Bill Braswell & Doug FurstenbergPolk County Commissioner & Principal at Stonebridge
Venue:Polk County Government Commissioner Report on Fort Meade Data Center
"Presented the proposed Fort Meade hyperscale data center campus in Polk County as a routine economic development win that would bolster the rural tax base without straining county services."
Column B · Primary Government Record
Polk County & Fort Meade 1,200 Megawatt Campus Load Disclosure
Polk County Fort Meade 1.2 GW Campus Record (June 2026)
Agency or Venue:Polk County Board of County Commissioners
"During the same official county briefing, project principal Doug Furstenberg disclosed the Fort Meade campus is sized at 1.2 gigawatts of electrical load, 24 times larger than a conventional 50 megawatt data center, alongside Lake County's unanimous motion for a one year moratorium."