Birmingham City Council Six Month Hyperscale Data Center Moratorium Vote
On March 3, 2026, the Birmingham City Council voted to enact a 6 month moratorium on hyperscale data centers across the city to study water supply, Alabama Power grid demand, and neighborhood land use impacts.
Privacy enhanced player · zero third party requests until clicked
Birmingham City Council Six Month Hyperscale Data Center Moratorium Vote
Birmingham City Council · March 3, 2026
Timestamped Speaker & Testimony Ledger
3 verified timestamped clips extracted chronologically from the closed caption record. Select any clip to play that exact window in the master player or copy a canonical clip link.
- Clip 1 · 0:21 Birmingham City Council Elected Official Opposed auto captions, uncheckedMoratorium Zoning Water Power & Grid
Birmingham City Council passes a 6 month moratorium on hyperscale data centers to evaluate water and electrical grid impacts.
"ACCORDING TO THE DATA CENTER MAP, THERE ARE 19 DATA CENTERS ALREADY BUILT OR UNDER CONSTRUCTION IN OUR STATE. THERE ARE EIGHT IN CENTRAL ALABAMA. IN BIRMINGHAM, THERE ARE PLANS FOR AN ARTIFICIAL INTELLIGENCE CENTER IN D.C. BLOCKS IS LOOKING TO EXPAND ITS EXISTING DATA CENTER IN TITUSVILLE. HOWEVER, ANY ADDITIONAL PROPOSALS WITHIN BIRMINGHAM CITY LIMITS ARE CURRENTLY ON HOLD. WVTM 13 LISA CRANE JOINS US LIVE AND LOCAL IN BIRMINGHAM, AND LISA BIRMINGHAM CITY COUNCIL MEMBERS HELD A PUBLIC HEARING ON DATA CENTERS TODAY."
- Clip 2 · 0:52 Resident public comment Resident Public Comment auto captions, unchecked
Residents and community speakers address Birmingham City Council regarding local water, power grid, noise, and zoning impacts.
"WHAT CAME OUT OF THAT MEETING? WELL, THE COUNCIL VOTED ON A SIX MONTH MORATORIUM ON DATA CENTERS. BEHIND ME, YOU CAN SEE THE FUTURE HOME OF THE AI FACTORY. BUT FOR NOW, NO MORE HYPERSCALE DATA CENTERS OR AI FACTORIES WILL BE ALLOWED TO START THE PERMITTING PROCESS UNTIL CITY LEADERS CAN ACTUALLY GET A HANDLE AND DEFINE EXACTLY WHAT THESE BUILDINGS ARE AND HOW THESE NEW FACILITIES ACTUALLY FIT INTO THE CURRENT ZONING REGULATIONS. THIS IS AN AREA THAT WE REALLY NEED TO GET A HANDLE ON BEFORE WE DO ANYTHING ELSE."
- Clip 3 · 1:31 Birmingham City Council Member Elected Official Opposed auto captions, uncheckedMoratorium Zoning Water Power & Grid
Birmingham City Council members deliberate on municipal siting standards, utility capacity, and the recorded ordinance action.
"ALMOST TWO DOZEN RESIDENTS VOICED THEIR CONCERNS ABOUT DATA CENTERS TO BIRMINGHAM CITY COUNCIL MEMBERS AT A PUBLIC HEARING. MOST PEOPLE ARE JUST TRYING TO UNDERSTAND WHAT THEY ARE AND WHY THEY NEED MASSIVE AMOUNTS OF ELECTRICITY, WATER AND OTHER RESOURCES. THE INDUSTRY SO NOVEL IT DOESN’T REALLY FIT INTO CURRENT ORDINANCES OR ZONING REGULATIONS. IT IS SOMETHING NEW THAT OUR ORDINANCE DOESN’T CURRENTLY CONSIDER. SO IT’S SOMETHING THAT WE WANT TO PLAN FOR IN A WAY THAT RESPONSIBLY ALLOWS FOR THIS TYPE OF GROWTH IN THE CITY, WHILE TAKING INTO ACCOUNT, YOU KNOW, THE THE BEST INTEREST OF OUR"
Using this data in a report? Support the record.
Related Records on Data Center Record
Jurisdiction & Local Rules
Linked Data Center Projects (2)
- Patmos Fairfield Data Center · Fairfield
- QTS Bessemer · Bessemer