Data centers in Houston, Texas

Houston has 5 data centers on the record: 3 running and 2 proposed. No city rule about data centers is on the record for Houston yet. Harris County's own decisions are on the Harris County page.

Updated · Every line below links to its source · How the record works

How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.

The 5 data centers in Houston

Newest activity first

Each row is one site with its stage, its latest dated entry and what its sources disclose. A figure no source gives reads Not disclosed.

  1. Reported Built from one source

    CyrusOne Houston HOU3-HOU4

    Houston, Harris County · CyrusOne

    No dated entry on the record yet.

    Land
    Not disclosed
    Power
    Not disclosed
    Water
    Not disclosed
    Tenant
    Not disclosed
  2. Running Built from one source

    DataBank Houston data center

    Houston, Harris County · DataBank

    No dated entry on the record yet.

    Land
    Not disclosed
    Power
    Not disclosed
    Water
    Not disclosed
    Tenant
    Not disclosed
  3. Running Built from one source

    Digital Realty Houston

    Houston, Harris County · Digital Realty

    No dated entry on the record yet.

    Land
    Not disclosed
    Power
    Not disclosed
    Water
    Not disclosed
    Tenant
    Not disclosed
  4. Reported Built from one source

    East Houston data center (Chron)

    Houston, Harris County

    No dated entry on the record yet.

    Land
    Not disclosed
    Power
    Not disclosed
    Water
    Not disclosed
    Tenant
    Not disclosed
  5. Running Built from one source

    Equinix HO1

    Houston, Harris County · Equinix

    No dated entry on the record yet.

    Land
    Not disclosed
    Power
    Not disclosed
    Water
    Not disclosed
    Tenant
    Not disclosed

Where

5 data centers in Houston: 3 running, 2 proposed. A dashed edge means the exact site is not in the public record; every pin here marks a town or the county.

The outline is Houston's boundary from the U.S. Census Bureau. Tap a pin for that data center's facts and a link to its page.

What was said

MD Anderson Cancer Center delayed two projects planned for next five years due to data center boom impacts
Karen Mooney, MD Anderson Cancer Center · September 8, 2026 · paraphrased · Bisnow trade press
Data centers have tied up large swaths of steel and concrete supply
Synjyn Dodd, Hoar Construction · September 8, 2026 · paraphrased · Bisnow trade press
Paul Bettencourt, state senator, said counties do not have the legal authority to ban data center construction
Paul Bettencourt, State Senator (R-Houston), chair of Senate Local Government Committee · June 11, 2026 · paraphrased · Houston Public Media local outlet

Every Texas statement, by speaker

14 more statements on this page

Karen Mooney, MD Anderson Cancer Center

Data center development in Texas is straining demand for construction materials and equipment

September 8, 2026, Bisnow · Bisnow trade press · the record (Paraphrased; said in the source itself)

Chris Tomlinson, journalist

Counties asked Attorney General Ken Paxton what power they retained, and he did not answer six months later

August 27, 2026, YouTube · YouTube video · the record (Paraphrased; said in the source itself)

Chris Tomlinson, journalist

Abbott and Republican lawmakers passed multiple laws providing property tax cuts to data centers

August 27, 2026, YouTube · YouTube video · the record (Paraphrased; said in the source itself)

Chris Tomlinson, journalist

Governor Greg Abbott invited data center companies to Texas and promised low taxes, regulations, cheap electricity and water

August 27, 2026, YouTube · YouTube video · the record (Paraphrased; said in the source itself)

Meta spokesperson

Meta pledged to pay for own infrastructure and launched fund for water and energy infrastructure investment

August 10, 2026, Houston Public Media · Houston Public Media local outlet · the record (Paraphrased; said in the source itself)

OpenAI pledged to pay for own infrastructure, support new electricity sources and minimize water usage

August 10, 2026, Houston Public Media · Houston Public Media local outlet · the record (Paraphrased; said in the source itself)

Republican Party of Texas Legislative Priorities Committee member and Bexar County judge candidate

Patrick Von Dohlen said at least a quarter of 160 plus testimony speakers were concerned about AI data centers

June 11, 2026, Houston Public Media · Houston Public Media local outlet · the record (Paraphrased; said in the source itself)

Republican Party of Texas proposes prohibiting all tax payer funded incentives, property tax abatements, corporate welfare, or economic development packages for data centers

June 11, 2026, Houston Public Media · Houston Public Media local outlet · the record (Paraphrased; said in the source itself)

Republican Party of Texas proposes requiring major data centers to secure their own independent power generation and non potable water sources

June 11, 2026, Houston Public Media · Houston Public Media local outlet · the record (Paraphrased; said in the source itself)

Republican Party of Texas convention delegate

Rolando Garcia said data centers use massive amounts of water and electricity, and Texas is already having problems with its electrical grid and water infrastructure

June 11, 2026, Houston Public Media · Houston Public Media local outlet · the record (Paraphrased; said in the source itself)

Republican Party of Texas proposes granting cities and counties final authority over zoning, land development, and comprehensive planning decisions for data centers

June 11, 2026, Houston Public Media · Houston Public Media local outlet · the record (Paraphrased; said in the source itself)

Republican Party of Texas Legislative Priorities Committee named regulating AI as the 15th of its top 15 priorities for the 2027 Legislature

June 11, 2026, Houston Public Media · Houston Public Media local outlet · the record (Paraphrased; said in the source itself)

Republican Party of Texas proposes mandating that data center construction companies pay full impact fees to compensate communities

June 11, 2026, Houston Public Media · Houston Public Media local outlet · the record (Paraphrased; said in the source itself)

State Senator (R-Houston), chair of Senate Local Government Committee

Paul Bettencourt said he is open to Texas' 254 counties having more input on data centers but stressed critical importance to state and country economic development

June 11, 2026, Houston Public Media · Houston Public Media local outlet · the record (Paraphrased; said in the source itself)

Disclosed figures

nothing disclosed by 5 records

Power, water, jobs and tax, summed only where a data center disclosed the figure; what each facility is for; how each is cooled. Nothing here is estimated.

Power, water, jobs and tax

FigureDisclosed totalDisclosedNot disclosedBasis
PowerNot disclosed05Not disclosed by any of the 5 records
Water, stated per dayNot disclosed05Not disclosed by any of the 5 records
Water, stated per yearNot disclosed05Not disclosed by any of the 5 records
Permanent jobsNot disclosed05Not disclosed by any of the 5 records
Tax each yearNot disclosed05Not disclosed by any of the 5 records

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

By what the facilities are for

UseRecordsPowerWaterJobsTax each year
Not disclosed5Not disclosedNot disclosedNot disclosedNot disclosedNot disclosed: power, water, jobs, tax each year

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

What the facilities are for

No source on file states what any of the 5 tracked facilities in Houston are for.

How the facilities are cooled

No source on file states how any of the 5 tracked facilities in Houston are cooled.

Cite this page

Data Center Record, "Data centers in Houston, Harris County, Texas", https://datacenterrecord.org/states/tx/harris-county/houston, updated September 17, 2026.

Cite this page

Data Center Record, "Data center records in Houston, Harris County, Texas", https://datacenterrecord.org/states/tx/harris-county/houston. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.

The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change

The rows here are part of the Texas export.