Data centers in Monroe County, Georgia
Monroe County has 1 data center on the record; it is proposed. No county or city rule about data centers is on the record for Monroe County yet.
How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.
The data center in Monroe County
Every Monroe County record 1 record · blank cell: not disclosed · sort by any column
| Facility and county | Stage | Operator | Power (MW) | Latest entry |
|---|---|---|---|---|
| Bolingbroke Technology Campus (Forsyth) Forsyth, Monroe County | Proposed Waiting on permits | Trammell Crow Company | Trammell Crow Company proposes a $21 billion, 1,632 acre data center campus along I 75 in Forsyth, Georgia, comprising up to 12 million square feet across 21 data center warehouses. ajc.com (opens in a new tab) query feed November 28, 2025 |
A blank cell means not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.
| Record | Place | Stage | Operator | MW | Basis | Located | Tier | Verified |
|---|---|---|---|---|---|---|---|---|
| Bolingbroke Technology Campus (Forsyth) | Forsyth, Monroe | Proposed | Trammell Crow Company | site | 1 | 2026-10-26 |
Tier 1: an official or company source. Tier 2: a news report resolving to the outlet's own page. Located: a site coordinate from a permit, a parcel or an address, or the county or town centroid. Verified: the last day a person read the source. A blank cell means not disclosed by any source on file.
What happened
-
Now proposedBolingbroke Technology Campus (Forsyth)
ajc.com (opens in a new tab) query feed
Nearby places with records
Distances run between the centers the Census Bureau gives each place. Every Georgia county.
Disclosed figures
water from 1 record
Power, water, jobs and tax
| Figure | Disclosed total | Disclosed | Without a figure | Basis |
|---|---|---|---|---|
| Power | 0 | 1 | ||
| Water, stated per day | 1,500,000 gallons a day | 1 | 0 | 1 the developer's figure |
| Permanent jobs | 0 | 1 | ||
| Tax each year | 0 | 1 |
A blank total means no record disclosed the figure; the count without one says how many.
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
By what the facilities are for
| Use | Records | Power | Water | Jobs | Tax each year |
|---|---|---|---|---|---|
| No stated use | 1 | 1,500,000 gallons a day |
A blank cell means no record with that use disclosed the figure.
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
What the facilities are for
No source on file states what any of the 1 tracked facility in Monroe County is for.
How the facilities are cooled
No source on file states how any of the 1 tracked facility in Monroe County is cooled.
About this data
Report a correction · Send a tip about Monroe County · The rows here are part of the Georgia export.
Cite this page
Data Center Record, "Data center records in Monroe County, Georgia", https://datacenterrecord.org/states/ga/monroe-county. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.
For researchers
- Level
- county
- Census GEOID
- 13207
- Census geography
- County, Monroe County
- Rating
- Not rated