Data Center Record.
States / Arkansas

Arkansas, year by year.

Every act on the record for Arkansas, on the day it happened, newest first by month. Under each month, one tap away, the background, plans and statements the same sources carried. The counts are the state hub's records; nothing is estimated.

The record by year

On the record as of October 27, 2026.

An act sits on the day it happened: the day its own sentence names, or the day its source gives for it. An act the record knows only from the date of the article that reported it sits under that article's month, one tap away, marked Reported with the article's date. So do background, plans and statements, which are not acts. The same act reported by several sources is one line with the reports behind it, on its day where any of them dates it. The milestones alone, for every state, are on the timeline.

29 acts on the line for Arkansas, from 134 dated lines in the records' histories and the scorecard. 25 more acts are dated only by the article that reported them and sit under their month. 11 lines report an act already listed. 69 lines are background, plans or statements. 14 lines sit on a date other than the one they were filed under, because their own sentence names the day, the month or the year it happened; each says so. Where a line sits is read from its own words and the row is never changed (how dates are read).

Narrow the acts
Kind
Topic

Each count is the number of lines on this page the chip keeps. Topics are matched from the words of each line and are a finding aid, not a fact about the event.

2026 17 acts on the line from 24 reports; 25 reported, dated only by the article; 57 lines of background, plans and statements

October 2026 2 acts on the line

  1. Moratorium rejected Little Rock, Arkansas

    Little Rock Board of Directors rejected a six month moratorium on large data centers in a 4-4 vote

    arkansasonline.com (opens in a new tab), local outlet

  2. Filing Google West Memphis Data Center, West Memphis, Arkansas

    Entergy Arkansas filed heavily redacted amended application for Google West Memphis data center project.

    arkansasonline.com (opens in a new tab), local outlet

September 2026 9 acts on the line from 13 reports; 12 reported; 33 lines of background, plans and statements

  1. Ordinance Pulaski County, Arkansas

    Pulaski County Quorum Court on September 22, 2026 passed 11-4 an ordinance to regulate large data centers in unincorporated parts of the county, covering noise, fire safety, and water consumption. AVAIO Digital's proposed $6 billion, 1 gigawatt Wrightsville campus will be subject to the new rules.

    arktimes.com (opens in a new tab), local outlet

  2. Litigation Pulaski County, Arkansas

    Pulaski County Quorum Court voted 11-4 Tuesday night in favor of new data center regulations

    ualrpublicradio.org (opens in a new tab), local outlet

  3. Litigation Pulaski County, Arkansas

    Pulaski County Quorum Court on Tuesday approved a measure to establish new regulations on data centers

    arkansasonline.com (opens in a new tab), local outlet

  4. Arkansas

    Lawmakers questioned Entergy on Arkansas data center projects it is powering on September 15, 2026

    magnoliareporter.com (opens in a new tab), local outlet

  5. Hearing Arkansas

    Arkansas Legislature's Joint Energy Committee held a hearing on Tuesday regarding Google and Entergy's partnership to power the West Memphis data center

    katv.com (opens in a new tab), local outlet

  6. Ordinance North Little Rock, Arkansas

    North Little Rock city council approved an ordinance applying zoning regulations to future data center campuses within city limits on Monday night, September 15, 2026.

    nwaonline.com (opens in a new tab), local outlet (the weekday its sentence names, the last before the report; filed under Sep 15, 2026)

    1 more report of this
    1. Reported September 15 North Little Rock City Council approved an ordinance applying zoning regulations to future data center campuses. arkansasonline.com (opens in a new tab)
  7. Litigation Arkansas

    U.S. District Judge Lee Rudofsky denied Entergy's request for temporary restraining order on Wednesday after hearing arguments in the trade secret lawsuit

    kvom.com (opens in a new tab), local outlet

    2 more reports of this
    1. Reported September 2 Judge Lee Rudofsky denied Entergy's request for temporary restraining order against Arkansas Democrat Gazette and Arkansas Times cnbc.com (opens in a new tab)
    2. Reported September 3 U.S. District Judge Lee P. Rudofsky denied Entergy's temporary restraining order request and stated the First Amendment gives significant concern about prior restraint yahoo.com (opens in a new tab)
  8. Litigation Google West Memphis Data Center, West Memphis, Arkansas

    U.S. District Judge Lee Rudofsky denied Entergy's request for a temporary restraining order on September 2, 2026

    kait8.com (opens in a new tab), local outlet (the day its own sentence names)

    1 more report of this
    1. Reported September 3 Judge Lee Rudofsky denied Entergy request for a restraining order against the news outlets youtube.com (opens in a new tab)
  9. Arkansas

    Unredacted APSC records made public in early September regarding contract details

    pv-magazine-usa.com (opens in a new tab), trade press (the month its own sentence names; no day is given; filed under Sep 23, 2026)

Reported in September 2026, dated only by the article that carried them: 12 acts
  1. Google West Memphis Data Center, West Memphis, Arkansas

    Entergy and Google began talks about a data center in West Memphis; three months later, work on the Generating Arkansas Jobs Act began

    arkansasonline.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Hearing Arkansas

    State lawmakers held joint energy committee meeting to question impact on ratepayers

    actionnews5.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  3. Litigation Arkansas

    A federal judge denied Entergy's request for a temporary restraining order to prohibit newspapers from disclosing details about Entergy's agreements with Altitude Capital LLC, a Google subsidiary.

    ualrpublicradio.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  4. Denial Arkansas

    Arkansas Public Service Commission denied Entergy Arkansas's request for a 20 year power purchase agreement for the proposed 440 megawatt Big Island Solar facility in Mississippi County.

    myarklamiss.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  5. Litigation Google West Memphis Data Center, West Memphis, Arkansas

    Entergy Arkansas filed a notice of dismissal of its lawsuit against the Arkansas Democrat Gazette, Arkansas Times, and a resident over publication of details from a West Memphis data center agreement.

    kjnbtv.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

    1 more report of this
    1. Reported September 17 Entergy Arkansas filed and then dismissed a lawsuit against the Arkansas Democrat Gazette, Arkansas Times and Jessica Kivell over publication of details about its data center agreement with Altitude Capital LLC. ualrpublicradio.org (opens in a new tab)
  6. Arkansas

    Entergy Arkansas added a rider to power bills that charges just over half a cent per kilowatt hour as a result of the Generating Arkansas Jobs Act of 2025

    magnoliareporter.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  7. Ordinance North Little Rock, Arkansas

    North Little Rock approved new zoning regulations establishing where data center campuses can operate and what requirements developments must meet before receiving approval.

    katv.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  8. Litigation Arkansas

    Judge ruled against Arkansas utility in freedom of the press fight concerning data center information

    okenergytoday.com (opens in a new tab), trade press (dated only by the report that carried it, so under the month of the report)

  9. Litigation Arkansas

    Entergy filed lawsuit over West Memphis Google data center

    actionnews5.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  10. Arkansas

    Entergy Arkansas sought a temporary restraining order to prevent disclosure of trade secrets related to a planned data center near West Memphis

    kait8.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  11. Litigation Arkansas

    Judge denied effort to block Arkansas news outlets from publishing data center agreement details

    arkansasadvocate.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  12. Approval Google West Memphis Data Center, West Memphis, Arkansas

    Special rate contract between Google and Entergy approved by Arkansas Public Service Commission in December

    actionnews5.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for September 2026, not acts of their own: 33 lines of background, plans and statements
  1. Pulaski County, Arkansas

    Judge Barry Hyde has seven days to veto the ordinance before it takes immediate effect under emergency provision.

    arktimes.com (opens in a new tab) (a description, not an act)

  2. Pulaski County, Arkansas

    County Judge Barry Hyde has seven days to veto the new regulations

    ualrpublicradio.org (opens in a new tab) (a description, not an act)

  3. Pulaski County, Arkansas

    The regulations require prospective data center projects to submit electrical load analyses, water and wastewater plans, land use suitability studies and decommissioning plans

    ualrpublicradio.org (opens in a new tab) (a description, not an act)

  4. Pulaski County, Arkansas

    The regulations require prospective data center projects to demonstrate development won't materially impair utilities and other public infrastructure but do not limit water or power use

    ualrpublicradio.org (opens in a new tab) (a description, not an act)

  5. Google West Memphis Data Center, West Memphis, Arkansas

    Google exploring second potential data center project in Little Rock

    actionnews5.com (opens in a new tab) (a plan or a schedule, not an act yet)

  6. Google West Memphis Data Center, West Memphis, Arkansas

    Google partnership with Entergy Arkansas is for 20 years

    actionnews5.com (opens in a new tab) (a description, not an act)

  7. Google West Memphis Data Center, West Memphis, Arkansas

    Construction on Google West Memphis facility has been ongoing for nearly a year

    actionnews5.com (opens in a new tab) (a description, not an act)

  8. Google West Memphis Data Center, West Memphis, Arkansas

    A federal judge denied Entergy's request to block publication of agreement details earlier in September 2026.

    kjnbtv.com (opens in a new tab) (an act at a time its sentence does not give)

  9. Arkansas

    Generating Arkansas Jobs Act of 2025 allows utilities to begin recouping costs of building new power generation facilities from ratepayers before those facilities are completed and charges just over half a cent per kilowatt hour used per month.

    arkansasadvocate.com (opens in a new tab) (a description, not an act)

  10. Arkansas

    Arkansas Public Service Commission approved the rider earlier in 2026 that pays for three power generation facilities being built by Entergy Arkansas, including Cypress Solar for Google West Memphis data center.

    arkansasadvocate.com (opens in a new tab) (an act at a time its sentence does not give)

  11. Arkansas

    Representative Vasquez supports a temporary moratorium on data centers in Grant County citing concerns about water use, electricity demand, and emissions.

    quiverquant.com (opens in a new tab) (a description, not an act)

  12. Google West Memphis Data Center, West Memphis, Arkansas

    Google is exploring a potential data center project in Little Rock

    4029tv.com (opens in a new tab) (a plan or a schedule, not an act yet)

  13. Google West Memphis Data Center, West Memphis, Arkansas

    Construction is already underway on Google's data center in West Memphis

    4029tv.com (opens in a new tab) (a description, not an act)

  14. North Little Rock, Arkansas

    Data center campuses are allowed as a conditional use in I-3 industrial zones.

    katv.com (opens in a new tab) (a description, not an act)

  15. North Little Rock, Arkansas

    Regulations address utilities, noise, and proximity to residential areas.

    katv.com (opens in a new tab) (no act in the sentence)

  16. North Little Rock, Arkansas

    The ordinance includes an emergency clause, meaning regulations took effect immediately after approval.

    katv.com (opens in a new tab) (a description, not an act)

  17. Arkansas

    Arkansas Legislative Black Caucus meeting scheduled for September 10, 2026 at 9 a.m. at South Arkansas College East Campus Center

    kvom.com (opens in a new tab) (a plan or a schedule, not an act yet)

  18. Google West Memphis Data Center, West Memphis, Arkansas

    Construction work was continuing at the Google project on June 1, 2026

    arkansasonline.com (opens in a new tab) (no act in the sentence)

  19. Arkansas

    EPA plan to shroud details on data center sites

    arkansasonline.com (opens in a new tab) (a plan or a schedule, not an act yet)

  20. Google West Memphis Data Center, West Memphis, Arkansas

    Google's data center in West Memphis is under construction

    yahoo.com (opens in a new tab) (a description, not an act)

  21. Arkansas

    Entergy lawyers asked judge to restrain journalists from publishing mistakenly shared data center documents

    arktimes.com (opens in a new tab) (a statement; who said what is on the statements pages)

  22. Arkansas

    Judge considering blocking Arkansas news outlets from publishing data center pact details

    ualrpublicradio.org (opens in a new tab) (a plan or a schedule, not an act yet)

  23. Google West Memphis Data Center, West Memphis, Arkansas

    Google data center agreement with Entergy has 20 year term

    arkansasadvocate.com (opens in a new tab) (a description, not an act)

  24. Google West Memphis Data Center, West Memphis, Arkansas

    Google West Memphis data center campus will have five data centers, office buildings on approximately 1,200 acres

    actionnews5.com (opens in a new tab) (a plan or a schedule, not an act yet)

  25. Arkansas

    Arkansas Public Service Commission approved Cypress earlier in 2026

    deltaplexnews.com (opens in a new tab) (an act at a time its sentence does not give)

  26. Arkansas

    Judge expected to rule on Entergy's request to stop Democrat Gazette from publishing data center info

    arkansasonline.com (opens in a new tab) (a plan or a schedule, not an act yet)

  27. Google West Memphis Data Center, West Memphis, Arkansas

    U.S. District Judge Lee Rudofsky expected to rule Wednesday September 3 2026 on Entergy's request to stop Arkansas Democrat-Gazette from publishing data center details

    arkansasonline.com (opens in a new tab) (a plan or a schedule, not an act yet)

  28. Google West Memphis Data Center, West Memphis, Arkansas

    Arkansas Cypress is expected to begin operating by the end of 2028

    deltaplexnews.com (opens in a new tab) (a plan or a schedule, not an act yet)

  29. Google West Memphis Data Center, West Memphis, Arkansas

    Google's West Memphis data center is served under special rate agreement between Entergy Arkansas and Altitude LLC, a Google subsidiary.

    deltaplexnews.com (opens in a new tab) (a description, not an act)

  30. Google West Memphis Data Center, West Memphis, Arkansas

    Arkansas Public Service Commission approved Arkansas Cypress project earlier in 2026.

    deltaplexnews.com (opens in a new tab) (an act at a time its sentence does not give)

  31. Google West Memphis Data Center, West Memphis, Arkansas

    Arkansas Cypress project is expected to begin operating by the end of 2028.

    deltaplexnews.com (opens in a new tab) (a plan or a schedule, not an act yet)

  32. Google West Memphis Data Center, West Memphis, Arkansas

    Total package tied to Google's West Memphis data center is $716 million, with $190 million designated for transmission system upgrades.

    deltaplexnews.com (opens in a new tab) (a description, not an act)

  33. Google West Memphis Data Center, West Memphis, Arkansas

    Google will contribute $526 million toward Entergy Arkansas' Arkansas Cypress Solar and Battery project.

    deltaplexnews.com (opens in a new tab) (a plan or a schedule, not an act yet)

August 2026 1 act on the line from 2 reports; 8 reported; 8 lines of background, plans and statements

  1. Moratorium Arkansas

    Arkansas Democratic gubernatorial nominee Fred Love proposed a resolution for the Arkansas Legislative Council to suggest a pause on data center development and opening.

    arkansasonline.com (opens in a new tab), local outlet

    1 more report of this
    1. Reported August 21 Fred Love proposed a resolution for the Arkansas Legislative Council to suggest a pause on data center development and openings arkansasonline.com (opens in a new tab)
Reported in August 2026, dated only by the article that carried them: 8 acts
  1. Ordinance Arkansas

    Proposed data center ordinance received first reading

    arktimes.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Litigation Pulaski County, Arkansas

    Pulaski County Quorum Court delayed final vote on proposed regulations for data center development.

    arkansasonline.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  3. Moratorium adopted Madison County, Arkansas

    Madison County Quorum Court unanimously voted to approve a data center moratorium running through August 31, 2029

    yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  4. Moratorium Madison County, Arkansas

    The moratorium took effect immediately with an emergency clause

    yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  5. Arkansas

    Lawmakers referred Love's resolution for review at the Arkansas Legislative Council meeting

    arkansasonline.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  6. Fayetteville, Arkansas

    Fayetteville City Council unanimously passed an amendment to strengthen the city's data center regulations

    yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  7. Fayetteville, Arkansas

    City implemented harsher penalties for violating city code, including withholding utilities or revoking business licenses

    yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  8. Ordinance Pulaski County, Arkansas

    Pulaski County voted down data center ordinance

    thv11.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for August 2026, not acts of their own: 8 lines of background, plans and statements
  1. Pulaski County, Arkansas

    Pulaski County Quorum Court scheduled to vote on emergency ordinance establishing conditional use permit process for hyperscale data centers

    katv.com (opens in a new tab) (a plan or a schedule, not an act yet)

  2. Pulaski County, Arkansas

    Ordinance would establish review of factors including power and water use, noise and traffic for hyperscale data center projects in unincorporated Pulaski County

    katv.com (opens in a new tab) (a plan or a schedule, not an act yet)

  3. Pulaski County, Arkansas

    Ordinance provision states that purchasing property, spending money or beginning certain work would not exempt project from new requirements, potentially affecting AVAIO's proposed project near Wrightsville

    katv.com (opens in a new tab) (a plan or a schedule, not an act yet)

  4. Pulaski County, Arkansas

    Proposal would require conditional use permits for large scale data centers in unincorporated Pulaski County.

    katv.com (opens in a new tab) (a plan or a schedule, not an act yet)

  5. Pulaski County, Arkansas

    Proposal would set standards for data center operations, monitoring, and inspections.

    katv.com (opens in a new tab) (a plan or a schedule, not an act yet)

  6. Arkansas

    Arkansas communities are putting data centers on hold

    arktimes.com (opens in a new tab) (a description, not an act)

  7. Fayetteville, Arkansas

    Data centers must follow stronger protections for noise levels and limits on energy and water use

    yahoo.com (opens in a new tab) (a description, not an act)

  8. Arkansas

    Arkansas cities weighing data center restrictions amid growth and environmental concerns

    kvom.com (opens in a new tab) (a plan or a schedule, not an act yet)

July 2026 2 acts on the line; 1 reported; 2 lines of background, plans and statements

  1. Groundbreaking Google West Memphis Data Center, West Memphis, Arkansas

    Steel River Energy Center held ceremonial groundbreaking July 14, 2026

    commercialappeal.com (opens in a new tab), local outlet (the day its own sentence names)

  2. Groundbreaking Google West Memphis Data Center, West Memphis, Arkansas

    Groundbreaking for the solar farm took place July 11.

    myarklamiss.com (opens in a new tab), news outlet (the day its own sentence names; filed under Sep 17, 2026)

Reported in July 2026, dated only by the article that carried it: 1 act
  1. Google West Memphis Data Center, West Memphis, Arkansas

    Google agreed to purchase initial electricity output from Steel River Energy Center solar project near Wilson in Mississippi County

    arkansasonline.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for July 2026, not acts of their own: 2 lines of background, plans and statements
  1. Google West Memphis Data Center, West Memphis, Arkansas

    First two phases will add three million solar panels, estimated for completion by early to mid 2028

    commercialappeal.com (opens in a new tab) (a plan or a schedule, not an act yet)

  2. Arkansas

    A public records case seeking data center contracts near West Memphis belongs before the Public Service Commission

    arkansasonline.com (opens in a new tab) (no act in the sentence)

June 2026 2 acts on the line; 2 reported; 3 lines of background, plans and statements

  1. Ordinance Fayetteville, Arkansas

    Existing regulations were approved June 16

    yahoo.com (opens in a new tab), national outlet

  2. Rate rule Arkansas

    Entergy added a new rider, the Generating Arkansas Jobs Act (GAJA), in June allowing the utility to pass immediate construction costs of new power plants to ratepayers

    katv.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 16, 2026)

Reported in June 2026, dated only by the article that carried them: 2 acts
  1. Approval Arkansas

    West Memphis City Council approved maximum of $60 billion in industrial development bonds over 30 years

    arkansasonline.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Ordinance Arkansas

    Arkansas's largest city approved a new data center ordinance

    arkansasadvocate.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for June 2026, not acts of their own: 3 lines of background, plans and statements
  1. Google West Memphis Data Center, West Memphis, Arkansas

    Data center property is located south of West Memphis city limits

    youtube.com (opens in a new tab) (a description, not an act)

  2. Google West Memphis Data Center, West Memphis, Arkansas

    Initial build out takes 18 to 24 months to complete

    arkansasonline.com (opens in a new tab) (no act in the sentence)

  3. Google West Memphis Data Center, West Memphis, Arkansas

    Site is 1,100 acres in West Memphis industrial park

    arkansasonline.com (opens in a new tab) (a description, not an act)

May 2026 No acts on the line; 3 lines of background, plans and statements

Also on the record for May 2026, not acts of their own: 3 lines of background, plans and statements
  1. Google West Memphis Data Center, West Memphis, Arkansas

    Google is developing a $4 billion data center campus in West Memphis

    arkansasonline.com (opens in a new tab) (a description, not an act)

  2. Google West Memphis Data Center, West Memphis, Arkansas

    Google and Entergy keeping energy rate contract secret

    arkansasonline.com (opens in a new tab) (no act in the sentence)

  3. Google West Memphis Data Center, West Memphis, Arkansas

    Google data center campus in West Memphis with projected cost of $4 billion

    arkansasonline.com (opens in a new tab) (a statement; who said what is on the statements pages)

April 2026 1 act on the line from 3 reports; 2 reported; 4 lines of background, plans and statements

  1. Google West Memphis Data Center, West Memphis, Arkansas

    Google announced the first recipients of the West Memphis Energy Impact Fund on April 28, 2026

    commercialappeal.com (opens in a new tab), local outlet (the day its own sentence names)

    2 more reports of this
    1. Reported April 28 Google announced grants for West Memphis area wreg.com (opens in a new tab)
    2. Reported April 28 Google announced first two recipients of West Memphis Energy Impact Fund talkbusiness.net (opens in a new tab)
Reported in April 2026, dated only by the article that carried them: 2 acts
  1. Arkansas

    $300 million allocated from state budget for economic incentives and infrastructure for advanced manufacturing super project in West Memphis

    arkansasonline.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Google West Memphis Data Center, West Memphis, Arkansas

    Google started construction of $4 billion data center campus in West Memphis

    arkansasonline.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for April 2026, not acts of their own: 4 lines of background, plans and statements
  1. Google West Memphis Data Center, West Memphis, Arkansas

    Project originally called Project Pyramid, filed permit application December 2024 for five building campus on 1,178 acres along Bollinger Road

    commercialappeal.com (opens in a new tab) (a statement; who said what is on the statements pages)

  2. Google West Memphis Data Center, West Memphis, Arkansas

    Data center located approximately 3 miles south of Interstate 55

    commercialappeal.com (opens in a new tab) (no act in the sentence)

  3. Google West Memphis Data Center, West Memphis, Arkansas

    West Memphis Utilities to provide water and wastewater, Entergy Arkansas to provide power

    arkansasonline.com (opens in a new tab) (a description, not an act)

  4. Arkansas

    Arkansas lawmakers propose sending $300 million to economic incentive fund for West Memphis super project

    arkansasadvocate.com (opens in a new tab) (no act in the sentence)

February 2026 No acts on the line; 4 lines of background, plans and statements

Also on the record for February 2026, not acts of their own: 4 lines of background, plans and statements
  1. Google West Memphis Data Center, West Memphis, Arkansas

    Google is hiring for West Memphis data center positions

    wreg.com (opens in a new tab) (a description, not an act)

  2. Google West Memphis Data Center, West Memphis, Arkansas

    Project expected to take 18 to 24 months to complete

    actionnews5.com (opens in a new tab) (a plan or a schedule, not an act yet)

  3. Google West Memphis Data Center, West Memphis, Arkansas

    Project is Google's first data center in Arkansas

    actionnews5.com (opens in a new tab) (a description, not an act)

  4. Google West Memphis Data Center, West Memphis, Arkansas

    Facility is on 1,100 acre property at 1500 South Loop Drive near Mississippi River

    actionnews5.com (opens in a new tab) (a description, not an act)

2025 10 acts on the line from 13 reports; 12 lines of background, plans and statements

December 2025 1 act on the line

  1. Approval Arkansas

    Arkansas Public Service Commission approved in December 2025 special rate contract between Entergy Arkansas and Google

    arkansasonline.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 1, 2026)

October 2025 4 acts on the line from 7 reports; 11 lines of background, plans and statements

  1. Groundbreaking Google West Memphis Data Center, West Memphis, Arkansas

    Google broke ground on West Memphis data center project on October 2, 2025

    bizjournals.com (opens in a new tab), local outlet (the day its own sentence names)

    3 more reports of this
    1. Oct 2 Google broke ground on $4 billion West Memphis data center on October 2, 2025 wreg.com (opens in a new tab)
    2. Oct 2 Google broke ground on a $4 billion data center in West Memphis on October 2, 2025 businessfacilities.com (opens in a new tab)
    3. Oct 2 Google broke ground on a data center in West Memphis youtube.com (opens in a new tab)
  2. Google West Memphis Data Center, West Memphis, Arkansas

    Google began construction in October 2025 on West Memphis data center

    actionnews5.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Feb 26, 2026)

  3. Google West Memphis Data Center, West Memphis, Arkansas

    Google data center project at 1500 South Loop Dr. in West Memphis announced October 2025

    commercialappeal.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Apr 28, 2026)

  4. Groundbreaking Google West Memphis Data Center, West Memphis, Arkansas

    Construction began in October 2025 on first of possible five buildings

    arkansasonline.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Jun 4, 2026)

Also on the record for October 2025, not acts of their own: 11 lines of background, plans and statements
  1. Arkansas

    Arkansas IMPACT legislation reduced the permitting process on energy projects from 18 months down to 6 months

    youtube.com (opens in a new tab) (no act in the sentence)

  2. Google West Memphis Data Center, West Memphis, Arkansas

    First data center building expected to be completed within 18 to 24 months

    commercialappeal.com (opens in a new tab) (a plan or a schedule, not an act yet)

  3. Google West Memphis Data Center, West Memphis, Arkansas

    Data center campus on 1,100 acres in West Memphis

    commercialappeal.com (opens in a new tab) (no act in the sentence)

  4. Google West Memphis Data Center, West Memphis, Arkansas

    Google to build a data center in Arkansas

    wsj.com (opens in a new tab) (no act in the sentence)

  5. Google West Memphis Data Center, West Memphis, Arkansas

    Google announcing $4 billion investment in Arkansas through 2027 including first data center in West Memphis

    blog.google (opens in a new tab) (no act in the sentence)

  6. Google West Memphis Data Center, West Memphis, Arkansas

    Google plans to partner with the state to offer AI training and credentials to over 10,000 Arkansans

    katv.com (opens in a new tab) (a plan or a schedule, not an act yet)

  7. Google West Memphis Data Center, West Memphis, Arkansas

    Construction of the data center is expected to take up to two years

    katv.com (opens in a new tab) (a plan or a schedule, not an act yet)

  8. Google West Memphis Data Center, West Memphis, Arkansas

    The data center is expected to span 1,000 acres in West Memphis

    katv.com (opens in a new tab) (a plan or a schedule, not an act yet)

  9. Google West Memphis Data Center, West Memphis, Arkansas

    The project is expected to take 18 to 24 months to complete

    youtube.com (opens in a new tab) (a plan or a schedule, not an act yet)

  10. Google West Memphis Data Center, West Memphis, Arkansas

    Google's project includes adding solar power and battery storage

    youtube.com (opens in a new tab) (a description, not an act)

  11. Google West Memphis Data Center, West Memphis, Arkansas

    Google's project includes building a greywater plant to reuse water to cool equipment

    youtube.com (opens in a new tab) (a description, not an act)

September 2025 1 act on the line; 1 line of background, plans and statements

  1. Filing Arkansas

    Entergy Arkansas filed long term special rate contract with Google via Arkansas Public Service Commission in September 2025

    commercialappeal.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Apr 28, 2026)

Also on the record for September 2025, not acts of their own: 1 line of background, plans and statements
  1. Google West Memphis Data Center, West Memphis, Arkansas

    Google is the developer of the West Memphis data center project in Arkansas

    datacenterdynamics.com (opens in a new tab) (a description, not an act)

May 2025 2 acts on the line

  1. Approval Arkansas

    West Memphis City Council approved 30 year payment in lieu of taxes for the project in May

    commercialappeal.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Oct 2, 2025)

  2. Google West Memphis Data Center, West Memphis, Arkansas

    Groot LLC awarded 30 year payment in lieu of taxes by West Memphis City Council in May 2025 covering up to $10 billion in construction costs

    commercialappeal.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Apr 28, 2026)

2025, no month given 2 acts

  1. Google West Memphis Data Center, West Memphis, Arkansas

    The fund was announced last year to help scale energy saving and affordability initiatives for residents in Crittenden County and surrounding areas

    actionnews5.com (opens in a new tab), local outlet (the year its own sentence names; filed under Apr 28, 2026)

  2. Google West Memphis Data Center, West Memphis, Arkansas

    Google announced a $4 billion investment in West Memphis data center in fall 2025

    arkansasonline.com (opens in a new tab), local outlet (the year its own sentence names; filed under Jun 4, 2026)

2024 2 acts on the line

June 2024 1 act on the line

  1. Google West Memphis Data Center, West Memphis, Arkansas

    West Memphis signed a nondisclosure agreement for a data center project on June 3, 2024

    arkansasonline.com (opens in a new tab), local outlet (the day its own sentence names; filed under May 12, 2026)

2024, no month given 1 act

  1. Arkansas

    Work on the Generating Arkansas Jobs Act and related legislation began in 2024

    arkansasonline.com (opens in a new tab), local outlet (the year its own sentence names; filed under Sep 20, 2026)