● Proposed Campus Reported July 29, 2025

Stafford County data center complex

Location Stafford County, Virginia county centroid County level, the county seat

Overview, regulatory gates and specifications

Stafford County Planning Commission backed a new 590,000 square foot data center complex. [4] Potomac Creek Campus proposed 975,000 square feet of data center space on 99 acres south of Eskimo Hill Road [5]

1. Land & Parcel
Location tracked
2. Local Zoning
In local review
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Not yet on file
5. Air & Water Permits
Not yet on file
What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings
Not disclosed
Acreage not stated in public filings yet

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Parcel boundaries and municipal zoning tracked.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
Not disclosed
Backup generators
Not disclosed
Capital investment
Not disclosed
Not disclosed
Who leads it, Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Willie Shelton Jr.

Hartwood District Planning Commissioner

DID Recorded statement at www.fredericksburgfreepress.com (May 29, 2026) [5]
SAID Willie Shelton Jr., planning commissioner, expressed concern about desecration of cemetery and opposition to placing data center on graveyard (May 29, 2026) [5]

Nancy Kotting

cultural resources specialist

DID Recorded statement at www.fredericksburgfreepress.com (May 29, 2026) [5]
SAID Cemetery on Potomac Creek Campus site includes four known Seddon family burials and indications of 12 or more unmarked burials believed to be enslaved individuals (May 29, 2026) [5]

Erin Sanzero

President of Protect Stafford

DID Recorded statement at YouTube (February 26, 2026)
SAID Protect Stafford is a grassroots coalition working to ensure data center development in Stafford County is responsible, community informed, and sustainable. (February 26, 2026) youtube.com (opens in a new tab)

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Not disclosed
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Stafford County data center complex.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Who is behind it A land record, a zoning application or a company's own announcement.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

November 19, 2025 Stafford County, VA Stafford residents oppose massive data centers proposed near Rappahannock River Stafford County Board of Supervisors 3 clips

Following the Stafford County Board of Supervisors approval rezoning 504 acres along Eskimo Hill Road from agricultural to light industrial for the Stafford Technology Campus, residents organized to demand stricter water, noise, and setback rules on pending data center filings.

  1. ABC 7 News - WJLA Broadcast Report Broadcast Report transcribed from local broadcast report
    "who live in this neighborhood are concerned about this data center project because it would be placed right next to their homes on this farm. This is where a developer wants to build a massive data center. Right behind those trees is the Rappahannock River, and that is why these homeowners chose to live here to have a nice river view. I hate it. I want to cry."
  2. ABC 7 News - WJLA Broadcast Report Broadcast Report transcribed from local broadcast report
    "Arlene's, and he's concerned about the data center noise. I've had a choice to you know, the entire country to live. I chose here. And this is a idyllic area with a lot of nature. We've got a river here. We've got eagles. We've got wildlife. That'll all disappear. Altogether, the developer's proposing four data center locations including one that can be seen across the river in"
  3. Resident public comment Resident Public Comment transcribed from local broadcast report
    "They need to know that there is one very large data center being put literally right across the river from a very large subdivision. And they're very likely going to see the light effect of that at night. The developer's attorney told me at full build out, King's Corridor is projected to generate $245 million annually for the county, which is just over 20% of the county's total budget. The"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. Filing (content date)

    Stafford County Planning Commission backed a new 590,000 square foot data center complex.

    [4] wjla.com

  2. (source date; the content gives no date of its own)

    Potomac Creek Campus proposed 975,000 square feet of data center space on 99 acres south of Eskimo Hill Road

    [5] fredericksburgfreepress.com

  3. · Status: permitting (source date; the content gives no date of its own)

    Stack topped out its first building at a 1 gigawatt data center campus in Stafford County, Virginia.

    [2] datacenterdynamics.com

  4. · Status: proposed (source date; the content gives no date of its own)

    A data center was proposed for 850 acres of land in Stafford County, Virginia.

    [3] datacenterdynamics.com

Every event in order

10 corrections to this record

Every correction, with its reason
  1. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  2. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  3. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  4. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  5. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier: fredericksburgfreepress.com is a news outlet (tiered by kind, the record's rules of September 23, 2026). The link did not change.

  6. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier: the tier the record already gives datacenterdynamics.com. The link did not change.

  7. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier: the tier the record already gives datacenterdynamics.com. The link did not change.

  8. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier: wjla.com is a news outlet (tiered by kind, the record's rules of September 23, 2026). The link did not change.

  9. · Project summary

    Hyphenated compound split to meet the writing rule; the words are unchanged.

Every correction on the record is on the corrections page.

Nearest data centers in Virginia

Verified data center records in Virginia within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Amazon Data Services Inc IAD-350 Stafford, Stafford County Less than 1 mi Proposed Amazon Web Services
Amazon Data Services Inc. IAD450 Cosner Tech Campus Fredericksburg, Spotsylvania County ~8 mi Proposed Amazon Web Services
Amazon Data Services IAD-870 Fredericksburg, Spotsylvania County ~8 mi Proposed Amazon Web Services
Vantage Fredericksburg Fredericksburg, Fredericksburg city ~9 mi Running Vantage Data Centers 1 building
CloudHQ Manassas Campus (MCC1) Prince William County ~21 mi Running CloudHQ 1 building
Digital Realty - Porpoise Ventures LLC (VA4) Bristow, Prince William County ~22 mi Proposed Digital Realty

Blank cell: not disclosed by any source on file.

Common questions about Stafford County data center complex

Answered directly from the verified filings and local actions on this page.

Who is building Stafford County data center complex?

Not disclosed. No source on file names the developer. The sources read for this record are listed under Sources.

How much power and water does Stafford County data center complex say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Stafford County data center complex stand today?

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Peterson Co. files for 16-building data center campus in Stafford County, Virginia (opens in a new tab), Data Center Dynamics, October 21, 2025, trade press
  2. Stack tops out first building at 1GW data center campus in Stafford County, Virginia (opens in a new tab), Data Center Dynamics, May 26, 2026, trade press
  3. Data center proposed for 850 acres of land in Stafford County, Virginia (opens in a new tab), Data Center Dynamics, July 29, 2025, trade press
  4. Stafford County Planning Commission backs new 590K-square-foot data center complex - WJLA (opens in a new tab), WJLA, August 27, 2026, local outlet
  5. Stafford County Planning Commission recommends denial of data center after cemetery concerns (opens in a new tab), www.fredericksburgfreepress.com, May 29, 2026, local outlet

5 sources on file.

Regional grid context

This site is in the SERC Virginia and Carolina North (SRVC-N) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Stafford County data center complex", https://datacenterrecord.org/projects/stafford-county-data-center-complex-va, last verified October 24, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Stafford County data center complex", https://datacenterrecord.org/projects/stafford-county-data-center-complex-va. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
reviewed in depth
Tags
Reviewed in depth
Coordinates
38.4153, -77.4156
How the location is known
Location is the county seat; exact site not disclosed.
Location source
County seat (Stafford), Wikidata, placed at county level
Coordinate source
wikidata county seat
Location last verified
September 16, 2026
Published
September 4, 2026
Last verified
October 24, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Stafford County data center complex · 5 sources, 4 entries · basis and source tier on every row · verified October 24, 2026

Download CSV JSON