Data Center Record.
Census GEOID: 08005 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 3 primary sources

● Running First recorded September 14, 2026 · 3 Buildings

QTS Aurora Denver Data Center Campus (DEN1)

Street address 23855 East E-470, Aurora, CO 80018, Arapahoe County verified address Exact, at the address [2] QTS Data Centers: All locations

Overview, regulatory gates and specifications

QTS Data Centers operates its 170 MW, three building Denver Aurora hyperscale data center campus at 23855 East E 470 in Aurora, Arapahoe County, Colorado. [1] QTS Data Centers lists QTS Denver at Aurora, Colorado on its own page of data center locations, read September 14, 2026. [2]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
EPA air permit on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [2]
170 MW
the developer's figure

Equivalent to ~141,100 U.S. homes (U.S. EIA 830 homes/MW baseline) · 8.2% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [2]
3 buildings
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 23855 East E-470, Aurora, CO 80018.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
170 MW developer figure Equivalent to the continuous electricity demand of about 141,100 average U.S. homes based on U.S. Energy Information Administration residential consumption data. About 2 percent of New York City's summer peak demand in 2024.
[2] q.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
3 buildings operator page
[2] q.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2020 (6 years)
Who leads it
QTS Data Centers as stated by the source
Official project website
q.com (opens in a new tab) verified October 28, 2026
q.com (opens in a new tab)
Archived promotional websites
q.com (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. QTS Aurora Denver Data Center Campus (DEN1), capacity: 170 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 170 ÷ 10,245 = 0.02 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: QTS Data Centers
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for QTS Aurora Denver Data Center Campus (DEN1).

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 170 MW 170 MW the developer's figure [2] q.com
Site Footprint (Acres)
Data Hall Buildings 3 buildings 3 operator page [2] q.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

October 26, 2026 Aurora, CO Aurora City Council Vote on 180 Day Data Center Moratorium and Zoning Rules Aurora City Council 3 clips

CBS Colorado report on Aurora City Council and community proceedings in Aurora, CO: Aurora City Council Vote on 180 Day Data Center Moratorium and Zoning Rules (October 26, 2026).

  1. Aurora City Council and CBS Colorado Broadcast Report (CBS Colorado Report) Broadcast Report transcribed from local broadcast report
    "And, ashley, the city now has a letter from a data center developer to consider as well. Yeah. Michelle and brian, good morning. And data centers will once again be the topic of conversation during city council's meeting later tonight. Now, the city of Aurora is actually home to nine data centers and the largest data center here in the state of colorado. Five of those data"
  2. Mike Coffman, Mayor of Aurora, and Council Deliberation Elected Official transcribed from local broadcast report
    "Valley ranch. That one has already been approved, but now the developer says it will explore a new site for the 860,000 square foot facility, but only if the city pauses. New data center rules for 90 days. Now, city council did vote against a six month moratorium earlier earlier this year, with mayor mike coffman casting the tie breaking vote against the ordinance. But now,"
  3. CBS Colorado Broadcast Report Broadcast Report transcribed from local broadcast report
    "Developer's letter to city council. Now, a moratorium would need seven votes to pass. If it does pass, it would not go into effect until sometime next year. If passed tonight, it would also not stop the trident data center for moving forward, because that data center has already been approved. Now, that meeting is scheduled to start later tonight at 6:00, reporting live in Aurora this morning. I'm your"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    QTS Data Centers lists QTS Denver at Aurora, Colorado on its own page of data center locations, read September 14, 2026.

    [2] q.com

Nearest data centers in Colorado

Verified data center records in Colorado within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
11:11 Systems and Sungard AS Aurora Data Center (CO1) Aurora, Adams County 4 mi Running 11:11 Systems 8 MW
Vantage Data Centers Aurora Campus (Project Trident) Aurora, Adams County ~6 mi Proposed Vantage Data Centers
Flexential Aurora Data Center (DEN03) Aurora, Arapahoe County 8 mi Running Flexential 10 MW
Flexential Centennial Data Center (DEN05) Centennial, Arapahoe County 10 mi Running Flexential 15 MW
DataBank Centennial Campus (DEN2 and DEN5) Centennial, Arapahoe County 11 mi Running DataBank 20 MW
H5 Data Centers Denver Tech Center Campus Denver, Denver County 11 mi Running H5 Data Centers 20 MW

Blank cell: not disclosed by any source on file.

Common questions about QTS Aurora Denver Data Center Campus (DEN1)

Answered directly from the verified filings and local actions on this page.

Who is building QTS Aurora Denver Data Center Campus (DEN1)?

QTS Data Centers is the developer. No construction contractor is named on the record yet.

How much power and water does QTS Aurora Denver Data Center Campus (DEN1) say it needs?

Power: 170 MW (the developer's figure, q.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does QTS Aurora Denver Data Center Campus (DEN1) stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. EPA Facility Registry Service (FRS) Detailed Facility Report: QTS Aurora LLC DEN1 (110071767620) (opens in a new tab), US Environmental Protection Agency ECHO, October 28, 2026
  2. QTS Data Centers: All locations (opens in a new tab), QTS Data Centers, September 14, 2026
  3. Aurora City Council votes down data center moratorium for second time amid Project Trident pushback (opens in a new tab), CBS Colorado, October 28, 2026

3 sources on file.

Regional grid context

This site is in the WECC Rockies (RMPA) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "QTS Aurora Denver Data Center Campus (DEN1)", https://datacenterrecord.org/projects/qts-denver-aurora-co, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "QTS Aurora Denver Data Center Campus (DEN1)", https://datacenterrecord.org/projects/qts-denver-aurora-co. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
39.7100429, -104.7205688
How the location is known
Location from the site's street address.
Location source
https://q.com/data-centers/
Coordinate source
CDPHE APCD / QTS Data Centers
Location last verified
September 14, 2026
How capacity was disclosed
the developer's figure
Capacity, if disclosed
170 MW, the developer's figure
Published
September 14, 2026
Last verified
October 27, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · QTS Aurora Denver Data Center Campus (DEN1) · 3 sources, 1 entry · basis and source tier on every row · verified October 27, 2026

Download CSV JSON