Meta Fort Worth Data Center

Street address 4500 Live Oak Blvd, AllianceTexas Corridor, Fort Worth, TX 76177, Tarrant County verified address Exact, at the address [3] U.S. Census Bureau TIGERweb city centroid, public domain

Overview, regulatory gates and specifications

Meta lists a data center at Fort Worth, Texas among the sites it operates. [1] Filings on the record specify a 260 acre site footprint, 5 planned or operational buildings. [1] Meta lists Meta Fort Worth Data Center at Fort Worth, Texas on its own page of data center locations, read September 14, 2026. [1]

1. Land & Parcel
260 acres on file
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
EPA ECHO Facility Registry R
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
260 acres
measured

5 planned or operational data hall buildings.

Location: 4500 Live Oak Blvd, AllianceTexas Corridor, Fort Worth, TX 76177.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
260 acres assessor parcel
tad.org (opens in a new tab)
Buildings
5 buildings assessor parcel
[1] datacenters.atmeta.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2017 (9 years)
Who leads it
Meta attributed via corporate HQ or property filing
[1] datacenters.atmeta.com
Permitted legal entity
Ernst LLC (Meta Platforms, Inc.) what a permit allows
[3] echo.epa.gov
State air permit registration
FRS 110071163236, TX0000004843901764, FRS 110070191444, TXR15905N state air permit register
State permit status
EPA ECHO Facility Registry Record FRS 110071163236 (Clean Air Act Permit ID TX0000004843901764) and FRS 110070191444 (TCEQ Stormwater Permit TXR15905N) at 4500 Live Oak Blvd, Fort Worth, TX 76177 and Texas Comptroller Qualified Data Center Registration (Ernst LLC) the state's permit register, last verified November 9, 2026
[3] echo.epa.gov
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Meta · Applicant / Shell LLC: Ernst LLC
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Meta Fort Worth Data Center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres) 260 acres 260 acres measured
Data Hall Buildings 5 buildings 5 5 operational data center buildings at 4500 Live Oak Blvd in the AllianceTexas corridor per Meta Fort Worth campus specification and Tarrant Appraisal District parcel records [1] datacenters.atmeta.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

August 26, 2026 Fort Worth, TX Fort Worth site plan for data center brings more debate among residents Fort Worth City Council 2 clips

CBS TEXAS report on Fort Worth City Council and community proceedings in Fort Worth, TX: Fort Worth site plan for data center brings more debate among residents (August 26, 2026).

  1. CBS TEXAS Broadcast Report Broadcast Report transcribed from local broadcast report
    "They have. Good morning carmen. Now we're talking about the black mountain data center. And this was actually approved by the city council last year before the city took steps towards a moratorium, a kaa pause at last night's city council meeting. They did vote to approve an amendment that would add more distance between the data center and homes. Take a listen to some of those comments at last night's meeting. Brings far more negatives"
  2. CBS TEXAS Broadcast Report Broadcast Report transcribed from local broadcast report
    "Think about our needs as residents of Fort Worth. I'm not for or against data centers. I'm worried about the zoning, what they want in the zoning is more than what they ask for. Data centers are here to stay. We can get on the winning team. We can stay behind. We can gripe, we complain. Our next. A lot of thoughts and a lot of emotions at yesterday's meeting. Ultimately, the city council voted to approve those"
August 11, 2026 Fort Worth, TX Fort Worth City Council Unanimous Vote Initiating 90 Day Data Center Moratorium Fort Worth City Council 3 clips

After three hours of public testimony from more than 100 speakers on August 11, 2026, the Fort Worth City Council voted unanimously on a motion by Council Member Elizabeth Beck to initiate a 90 day moratorium on data center rezoning and permits.

  1. CBS TEXAS Broadcast Report Broadcast Report transcribed from local broadcast report
    "Continues of trevor, north texas, residents just pushing back on these projects. Yeah, madison, we have seen people pack into city council meetings just like the one last night in order to argue against data center development right in their backyard. This time, it took about three hours to get through all the public comment before the city council unanimously voted to enact this moratorium process. I've got a motion by council member back in a second by dr."
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "Fort Worth currently has four data center developments with ten buildings across the city. The moratorium will last 90 days and pause all rezoning and permit applications. During that time, city staff would study noise issues, water supply concerns and possible code changes for future development. City council is also voting to create a commission to study the impacts of data centers. It would look at economic benefits weighed against incentives for developers, a final report and recommendation would go in front"
  3. CBS TEXAS Broadcast Report Broadcast Report transcribed from local broadcast report
    "Match the public comment. Worries over water use, noise and environmental impacts. The people here in Fort Worth are the only ones who can tell you what they're willing to put up with, what they're afraid of and what they want to see happen. We can be known for the leader of data center regulation while keeping our citizens safe. Our mental health positive in keeping our physical health from"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Meta lists Meta Fort Worth Data Center at Fort Worth, Texas on its own page of data center locations, read September 14, 2026.

    [1] datacenters.atmeta.com

Nearest data centers in Texas

Verified data center records in Texas within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
QTS Fort Worth Fort Worth, Tarrant County 2 mi Running QTS Data Centers 2 buildings
TierPoint Fort Worth Data Center Fort Worth, Tarrant County 3 mi Running TierPoint 1 building
Rackspace Dallas Grapevine (DFW1) Grapevine, Tarrant County 12 mi Running Rackspace 1 building
CyrusOne Lewisville DFW2 Lewisville, Denton County 18 mi Running CyrusOne 1 building
Centersquare Fort Worth data center Fort Worth, Tarrant County 18 mi Running Centersquare 1 building
Digital Realty DFW26 Lewisville, Denton County 19 mi Running Digital Realty 1 building

Blank cell: not disclosed by any source on file.

Common questions about Meta Fort Worth Data Center

Answered directly from the verified filings and local actions on this page.

Who is building Meta Fort Worth Data Center?

Meta is the developer, datacenters.atmeta.com (opens in a new tab). No construction contractor is named on the record yet.

How much power and water does Meta Fort Worth Data Center say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Meta Fort Worth Data Center stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Meta: Our U.S. data center fleet (opens in a new tab), Meta, September 14, 2026
  2. Meta 2025 Environmental Data Index (Page 9: Water Withdrawal by Facility) (opens in a new tab), Meta
  3. US EPA ECHO Detailed Facility Report 110071163236 (Alliance Site CAA ID TX0000004843901764 and FTW Data Center NPDES TXR15905N) (opens in a new tab), U.S. Environmental Protection Agency, November 9, 2026

3 sources on file.

Regional grid context

This site is in the ERCOT All (ERCT) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Meta Fort Worth Data Center", https://datacenterrecord.org/projects/meta-fort-worth-data-center-tx, last verified November 9, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Meta Fort Worth Data Center", https://datacenterrecord.org/projects/meta-fort-worth-data-center-tx. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
reviewed in depth
Tags
Reviewed in depth
Coordinates
32.9845, -97.2965
How the location is known
Location from the site's street address.
Location source
U.S. Census Bureau TIGERweb city centroid, public domain
Coordinate source
US EPA ECHO FRS and municipal parcel records
Location last verified
November 6, 2026
How acreage was disclosed
measured
Published
September 14, 2026
Last verified
November 9, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Meta Fort Worth Data Center · 3 sources, 1 entry · basis and source tier on every row · verified November 9, 2026