Sources on this page
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Last verified: · 3 primary and local sources
Vantage Data Centers GA2, LLC received Georgia EPD Synthetic Minor Air Quality Permit No. 7374-121-0982 (S 01 to 0) on May 6, 2025 following Georgia DCA DRI #4256 review for its Westlake campus at 6585 Plummer Road SW in Fulton County. [3] Filings on the record specify 1 planned or operational building. [3] On the regulatory record, state permit status is Georgia EPD Air Quality Permit No. 7374-121-0982 (S 01-0) issued. [3]
U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.
Utility interconnection queue filings monitored.
Equivalent to ~15 U.S. households (U.S. EPA 300 gal/day household baseline).
Stated annual local tax revenue: $7,397,400.
Assessor parcel acreage and building square footage are added when municipal or county filings are published.
Location: 6585 Plummer Rd SW, South Fulton, GA 30331.
Permanent operational headcount not yet disclosed on the record.
Stated annual local tax revenue: $7,397,400.
Sources:
The two count different water: the data center figure is water withdrawn from its source, and the EPA's is water used at home, which the EPA does not split into water consumed and water returned.
A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).
Connected government officials, corporate entities, utilities and local rules on the public record.
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Vantage Data Centers Atlanta GA2 Campus (Westlake).
| Field / Parameter | Permitted / Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | |||
| Site Footprint (Acres) | |||
| Data Hall Buildings | 1 building | GA EPD Air Quality Permit and DRI filing | |
| Cooling & Water System | 4,380 gal/day | the developer's figure | |
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue | $7,397,400/yr | the developer's figure |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Acts of Fulton County and South Fulton about data centers, on the record with their source. A rule about the area is not a decision about this record.
| Date | Who | Decision | Source |
|---|---|---|---|
| Atlanta | Atlanta City Council introduced new legislation aimed at regulating local data centers and eliminating their tax breaks | theatlantavoice.com (opens in a new tab) | |
| Atlanta | Atlanta City Council members introduced zoning ordinances restricting data centers near transit stations and the BeltLine corridor and barring local tax incentives. | fox5atlanta.com (opens in a new tab) | |
| Atlanta | The City of Atlanta established a Data Center Task Force to evaluate municipal zoning, grid load and neighborhood rules for urban data centers. | usatoday.com (opens in a new tab) | |
| Atlanta | Communities placing moratoriums on data center development citing concerns about power and water usage, traffic, environmental impacts and noise | wsbradio.com (opens in a new tab) |
Chronological regulatory, corporate and permitting events on the record, newest first.
· Status: being built (content date)
Vantage Data Centers GA2, LLC received Georgia EPD Synthetic Minor Air Quality Permit No. 7374-121-0982 (S 01 to 0) on May 6, 2025 following Georgia DCA DRI #4256 review for its Westlake campus at 6585 Plummer Road SW in Fulton County.
Verified data center records in Georgia within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| Aligned ATL-01 Lithia Springs, Douglas County | 2 mi | Running | Aligned Data Centers | 180 MW |
| Microsoft Douglasville Data Center Campus (FTY01 / FTY02) Douglasville, Douglas County | 2 mi | Running | Microsoft | 3 buildings |
| Flexential Atlanta Douglasville (ATL5) Douglasville, Douglas County | 3 mi | Running | Flexential | 22.5 MW |
| DC BLOX Atlanta West Campus (Douglasville) Douglasville, Douglas County | 3 mi | Being built | DC BLOX | 2 buildings |
| Google Douglas County Data Center Lithia Springs, Douglas County | 3 mi | Running | 3 buildings | |
| Rock House Road Data Center Campus (DRI #4078) Lithia Springs, Douglas County | 3 mi | Proposed | Taylor & Mathis | 4 buildings |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
Vantage Data Centers is the developer, air.gaepd.org (opens in a new tab). No construction contractor is named on the record yet.
Power: not disclosed by any source on file. Water: 4,380 gallons a day (withdrawal) (the developer's figure, apps.dca.ga.gov (opens in a new tab)).
Atlanta (rated case by case): Atlanta City Council introduced new legislation aimed at regulating local data centers and eliminating their tax breaks (reported August 26, 2026, theatlantavoice.com (opens in a new tab)); and Atlanta: Atlanta City Council members introduced zoning ordinances restricting data centers near transit stations and the BeltLine corridor and barring local tax incentives (August 20, 2026, fox5atlanta.com (opens in a new tab)). 4 events are on the county's rows; a rule about the area is not a decision about this record.
3 sources on file.
This site is in the SERC South (SRSO) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Vantage Data Centers Atlanta GA2 Campus (Westlake). Last verified May 6, 2025. https://datacenterrecord.org/projects/georgia-dri-4256-vantage-data-center-westlake-ga. Accessed November 17, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page. Report a correction · Send a tip about Vantage Data Centers Atlanta GA2 Campus (Westlake)
Data Center Record, "Vantage Data Centers Atlanta GA2 Campus (Westlake)", https://datacenterrecord.org/projects/georgia-dri-4256-vantage-data-center-westlake-ga. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.