Data Center Record.

Running Built from one source

Atlantech Online Silver Spring Data Center

Silver Spring, Montgomery County, MDDeveloper: Atlantech OnlineCensus GEOID 24031

Stage
Running
Power
3 MW
the developer's figure
Buildings
1 building
operator page, verified October 27, 2026
Undisclosed in public filings
Land, Water

Atlantech Online operates a network colocation facility at 1010 Wayne Avenue in downtown Silver Spring, Montgomery County, Maryland, with 3 MW of power capacity. It is running; the record holds no sourced date for when it reached that stage.

How much water it would use and who would use it have not been disclosed.

Last verified · 1 source, 0 primary · Built from one source, not yet reviewed in depth by a person. · How to read this page

  • This record: Running, ringed
  • data center
  • Smaller pins: 18 other published records in Maryland
Details
  • this record's location, ringed
  • parcel outline, from the county parcel record
  • city limits, U.S. Census Bureau, on a town level record
  • county boundary

The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.

How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.

What is known

Each figure as its source gave it. The number in brackets is its place in the source list.

Buildings
1 building operator page, verified October 27, 2026
[1] atlantech.net
Power it would draw
3 MW the developer's figure About 0 percent of New York City's summer peak demand in 2024.
[1] atlantech.net
Who leads it
Atlantech Online as stated by the source
Undisclosed in public filings
Land, Water, Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Atlantech Online Silver Spring Data Center, capacity: 3 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 3 ÷ 10,245 = 0 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Every field, with who said it and when (Researcher view)

Impact figures

FieldValueWho says soSourceLast verified
How much power it needs 3 MW the developer's figure [1] atlantech.net (opens in a new tab) October 27, 2026
How much water it would use
How loud it would be
Jobs once it runs
Tax it would pay each year

The record's fields

FieldValueWho says soSourceLast verified
Who is building it Atlantech Online as stated by the source October 27, 2026
Who is constructing it
How much land
Buildings 1 building operator page, verified October 27, 2026 [1] atlantech.net (opens in a new tab) October 27, 2026
Where its power comes from
Grid connection
How it is cooled

A blank value cell means not disclosed by any source on file; a blank basis cell means the source gave the figure without saying on what basis.

The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Montgomery County and Silver Spring about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Montgomery County closed Montgomery County, Maryland approved 18 month pause on data center reviews in July 2026 commercialobserver.com (opens in a new tab)
Montgomery County closed Judge ruled that Preserve Montgomery County can continue to pursue claims that the county did not adequately inform the community about data centers komu.com (opens in a new tab)
Montgomery County closed Montgomery County Council extended its data center pause from six months to 18 months marylandmatters.org (opens in a new tab)
Montgomery County closed The vote passed unanimously nbcwashington.com (opens in a new tab)
Montgomery County closed Montgomery County Council voted unanimously on July 28, 2026 for an 18 month moratorium on new data centers of 25 megawatts or more, the threshold as reported by Bisnow nbcwashington.com (opens in a new tab)

What happened

No dated entry is on the record yet.

  • Read on October 27, 2026 (the day the page was read; it gives no date of its own)

    Verified facility status from Maryland state agency permits, utility dockets, municipal planning filings, or operator campus specifications.

    [1] atlantech.net

The site

The pin is the site's address.

The site map is at the top of the page.

Where
1010 Wayne Avenue, Silver Spring, MD 20910, Silver Spring, Montgomery County, Maryland [1] atlantech.net (opens in a new tab)
How exactly it is located
Exact, at the address
The parcel
No parcel outline in the public record
Nearest homes
Not computed for a record placed at a place center

USGS NAIP aerial view of Atlantech Online Silver Spring Data Center
LAT 38.99450 / LON -77.02680 Imagery: U.S. Geological Survey / USDA NAIP (Public Domain)

Questions about this project

5 questions answered from the record

Answered from the rows on this page.

How big is Atlantech Online Silver Spring Data Center?

The record has 2 measures of its size: 3 MW (the developer's figure, atlantech.net (opens in a new tab)) and 1 building (operator page, verified October 27, 2026, atlantech.net (opens in a new tab)). Its acreage is not disclosed.

Who is building Atlantech Online Silver Spring Data Center?

Atlantech Online is the developer. No construction contractor is named on the record yet.

How much power and water does Atlantech Online Silver Spring Data Center say it needs?

Power: 3 MW (the developer's figure, atlantech.net (opens in a new tab)). Water: not disclosed by any source on file.

Where does Atlantech Online Silver Spring Data Center stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

What has Silver Spring or Montgomery County decided about it?

Montgomery County (rated closed): Montgomery County, Maryland approved 18 month pause on data center reviews in July 2026 (reported September 23, 2026, commercialobserver.com (opens in a new tab)); and Montgomery County: Judge ruled that Preserve Montgomery County can continue to pursue claims that the county did not adequately inform the community about data centers (reported September 20, 2026, komu.com (opens in a new tab)). 5 events are on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Atlantech Online Silver Spring Data Center Official Disclosure (opens in a new tab), Atlantech Online, query feed

1 source on file.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Atlantech Online Silver Spring Data Center", https://datacenterrecord.org/projects/atlantech-online-inc-atlantech-online-silver-spring-md-silver-spring-md, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Atlantech Online Silver Spring Data Center", https://datacenterrecord.org/projects/atlantech-online-inc-atlantech-online-silver-spring-md-silver-spring-md. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
38.9945, -77.0268
How the location is known
Location from the site's street address.
Location source
https://www.atlantech.net/data-centers/
Coordinate source
Maryland SDAT / Atlantech Online Silver Spring specification
How capacity was disclosed
the developer's figure
Capacity, if disclosed
3 MW, the developer's figure
Rating of the county's rows
Closed
Published
October 21, 2026
Last verified
October 27, 2026
Undisclosed in public filings
Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection

Researcher view · Atlantech Online Silver Spring Data Center · 1 source, 1 entry, 5 decisions nearby · basis and source tier on every row · verified October 27, 2026

Download CSV JSON