Virginia DEQ issued a minor New Source Review air permit (Article 6, 9VAC5-80) to 13832 Redskin Acquisition, LP, registration 74336 (permit action 74336-1), Fairfax County, on May 22, 2026. The permit document authorizes 85 emergency backup generators totaling 250.75 MW of permitted backup generator rating at 2860 Towerview Road (IAD05 Data Center Building E) and 2850 Towerview Road (IAD06 Data Center Building F), Herndon, Virginia 20171. [1]
How much power it needs, how much water it would use and who would use it have not been disclosed.
Connected government officials, corporate entities, utilities and local rules on the public record.
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Starwood Capital Group - Word of Grace Data Center.
| Field / Parameter | Permitted / Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | |||
| Site Footprint (Acres) | |||
| Data Hall Buildings | |||
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | 85 units (250.75 MW) | what a permit allows [1] deq.virginia.gov | |
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Chronological regulatory, corporate and permitting events on the record, newest first.
· Status: permitting (content date)
Virginia DEQ issued a minor New Source Review air permit (Article 6, 9VAC5-80) to 13832 Redskin Acquisition, LP, registration 74336 (permit action 74336-1), Fairfax County, on May 22, 2026. The permit document authorizes 85 emergency backup generators totaling 250.75 MW of permitted backup generator rating at 2860 Towerview Road (IAD05 Data Center Building E) and 2850 Towerview Road (IAD06 Data Center Building F), Herndon, Virginia 20171.
Verified data center records in Virginia within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| Peterson Companies - Herndon Technology Partners LLC Herndon, Fairfax County | Less than 1 mi | Proposed | Peterson Companies | |
| BXP (Boston Properties) - New Dominion Technology Park LLC Herndon, Fairfax County | Less than 1 mi | Proposed | BXP (Boston Properties) | |
| Amazon Data Services Inc - IAD - 500/501 Herndon, Fairfax County | Less than 1 mi | Proposed | Amazon Web Services | |
| Amazon Data Services Inc - IAD-165/166/167/168/613 Herndon, Fairfax County | Less than 1 mi | Proposed | Amazon Web Services | |
| Lumen Technologies - Level 3 Communications Herndon Gateway Herndon, Fairfax County | Less than 1 mi | Proposed | Lumen Technologies | |
| Equinix, LLC, DC 97 Herndon, Fairfax County | Less than 1 mi | Running | Equinix | 1 building |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
Starwood Capital Group is the developer, starwoodcapital.com (opens in a new tab). No construction contractor is named on the record yet.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
No decision by Herndon or Fairfax County about data centers is on the record. The Fairfax County page and the Virginia scorecard list every rated row the day a person publishes one.
2 sources on file.
This site is in the SERC Virginia and Carolina North (SRVC-N) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Starwood Capital Group - Word of Grace Data Center. Last verified May 22, 2026. https://datacenterrecord.org/projects/13832-redskin-acquisition-fairfax-74336-va. Accessed November 17, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page. Report a correction · Send a tip about Starwood Capital Group - Word of Grace Data Center
Data Center Record, "Starwood Capital Group - Word of Grace Data Center", https://datacenterrecord.org/projects/13832-redskin-acquisition-fairfax-74336-va. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.