Millard County Commission Rezoning Vote for 4,000 Acre AI Data Center
Millard County Commissioners voted on August 5, 2025 to approve rezoning 4,000 acres of agricultural land near Delta for a multi billion dollar artificial intelligence data center campus.
Privacy enhanced player · zero third party requests until clicked
Millard County Commission Rezoning Vote for 4,000 Acre AI Data Center
Millard County Commission · August 5, 2025
Timestamped Speaker & Testimony Ledger
3 verified timestamped clips extracted chronologically from the closed caption record. Select any clip to play that exact window in the master player or copy a canonical clip link.
- Clip 1 · 0:16 Millard County Commission Hearing Summary Board & Planning Staff In support auto captions, uncheckedZoning Power & Grid Water
Millard County Commissioners approve rezoning 4,000 acres of agricultural land for a multi billion dollar artificial intelligence data center after public hearing testimony.
"previously designated for agriculture data centers use vast amounts of power and water. Some people say too much. >> ABC for spy on weighing attended a public hearing today. He spoke exclusively with a founding member of the company. There was definitely some different perspectives among the few residents that spoke at the hearing, some of them welcoming the project. Some of them objected to it. >> But I think the biggest takeaway was the tremendous"
- Clip 2 · 0:46 Resident public comment Resident Public Comment auto captions, unchecked
Residents and community speakers address Millard County Commission regarding local water, power grid, noise, and zoning impacts.
"talking about billions in economic impact and hundreds of millions of additional tax revenue for the county. I feel great. It's a it is a good start. We've been down this path. We now for over a year. So for us, this is just a great milestone. The largest data center in the nation is one step closer to being built in Millard County. Just south of Fillmore. This this project is actually on the farm that my"
- Clip 3 · 1:17 Millard County Commission Member Elected Official Questioning auto captions, uncheckedZoning Power & Grid Water
Millard County Commission members deliberate on municipal siting standards, utility capacity, and the recorded ordinance action.
"this place. I grew up here. The data centers, primarily the infrastructure, big take an artificial intelligence companies need to operate smoothly, which includes power, cutting edge, heating and cooling technology. The space for companies to operate efficiently. >> And network connectivity. If all goes as planned. Some of the biggest tech companies might purchase their tickets to Utah. Exactly what this is really a turnkey operation."