Archbald Borough Council Public Hearing on Wildcat Ridge Data Center
Prior to Archbald Borough Council's unanimous 7 to 0 denial, Lackawanna County Commissioner Bill Gaughan testified against hyperscale data center industrialization in the valley while developer attorney Edmund Campbell argued the applicant met conditional use criteria.
Privacy enhanced player · zero third party requests until clicked
Archbald Borough Council Public Hearing on Wildcat Ridge Data Center
Archbald Borough Council · October 21, 2026
Timestamped Speaker & Testimony Ledger
3 verified timestamped clips extracted chronologically from the closed caption record. Select any clip to play that exact window in the master player or copy a canonical clip link.
Lackawanna County Commissioner Bill Gaughan testifies before Archbald Borough Council opposing the Wildcat Ridge hyperscale data center and urging protection of residential neighborhoods.
"[APPLAUSE] One of those critics was Lackawanna County Commissioner Bill Gaughan, who has been a regular at these hearings in Archbald, echoing residents concerns about Wildcat Ridge. >> We cannot decide, and you cannot decide the future of artificial intelligence. But we can decide whether this valley, this community and these families must be sacrificed to power it. >> While most in attendance"
Clip 2 · 1:13Edmund Campbell, Legal Counsel for Wildcat Ridge Data Center ApplicantDeveloper RepresentativeIn supporttranscribed from the official recording
ZoningLitigation
Applicant attorney Edmund Campbell argues in closing remarks that Cornell Utility Management satisfied the borough zoning ordinance criteria for a conditional use permit.
"were against the proposed data center, attorney Edmund Campbell was representing the Wildcat Ridge Data Center and attempted one last push to get the proposal across the finish line. >> I know that what I'm asking you to do is not popular, but quite frankly, criminal. Quite frankly, we've met the standards under the ordinance and we ask you to approve it. >> The anti data center crowd"
Clip 3 · 0:18Archbald Borough Council MemberElected OfficialQuestioningtranscribed from the official recording
ZoningPower & GridWaterLitigation
Archbald Borough Council members deliberate on municipal siting standards, utility capacity, and the recorded ordinance action.
"is. Ryan Hartnett was at tonight's council meeting and has the recap of the council's decision. >> After nearly a year of hearings, the fate of the proposed Wildcat Ridge data Center was in the hands of the Archbald Borough Council. Residents packed into the community center gymnasium in a standing room only crowd. Most of those in attendance were in strong opposition to the proposed data center, with"
Venue:Governor's Responsible Infrastructure Development (GRID) Standards Announcement
"Announced the Governor's Responsible Infrastructure Development (GRID) standards for Pennsylvania data centers, stating that hyperscale developers must bring their own power generation, protect utility ratepayers from transmission costs, conserve water, and commit to community transparency."
Pennsylvania Department of Environmental Protection (PA DEP) Chapter 102/105 Permit Tracker & GRID Voluntary Program Scope
PA DEP Data Center Permit Tracker · GRID Voluntary Program Scope (Grandfathered Active Queue)
Agency or Venue:Pennsylvania Department of Environmental Protection (PA DEP) & Commonwealth of Pennsylvania
"The primary Pennsylvania Department of Environmental Protection (PA DEP) permit tracker and official GRID program terms confirm that GRID participation is voluntary and applies only to developers seeking state incentives or expedited permitting; active hyperscale applications already pending in the PA DEP Chapter 102 NPDES and air quality queue (including Wildcat Ridge in Archbald and Pennsylvania Digital One in Middlesex Township) are not bound by the GRID guardrails, a statutory gap corroborated by Lackawanna County Commissioner Bill Gaughan's October 21, 2026 hearing testimony."